Conservation Meeting
September 10, 2007
Present: Colin Cauldwell, Chair; Paul Boyden, Vice Chair; Carole Matthew; Joe
Mulkern; Cindy Ostrowki; Ben Monachino; Michele Grenier, Conservation an
Environmental Planner.
;ri~*;i!t~~~Jilg,; ....
~~~i~~.if:~P:~iJj.
!:"i~ff~gm~~l;i~ijijWfi.;:'.
Hearing started at 7:00 pm.
John Sullivan, Town Engineer and Mark Mitsch, Weston & Sampson project manager
were present.
Kingman Pond Dam is an earth embankment with a fixed weir concrete primary spillway
and a low-level outlet structure. The dam has been classified as a significant hazard
potential structure and is considered to be in poor condition.
Mark told the Commission the embankment has become overgrown with large trees and
brush and seepage has been observed along a good portion of the downside of the dam.
The vertical alignment of the embankment is inconsistent and several depressions were
observed, possibly caused by uprooted trees. Several animal burrows were also
observed.
The primary spillway is in poor condition with the concrete training walls cracked,
displaced, deteriorated and undermined. Mark said the spillway is significantly
undersized for current dam safety standards.
The low-level outlet is no longer operating. The intake structure for the low-level outlet
is a circular concrete manhole riser with a concrete slab roof. Water continually leaks
into the riser and out through the discharge pipe, which discharges uncontrolled below
the normal water level at the downstream right side of the existing primary spillway.
The dam rehabilitation design process consists primarily of identifying options for
spillway replacement to improve hydraulic capacity and identifying options for
improving the condition of the embankment while limiting the costs of the project.
Based on the April 2006 dam safety inspection, the Town of Mansfield, Engineering
Department proposes the following actions to be taken to address the deficiencies found
at the dam during inspection and evaluation.
· Design and construct a new, properly sized spillway system for the dam.
· Design and reconstruct the embankments to an appropriate crest elevation that is
coordinated with the spillway design. To improve hydraulic capacity.
· Develop and implement appropriate operations and maintenance procedures
consistent with the new design features of the dam.
Mark told the Commission Weston & Sampson has flagged the wetlands and have done a
survey base plan and hydraulic and hydrology studies.
Michele asked why the dam is being reconstructed instead of removing it. She said in
most states the dams are being removed and the Army Corps is giving the states money
for this purpose. Mark told her he first recommended the dam be removed but there are
issues with the removal.
Mark told the Commission the removal of the dam would be very simple; the concrete
structure would be removed, the water level in the pond would be reversed to a stream
and a wetland meadow. The problem is that when this has happened in the past the odors
(an organic issue) from the area are tremendous. By draining the water, the industrial
contamination in the sediment is exposed, creating more of a hazard to the public. If the
dam were to be removed, an evaluation of the environmental conditions of the sediment
would need to be done. If contamination were found, the town would become locked
into the Mass Contingency Plan, a 4 phase process for investigation and clean up. It
could even involve another level of bureaucracy; he said the town does not want to go
this route if it can be avoided. It is manageable now through the reconstruction of the
dam. A clean up of the hazardous waste would involve the EP A and potentially be very
costly to the town.
Mark gave as an example a dam removed in Dalton, MA. It was thought the removal of
the dam would cost approximately $50,000. The final cost to remove the dam was well
in excess of 5 million dollars because of industrial contamination.
Mark reviewed some of the design alternatives for the improvement of the dam; a
combination fixed crest weir with a stop log channel, deep sluice or low-level outlet,
similar to Fulton Pond Dam; small fixed crest weir and protected embankment and a
fixed crest weir system.
Mark told the Commission the combination fixed crest weir with a stop log channel, deep
sluice or low-level outlet is not suitable for this site. Because Kingman Pond is shallow,
a substantial amount of dredging in the pond would be required to create a suitably deep
upstream channel for a stop log channel or other low-level outlet to function effectively.
Regular maintenance of the channel, including occasional dredging, would be required to
prevent silt buildup in the channel. Sediment dredging in Kingman Pond is not
recommended since the pond is located on the Rumford River downstream from the
Hathaway Patterson Company site, which is on the EP A National Priorities List due to
environmental contamination. No action within Kingman Pond is required at this time
relative to potential contamination in the sediment. If this method for the reconstruction
is used, it is possible the dredged sediment may need to be disposed of as contaminated
material at a cost that could exceed the cost of the dam rehabilitation.
The fixed weir option involves replacing the existing spillway and low-level outlet
structure with a spillway system. However, if this method is used there is the potential
for flooding if the embankment is overtopped. Since private residences surround the
pond, an option that allows overtopping and flooding is not recommended.
A stepped fixed weir configuration is recommended for this site. The lowest step would
be set at E1.139.0, 0.2 ft above the lowest level of the existing weir and matches the
normal water level in the pond. A second step would be set at a higher elevation and
would act as an auxiliary spillway to discharge moderate to large storms. The auxiliary
spillway weir would have a crest elevation of El. 141.0 and would be 220 ft. long.
The width of the primary spillway weir would expand from 38 ft. be 90 ft. long. Mark
said this is a nice solution; it will keep the impact to the wetlands due to construction at a
minimum, dredging and disturbing the sediment in the pond would not be necessary and
operational/maintenance needs of the dam would be minimized. The disturbance to the
wetland resources would be less than 5,000 sq. ft.
This solution also keeps the project out ofDEP jurisdiction but more importantly, away
from the Army Corps of Engineers. The reconstruction will require a Programmatic
General Permit. The project is considered to be a Category 1, a "non-reporting" project,
and does not require a filing with the Corps. Mark said if the town is required to file with
the Army Corps, it could hold the project up for 6 months.
A low-level outlet is not considered necessary for this solution. Temporary pumping or
siphoning could be used in the unlikely event a drawdown is necessary. The low-level
outlet will remain in place to maintain the pond level at normal summer levels during
construction to reduce the cost of the project, additional costs incurred by the need for
construction dewatering. The existing low-level outlet will be sealed and abandoned as
soon as the project is completed.
Silt fence/hay bales will be installed along the limits of work and along the full length of
both sides of the site access way from Spring Street.
Embankment improvements would include removal of trees including their root systems,
regrading the embankment to a consistent crest level to limit the potential for erosion and
seepage through the embankment and protecting the upstream slope from erosion by
installing a turf-reinforcing mat. A drainage/stabilization system on the downstream
slope will be constructed if necessary.
There are several large sycamore trees on the dam and are shown on the plan as being
protected during construction with the intention that the Town would maintain these trees
even though it is generally not recommended that trees be allowed to grow on a dam.
Mark said Weston & Sampson would talk to the Office of Dam Safety about keeping the
trees but he feels they might require that the trees be removed. He explained that tree
roots loosen the soil on the dam. Mark said the removal of the trees and the root system
will be one of the most costly parts of the project. He told the Commission the
neighbors, when asked about the trees, said they would like the trees removed.
Mark told the Commission that tree roots are growing around the old stonewall on the
property and undermining it.
Paul wanted to know the longevity of the reconstructed dam. He asked what would be
the area most in need of assessment, the area most likely to deteriorate. Mark said the
life span of the reconstructed dam would be around 50 years. Mark said the area most
susceptible to deteriorate is the primary spillway, where you have significant water flow
and freeze/thaw conditions.
Cindy wanted to know if the sediment gets stirred up during a storm event. Mark told her
there is not much disturbance because the sediment is buried under water. Sediments are
not churned up during storm events or during normal operation of the dam.
Mark said the construction access way would follow the existing footpath from the gravel
parking area to the dam. On the plan submitted, Mark included a provision for a truck
wash area to clean the trucks of mud and dust before they re-enter onto Spring Street. It
should be set up in the existing parking area.
Cindy asked what the cost would be for this project. John said the cost would be between
$550,000 and $650,000. Paul asked ifthere were any grants to help reduce the cost. Mark
said there really isn't a lot of funding available anymore.
Michele asked when John thought the project would begin. He said the bids would go out
the end of October; all bids to be returned by November. It would then go to Town Meeting
in April 2008. Ifpassed at Town Meeting, John hopes the work can start in July 2008.
Paul made the motion to accept the plans for the reconstruction of the Kingman Pond
Dam as drawn, titled "For Permit Approval Only"and dated 8-14-2007, and any
amendment there of.
Cindy seconded.
Passed 6-0.
Mark told the Commission the plan still needs to go through a technical review within
Weston & Sampson. Michele asked that when the review is completed, if Mark would
make sure Conservation receives a plan of record, stamped and dated.
Hearing ended at 7:45 pm.
jj~'~m~~~~ti~~!9i~i.R~i~lm: ..',~t9~1~lt~;~~~"
:'~~;'~~m'~~Ji~~ri
John Sullivan wanted to make the Commission aware of the work on the underpass, even
though Mass Highway has indicated that no filing is necessary for this project. John said
maintenance repair or replacement of existing roadways and associated drainage is
exempt from the Mansfield by-law, provided the Conservation Commission is notified.
John told the Commission there has been a groundwater problem at the railroad
underpass for a number of years, more so in the winter months.
John said federal and state funding was secured a number of years ago. The improvements
include upgrading the existing drainage pump station and the existing underground
drainage discharge line adjacent to the railroad tracks. This drains into the Rumford River.
Existing pumps are not adequate. The existing18" gravity fed line will be replaced with an
18"force main (pump will create pressure to force water out). Spare pumps will also be
installed and also a new generator.
The design process is almost done and construction will start in 2008,
Paul, Ben, Carole and Cindy conducted a site walk at 4:30 pm today, September 10,2007
at 900 Maple Street and Map 40, Parcel 92.
Michele, Joe and Colin will walk the site tomorrow, September 11th.
Motion to approve the minutes of August 27, 2007.
Motion was made to adjourn at 8:15 pm. Paul/Joe
Next meeting will be October 15,2007.