HomeMy WebLinkAboutMBC 11/05/1996MUNICIPAL BUILDING COMMITTEE
NOVEMBER 5, 1996
MINUTES
MEMBERS PRESENT: Bill Antoine, Lawrence Carpenter, Richard Feeley, David Young,
James Liddick , Ed Sliney, Andres Gazzolo.
MEMBERS ABSENT: Bill Williams, Judith Scott
GUESTS PRESENT: Lou Bartolini, Bill Madan, Steve MacCaffrie, Alec Simonelli, Don
Walter, Ron Ashton, Walter Parker, Leo Sciarappa.
MINUTES: The minutes of the October 29, 1996 meeting were reviewed.
MOTION: To accept the minutes of October 29, 1996 as amended by
members Young and Liddick (Carpenter/Liddick) Approved 4-0-0.
INVOICES: J. T. Callahan Pay Req 1 $47,450
CORRESPONDENCE: General
Transmittal from R. Hoit - West Mansfield Fire Station - Fire protection system test certificate.
Request For Information (RFI) No. 1 from J. T. Callahan (Callahan)- Robinson School - Need
for owner to provide on-site survey benchmarks.
RFI No. 2 from Callahan regarding responsibility for temporary utility service expense.
A memo to Ron Ashton from Bob Gurek regarding coordination of the Gas Service into the
Robinson School.
A memo from Bill Williams to the Board of Selectmen - Robinson School Construction Contract
award to J. T. Callahan.
A memo from Dan Clifford to Bill Williams regarding notice of date for town hall move - needs
date to list in acquiring moving services.
A memo from Dan Clifford to Bill Williams regarding notice of a date for final wiring to be
performed by the telephone company at the town hall.
WEST MANSFIELD FIRE STATION
Punch list prepared by Strekalovsky & Hoit distributed and discussed. The following items
were added by the various members:
1. silt fence needs to be repaired in certain areas
1��
2. concrete needs to be patched on the pumping station surface
3. concrete needs to be removed from the pumping station hatch cover
4. some switch plates inside and outside are still missing
5. rake out loam as well as mulch from next to siding
6. fill nail holes better at front entrance
7. address fire rating issues regarding penetrations in electrical room
8. install appropriate pipe sleeves in mechanical room
9. verify that apparatus bay floor had appropriate concrete sealer applied
10. review apparatus bay door power cords for correct restraint
11. seal pipe penetrations in apparatus bay wall to staff building
12. check vinyl siding for correct clearances at front entry - weather tight
13. fix hole in wall of far cube in mens dorm
14. wire apparatus bay louvers
15. label switches in apparatus bay for function
16. missing light fixture cover in mens locker room
17. finish final cleaning - excess wax on floors, windows, litter on perimeter
Lou Bartolini reviewed the status of the building inspections: electrical, fire alarm, sprinkler
system are all passed; mechanical is almost done and plumbing is temporary. Target is to have
all code issues addressed by Consigli for building department to issue a certificate of occupancy
on Wednesday. Don Walter is working on getting all required affidavits submitted and the
certificate of substantial completion issued.
TCI has issued a punch list for mechanical items which needs to be reviewed. Chief Sliney
submitted a list of items he would like to see addressed as well. Larry Carpenter asked that the
roof be inspected one last time as well prior to release.
The committee stressed the need to have all as-builts reviewed prior to submitting the next
Consigli requisition. Operation and maintenance manuals must also be in hand.
All agreed that the fire department could move their furniture in on Wednesday 11-6-96 but that
actual occupancy would rest with receiving an official occupancy permit.
Communications tower installation is being arranged through Ed Sliney and is budgeted for
about $500.
TOWN HALL
Project meeting to address the window issues was held. Consigli and Lockheed appear to be in
agreement with the required revisions and have agreed that they own all costs. Therefore
recommended Stekalovsky and Hoit (S&H) revisions will be implemented. Larry Carpenter
requested that S&H issue a formal written agreement and Rich Feeley asked that S&H issue a
plan with it that indicates what is to be done at each window. Don Walter agreed these would be
done.
z%
General discussion on the South Main Street entrance sidewalk and its poor condition.
MOTION: To authorize Consigli to remove the existing South Main Street
sidewalk entrance and replace it with a new concrete one of similar size for an
amount not to exceed $2000. (Carpenter/Feeley) Approved 5-0-0.
Request of S&H to final all outstanding change orders for fire station and town hall to be acted
upon at the next MBC meeting.
Lou Bartolini updated the project status of the other trades. CAM is catching up and has been
staffing the project with 6 plus people daily. Electrical subcontractor is falling behind now.
S&H to send appropriate letters expressing concerns to them, Consigli and DCPO. Will call a
project meeting to review issues if need be.
Expect final paving in about a week. Wood fence in parking lot being installed. Request to
have all building repointing checked and done prior to cold weather. Lou B. and S&H to
coordinate.
POLICE STATION
Update on design status at next MBC meeting.
ROBINSON SCHOOL PROJECT
The first project meeting was held on Monday November 5, 1996. Ron Ashton provided a brief
overview of that meeting. Also the construction contract has been signed and the official
completion date is April 27, 1998.
Ron Ashton and Walter Parker are working on getting the property line and survey benchmarks
resolved by obtaining the required information from HSI who did the most recent survey.
The gas line installation will be coordinated with all appropriate parties and Bob Gurek will
notify the gas company of our desire to have it installed.
The ground breaking ceremony will be coordinated by Jim Liddick with the School Committee
and school staff. All agreed a Saturday morning would be best and a potential date is November
23, 1996.
All project correspondence from project meetings should go to attendees, the MBC, Building
Dept, Fire Dept., Town Manager, School Superintendent, and Project Coordinator. All RFIs
should be addressed to Keyes Assoc.
Jim Liddick has reviewed three proposals for material testing firms provided to him from Keyes
Assoc. Costs for each are similar. Jim has checked references for all and recommends Haller.
MOTION: To authorize Keyes Assoc . to subcontract with Haller Testing to provide
(` material testing services for the Robinson School project (Carpenter/Liddick)
Approved 5-0-0.
Ron Ashton has received and reviewed a schedule of values from Callahan along with their first
pay requisition. He recommends approval of both. The requisition is mainly for the contractors
bond costs on the project. General conditions will be billed on a percent of completion basis.
MOTION: To approve Callahan Pay Requisition No. 1 in the amount of $47,450 and
the associated preliminary schedule of values (Carpenter/Antoine)
Approved 5-0-0.
Keyes Assoc. will be working on processing change order no. 1 to address the filed subbid
amount errors and to address the value for the missing ADA hardware. Callahan will be directed
to provide pricing on the asphalt shingle roof alternate.
Steve MacCaffrie from Callahan distributed a preliminary phasing plan and schedule for
discussion. He reviewed their methodology behind the plan. A four phase plan is being
evaluated. Several suggestions to revise the plan were made. Leo Sciarappa stated he is willing
to put up with some reasonable hardships in order to help get the project done earlier but that
some things will be difficult to accommodate. The most difficult issue would be to ask teachers
to move their rooms multiple times during the construction time. Potentially acceptable items
might be having students eat in classrooms for a short duration of time or to close specific
bathrooms etc. A request to have the phasing plans done on the actual design plans was made so
that it is easier to review and coordinate.
Callahan will revise the phasing plan and bring an update version based on input received to a
future meeting. Site offices trailers will be on-site within a couple weeks. Building permits have
been filed for and site work on the revised bus loop may start within the week.
Walter Parker's contract was signed and he is officially on board.
MOTION: To adjourn at 10:30 p.m. (Carpenter/Feeley) Approved 4-0-0
Respectfully submitted,
David F. Young
Signature of Chair / y / Date of Acceptance - Vote