HomeMy WebLinkAboutMBC 09/25/1990a
MUNICIPAL BUILDING COMMITTEE
SEPTEMBER 25, 1990
90 OCT 10 F 4t 07
Present: MBC- S. MacCaffrie, E. Giordano, G. Wurphy, E°. Guardabascio
L. Amoruso, A. Micheli
Attendees: HMFH- J. Miller, R. Juusola
Dr. Warren, R. Gurek
Meeting called to order at 7:30 PM
Three bids for Library landscaping went to Town Counsel. They are
now in Town Manager's hands for action.
Motion made by LA seconded by AM to pay A.J. Robicheau requisition
#2 in the amount of $47,401 for work at Qualters School. VOTED 4-0.1A&A
S. MacCaffrie stated that A.J. Robicheau manpower is unacceptable.
Mansfield School Dept. has been "helping them" when necessary.
Requested that A.J. Robicheau give a completion date no later than
three weeks from today.
Read letter from Palmer & Dodge stating that they are ready to
issue bonds by the Town of Mansfield for $19,800,000.
Read letter from DEQE accepting dual fuel boilers.
Read letter from Corcoran & Jennison dated September 10, 1990 to
HMFH (faxed to SM on 9/11/90) asking for a two-week bid extension
for file sub bids and general contractors'. SM called RJ and asked
if any file sub -bidders called and asked for more time. RJ stated
there were none that he knew of. SM then asked RJ to tell Corcoran
& Jennison to continue bidding according to the present schedule.
SM inquired as to how many GC's were bidding as of that date. RJ
stated six. On 9/18/90 SM asked RJ for a list of GC bidders to
update the MBC. This list was faxed to SM on 9/18/90. Prior to this
SM had no knowledge of GC bidders. Corcoran & Jennison did not take
out plans until 9/17/90. Sciaba Construction (SM's employer) took
out plans on 9/18/90.
SM read a letter dated 9/25/90 to HMFH from Corcoran & Jennison
signed by David K. Rosen, President. It stated that they will file
a complaint with the Dept. of Labor & Industries if bid period is
not extended two weeks. They feel that due to the fact that SM works
for Sciaba Construction, Sciaba has an unfair advantage because plans
could have been in Sciaba's hands for many months. SM stated that
he does not estimate for Sciaba. He has been a Project Manager with
them since 8/13/90. SM requested that JM reply to Corcoran & Jennison
based on facts and information presented tonight.
Read letter stating that R. Gurek has resigned from the MBC because
he moved to Norton and is no longer a Mansfield resident. Motion
made by EG seconded by FG to make R. Gurek an adviser to MBC. VOTED 5-0
Voted 5-0 to accept meeting minutesA dated August 28, 1990.
Forwarded six resumes for Clerk of the Works position to Town
Manager. MBC asked for three back for consideration.
Reviewed file sub -bids. Rubin Glass was rejected because their bid
form was incomplete. Savings on file sub -bids totals approx. $2.million.
Authorized HMFH to send out RFP's for inspectional services (concrete,
steel, masonry, roofing). McPhail will do soils testing.
Next meeting scheduled for October 2, 1990 7:00 PM at Town Hall.
Meeting adjourned at 9:50 PM.