HomeMy WebLinkAboutCapital Improvements Comm 03/22/2018Capital Improvements Committee Minutes
March 22, 2018
Present: Scott Feely, Chair and Michael O'Brien, Finance Committee; Joe Cerretani, Planning
Board; Steve Schoonveld, Board of Selectmen; Jenn Walsh, School Committee; Evan Epstein,
MBC
Kevin Dumas, Town Manager; Teresa Murphy, Superintendent of Schools; John Stanbrook,
Town Accountant; Shaun P. Burke, Director of Planning and Development; Jim Puleo, Deputy
Fire Chief, Lee Azinheira, DPW Director; Mike Ahern, DPW Special Projects Manager; Mark
Cook, DPW Highway Manager, Kurt Gaffney, Water Operations Manager; Marianne Staples,
Town Clerk; William Walker and John Brandt, Airport Commission
Minutes May 30, 2017
Motion: To approve as submitted (Cerretani-Walsh) All in favor. PASSES
Town Manager
Mr. Dumas explained the capital request for $340,000 for MIS, including $40,000 for website
design, $10,000 for maintenance (the first year will come out of free cash) and $300,000 for
phase 1 of financial software.
Mr. Schoonveld asked if there would be a competitive bid for the financial software and how
many phases it would include. Mr. Dumas said there have been meetings with Munis and
TylerForms. Mr. Stanbrook said they want to phase it in over time. Mr. Schoonveld said the
committee would need to know the full cost. Mr. Cerretani said there should be a five-year plan.
Mr. Feely said he thinks the committee needs more information and suggested putting it off a
year or meeting again. Mr. Dumas said he would like to have another meeting by the end of
April. Mr. Feely suggested using a placeholder on the warrant; Mr. Epstein said there should be
a ballpark figure.
Town Cleric
Ms. Staples explained her request for an 8'x25' election trailer, to be parked at DPW and used
for storage. The estimated $12,677 does not meet the definition of a capital request.
Planning Board
Master Plan will be removed from the Capital Plan.
Department of Public Works
Town Hall Chiller - $175,000 (reduced from $205,000)
Memorial Hall Improvements - $360,000
Plymouth Street Fire Station - $660,000
3/22/2018
Mr. Stanbrook explained the cost of borrowing is higher this year. Mr. Feely asked if the
proposed work on the Plymouth Street fire station would result in 20 more useful years; Mr.
Ahern said it would result in 20-30 useful years. Mr. Schoonveld said the short-term debt would
be $200,000 per year for five years on the fire engine and fire station.
Fire Department
Engine 4 - $660,000 short-term borrowing
Schools
MHS Bleacher Replacement — A two-phase request for $100,000 to cover contingencies. The
department already has $250,000 from revolving accounts.
DPW Highway
Salt Shed - $26,500 to cut trees and spread fill. Total cost of project will be $1.2 million.
Route 106 Design - $110,000 for 25% design for Copeland Drive/Route 106; total
design/construction to North Main Street will be $500,000.
Foolish Hill Storage Tank — not needed next year
Airport
The airport projects will be funded from three grants and 20% from airport enterprise account.
Mr. Schoonveld said he would like to see a three to five year plan for items #16, Route 106
Design/Oversight; #15, Salt Shed; #2 Town -Wide Financial System; #7 — Plymouth Street Fire
Station; and #8 — Memorial Hall
Placeholders will be prepared by March 28.
Motion: To a4journ at 7:15 p.m. (Schoonveld-Walsh) All in favor. PASSES