HomeMy WebLinkAboutMBC 05/28/1996f MUNICIPAL BUILDING COMMITTEE `� ;` 17
MINUTES
MAY 289 1996
MEMBERS PRESENT: William Antoine,Lawrence Carpenter, Richard Feeley,
James Liddick, David Young, William Williams, Amos Robinson
MEMBERS ABSENT: Judith Scott, Edward Sliney, Andy Gazzolo
GUESTS PRESENT: Don Walter - Strekalovsky & Hoit, Lt. Walter Crickard -
Police Dept. Norman Mahana
THE MEETING OPENED AT 7:00pm IN ROOM 101 MANSFIELD HIGH SCHOOL
MINUTES: The Minutes of 5/21/96 were submitted.
MOTION: To accept as amended (LC/JL) 4-0-2 (WW,WA)
INVOICES: The following invoices were submitted for payment.
?! 1�TAQR PCtOI[Gx AMACIriT1 4P1?Xt0AL
L.Bartolini Clerk-Town Hall' 2,300.00 WA/LC 6-0-0
Summer & Dunbar DPW-West Mansfield 350.00 hold
Morse Sand & Gravel DPW West Mansfield 265.00 hold
Consi i Cons. West Mansfield Fire 55,950.15 " RF/BA 6-0-0
Consigh Cons. Town Hall 112,020,23 LC/JL 6-0-0
The committee reviewed the bills from DPW The MBC discussed the need to meet with
Mr. Clifford in regard to the DPW work.
The structural review of the anchor bolts and other issues were discussed.. Strekalovsky
and Hoit will send a written response to the Building Inspector's Office.
Member Carpenter gave an overview of the construction meeting. Several issues
concerning the HVAC system were reviewed. There was a tow of the facilities to observe
the items that were discussed. The meetings will be held weekly until the outstanding
items have been addressed.
Member Carpenter discussed the installation of the electronic door openers in the
connector building.
The committee also reviewed the R Factor of the installation on insulation in the wall in
the Town Hall.
The need for timely submittals was stressed to the Architect.
MBC Minutes - May 28, 1996 1
CORRESPONDENCE:
GENERAL
•
A letter to M. Codianne, Consigli fiom B. Cook (CC:MBC) RE: notification ofwork.
•
A letter to R. Hoit from D. Young RE: Status Report
•
Letter of transmittal from MBC to List RE:\Review of Payment Requisitions Town
Hall - W. Mans. Fire Station.
TOWNHALL
•
A memo to W. Williams from D. Young RE: Keying Schedule - Town Hall
•
A letter to R. Hoit from D.Young RE: Keying Schedule.
•
A memo to W, Williams from D. Young RE: Computer Room (approved by TM)
•
A memo to W. Williams from D. Young RE: Roof Hatch (waiting for electrical
inspectors review)
•
A memo to W. Williams from D. Young RE: PCO: Windows -'First Level
•
Transmittal from Strekalovsky & Hoit RE: Elevator Color Schedule -The Committee
asked for a full color submittal for;the Town Hall. The MBC reviewed the color
submittals for the frames for the elevator. The frame issues need to be resolved. 'The
connector will be boysenberry. The MBC discussed the status of the rug
manufacturer. The Committee put the color decision on hold until the other colors
have been submitted. S&H will send a letter.
•
A letter to D. Young from R. Hoit RE: Drawing of Structural beams
•
A letter to R. Hoit from G. Burns (CC:MBC) RE: HVAC
WEST MANSFIELD FIRE STATION
•
A letter to D. Young from R. Hoit RE: Approval of .6 mil polyethylene vapor barrier
SCHOOL PROJECTS
•
A letter to W. Williams fiom D. Young RE: Permitting Issues - Robinson School
•
A memo to D. Young from R. Goddeau RE: Roofing Survey Proposals (2 submitted)
The Committee reviewed this and will research the status of the warranty issues. R
Goddeau will be invited to the meeting of June Il, 1996, to discuss the remaining
items associated with the close out of the Jordan/Jackson School.
CLERK'S REPORTS
•
Minutes Job Site Meeting 5-14-96 - Strekalovksy & Hoit
•
Weekly Reports 5/13/96 and 5/20/96
•
Daily Reports Town Hall and West Mansfield Fire Station Projects: 5-17 through 5-
24-96.
(*8:10 L.Carpenter left meeting)
MBC Minutes - May 28, 1996 2
(` POLICE STATION:
A strategy meeting was held with the Police Chief, Town Manager and Strekalovsky and
Hoit. D. Walter discussed the meeting. The Chair had asked for the bids to be reviewed
versus the costs estimates. This was not submitted. It would have been helpful to help set
priorities. The MBC asked for this item to be addressed. For example, precast cells vs
block construction on the cells -, cost comparision bid prices vs estimates.
Reviewed Project Scope:
Division 1- General Requirements
• Work Sequence/Phasing
* ' Project Start-up Immediate, Not one year delay
* Police Operations Move from existing station
* Dept. of Corrections Complete Finishes (i.e., painting, flooring, ceilings,
doors, etc.)
Discussion: Station could move in Oct/Nov for, approximately 8 weeks - Dispatch could
be run from the Fire Dept. - could have reciprocal agreements for use of cells. Use of
Dept. of Corrections clients being handled by the Chief, concern was expressed over the
use of two contractors on site, prevailing wage, possible meeting with Dept. of
Corrections with NMC - need to address jurisdiction issues, and schedule) ;
Division 2-Sitework
1 • Eliminate Access Road
• Eliminate Stone Car Wash Pad, locate in Sallyport
Reduce Amount of Demolition
Discussion: The access road has already been eliminated, there are drains in the sally
port area, look at materials and areas to be salvaged, relocate plumbing to basement for
cell piping
Division 3 - Concrete
• N/A at this time
Division 4 - Masonry
Modify scope of Masonry Work
Discussion: use of precast cells vs built in place cells -compare costs
Division 5 -Metal '
Modify Scope of Structural Steel and Miscellaneous Metals
Discussion: review the openings in Sallyport area - put support columns in center or
decrease opening size
Division 6 -Wood and Plastics
• Modify Scope of Architectural Woodwork
Discussion: Use of Plastic Laminates vs Red Oak
Division 7- Moisture Protection
• Modify Flat Roof Membrane Scope
(' Discussion: Review of Costs - appeared to be very high bid prices, HVAC issue to pl
ceiling height. Roof presently leaks into vault area. 4
MBC Minutes - May 28, 1996 3
Division 8 -Doors and Windows
• Save Existing Solid Core Wood Doors and Re -Use
• Review Exterior Windows
• Review Bullet -Proof Glass
Discussion: Add bid clarification on exterior windows, review specification - comments
were received from bidders on dispatch area.
Division 9 - Finishes
• House of Corrections Complete Finishes Work (Veneer Plaster, ACT, Resilient
Flooring, Carpeting, Epoxy flooring, Painting)
Discussion: Ask Chief to have representatives from Dept. of Corrections attend a MBC
meeting.
Division 10 - Specialties
Review all Specialty Items
Division 11 - Equipment
• Modify Design, Quality and Location of Pre -fab Detention Cells
• Modify Crime Lab Equipment
Discussion: review current cell area, upgrading use and add additional cells, review
floor layout, compare block construction prices vs prefab cell prices, prices on the photo
lab appeared to be on the high side - review need with Chief.,
Division 12 - Furnishings
• Review Blinds
Division 13 - Special Conditions
Not used
Division 14 - Coneling System
• Review Wheel Chair Lift
Discussion: Variance for a two stop lift has been obtained -copies to be forwarded to S
&Hfor review
Division 15 -Mechanical
• Review/Modify Fire Protection, Plumbing and HVAC
Discussion: review scope of mechanical with TCI, Inc.
Division 16 -Electrical
• Modify TV Surveillance, Door Card Access Controls and Intercommunication
Systems
Discussion: reviewed access modification, and door card access requirements
The MBC asked the Town Manager for a management programming decision on the
location ofMEMA. The Town Manager stated that the MEMA office be relocated to the
main level. The Town Manager stated that MEMA only needs a room in the vicinity of the
Central Dispatch. Federal Funding can only be used for MEMA - a portion of all other
items can be prorated. Can Federal Funds be used for the installation of the elevator to
access the MEMA office where it is presently located?
MBC Minutes - May 28, 1996 4
It was the consensus of the committee to move forward with the construction budget
amount of $850,000. We may have to explore the possibility of phasing. We asked the
Police Chief to set priorities for example: Cells, sally port - detention area,
communications. Discussed the sale of the Paine School RE: endorsement of prior vote.
This issue will have to be forwarded to the Board of Selectmen for their presentation at a
Special Town Meeting.
CABLE TV - has requested space, This programming issue needs to be resolved.
The MBC is scheduled for the Selectmen's meeting on 6-5-96. The committee reviewed
the issues for BOS needs for Policy Decisions and cost items for West Mansfield Fire
Station to complete as a final package.
JUNE 18th - Next municipal project meeting- Police Station items to be completed are
Conceptual Plans, cost issues vs. bid prices, items addressed as discussed - development of
a project schedule.
The Chair discussed Records and Ethics informational seminar put on by the Town
Manager.
ADJOURNMENT:
MOTION: To adjourn at 10:50PM. (Liddick/Feeley) Unanimous
Respectfully submitted,
Maureen R Doherty
Secretary
Signature of Cluir Date
MBC Minutes - May 28, 1996 5