HomeMy WebLinkAboutConservation Comm 11/26/1984,- MANSFIELD CONSERVATION
( MONDAY, NOVEMBER 26, 19
MINUTES
PAGE ONE
Members Present: Chairman Durbano; Commissioners Benjamin,
Bonvie, Cheney, Graham, Rys and Sweet
The meeting was called to order at 7:32 p.m.
Minutes of October 15, 1984,
MOTION: To accept as written.
(Sweet -Graham; all in favor) VOTED
Minutes of October 29, 1984.
MOTION: To accept with one correction
and the suggestion that the amount
of pay .for Barbara Williams be
put into the minutes.
(Graham -Benjamin; all in favor) VOTED
Minutes of November.8, 1984.
MOTION: To accept and to incorporate
into the Minutes of October 29.
(Sweet-Bonvie; all in favor) VOTED
Correspondence
1. Bill from Bristol Office Supply for hole puncher and one
box of paper., in the amount of $11.08. This bill will be
voted on at the next meeting.
2. Payroll voucher for Barbara Williams for 27;2 hours, from
October 29 to November 26.
MOTION: To pay.
(Benjamin -Graham; all in favor) VOTED
?>, November 19 letter from Paul J. Folkman, The Folkman Company
to the Conservation Commission regarding the Morrow Street
Subdivision. Enclosed are Board of Health Plans for each of
the house lots.
4. November 13 letter from Kevin C. Grant, President, Mansfield
Little League to the Conservation Commission regarding the
Sweet Conservation .Sign. Mr. Grant stated that Little League
will bear the cost of a new sign to replace the original
damaged sign.
MANSFIELD CONSERVATION COMMISSION MINUTES
MONDAY, NOVEMBER 26, 1984 PAGE TWO
5. Memo from Town Manager Chad Maurer regarding information
received from the Board of Selectmen concerning an application
from the Conservation Districts of America for conservation
planning assistance. Deadline is December 15. Chairman Durbano
to fill out application.
6. Planning Board minutes.
7. Resources and Environment Newsletter.
Commissioner. Cheney brought to the
that the receipt on the last page
be filled out by the applicant and
prior to the commencement of work.
that the project has been recorded
The following motion was made:
attention of the Commission
of an Order of Conditions is to
returned to the Commission
This receipt is a record
at the Registry of Deeds.
MOTION: Receipt must be obtained by the
Conservation Commission from the
applicant for recording project
Pt the Registry of Deeds prior to
commencement of work.
(Sweet -Graham; all in favor) VOTED
Commissioner Graham asked if a letter was written to Kelton Potter
concerning the stream bed between Old Elm and School Streets.
Chairman Durbano stated a letter will be sent to Mr. Potter.
Commissioner. Sweet asked if a letter be sent to Denis Bonenfant
acknowledging his offer of land to the Commission to purchase
and to Mr. Sweet's phone conversation with Mr. Bonenfant. It
was mentioned that the Commission is interested in this land, but
at present does not have the available funds.
Telephone Calls
1. Mrs. Doreen St. Don, 483 Elm Street, called regarding a gravel
removal project adjacent to her property. She has if a member
of the Commission could take a look at the project. There are
some wetlands in the area. Chairman Durbano requested a. plan
from Bert Cook.
2. Mrs. Scott, Bristol at Mansfield, 18 Bonney Lane, called
regarding the stream behind the building is filled with
litter and she would like to have it cleaned up. It was
mentioned that this is private property. Chairman Durbano
stated that on inspecting the area he found that a cement
pipe was in the retention area. This pipe was asked to be
removed by the Commission sometime ago. A letter will be
sent to the owner of the property.
MANSFIELD CONSERVATION COMMISSION MINUTES
MONDAY, NOVEMBER 26, 1984 PAGE THREE
Wetlands Protection Act Hearing
Paul T. Thibault - File No. SE211-119
A Wetlands Protection Act Hearing was held on a Notice of Intent
dated October 25, 1984. Proposed work is within 100 feet of a
Bordering Vegetated Wetland. Filling of 1500 sq. ft. of wetland
and compensation will be done on Lot 5 to create a usuable lot.
A 200 -foot drain line will be installed. A copy of tie hearing
summary and hearing tape will be filed with the Town Clerk. This
hearing will be continued to December 10.
Wetlands Protection Act Hearing
Paul Lo Dico - Pile No. SE211-121
A Wetlands .Protection Act Hearing was meld on an Abbreviated
Notice of Intent dated November 6, 1984. Proposal is to construct
house and grade around mouse within the 100 --foot buffer zone.
A copy of the hearing summary and hearing tape will be filed wits
t'�e Town Clerk.
*See Page Four
sJetlands Protection Act Hearing
J. Brugliera Construction Co. -File No. SE211-122
A Wetlands Protection Act Hearing was held on the Notice of
Intent dated November 6, 1984. J. Brugliera Construction Co.
proposes to install a drainage system from Goward Drive down
Esser Street to Ware Street to discharge into the Canoe Rive^.
A copy of the hearing summary and hearing tape will be filed
with the Town Clerk.
Order of Conditions - Pile No. SE211-120
Mansfield DPW - Regional Interceptor
The Order of Conditions was written for the Department of Public
Works Regional Interceptor. They are as follows:
1. A plan shall be submitted to the Conservation Commission,
depicting the method to be used for construction of the
sewer main through the Rumford River, prior to commencement
of work, i.e., pumping around or separate channel.
2. Plan of crossing the Rumford River shall include method to
be used fo-r siltation control.
3. General. Conditions, No. 8, shall be completed before work
commences (see page two Motion regarding receipt for recording
project at the Registry of Deeds).
MANSFIELD CONSERVATION COMMISSION MINUTES
MONDAY, NOVEMBER 26, 1984 PAGE FOUR
MOTION: To issue the Order of Conditions
as written.
(Bonvie-Graham; all in favor) VOTED
Commissioner Cheney reminded members to view the Travers drainage
ditch at Tremont and Williams Streets. She is concerned because
fill is being removed and not sure if there is a wetlands on site.
Chairman Durbano mentioned a phone call was received .crom C,irs. Jean
Woodland, 172 Old Elm Street regarding filling adjacent to her
lot. She is concerned it may cause more problems on her property.
Members of the Commission are to view this site •also.
MOTION: To adjourn at 10:55 P.M.
(Sweet -Cheney; all in favor) VOTED
The next meeting of the Conse:cvation Commission is December 10.
Date to Town Clerk:
CC:bjw
*Two bids were received for the plan and field surveying of the
Jackson/Gonsalves property. RIM Engineering submitted a bid of
$3,600; Dunn Engineering submitted a bid for $5,155
MOTION: To accept the lowest bid from
RIM Engineering.
(Sweet -Benjamin; Bonvie abstained) VOTED