HomeMy WebLinkAboutMBC 06/11/1996MUNICIPAL BUILDING COMMITTEE
MINUTES
JUNE 119 1996
�CIJi�+'.
a,
[ To'
MEMBERS PRESENT: Lawrence Carpenter, Richard Feeley, James Liddick, David
Young, Emil Giordano, Donald Nicoletti
MEMBERS ABSENT: William Antoine
GUESTS PRESENT Rick Goddeau - Manager, Buildings and Grounds MPS,
Leo Sciarappa- Principal - Robinson, Pete Noll - Sun Chronicle, George Dainis and Jean
Miller - School Committee, Bob Gurek - Business Mgr. - MPS, Jim Higgins - Youth
Basketball, Larry Gannon, Dan Freeman and Ron Ashton - Keyes Associates
The Minutes of May 28, 1996 were submitted for review.
MOTION: To approve as amended. (Feeley/Liddick) 3-0-1 (Carpenter)
INVOICES: The following invoices were submitted for payment.
ENDOIS
Sumner & Dunbar
Y'ROJECT
W. Mans, DPW
AMOUNT
350.00
VOTE
RF/LC 4-0-0
Morse Sand & Gravel
W. Mans. DPW
265.00
RF/LC 4-0-0
Folan's Presc. SILoppe
MBC Supplies
7.13
RF/LC 4-0-0
W.B. Mason
MBC Supplies
139.77
LORF 4-0-0
M. Doherty
Payroll - May
$1,179.61
LORF 4-0-0
L. Bartohm
Pa o115-25-6-7-96
2,300.00
LC/RF 4-0-0
Fas rint
JJ - (roof hoto's)
12.00
LC/RF 4-0-0
Budget Reports - MBC Clerical and MBC Office Supplies - May 31, 1996
West Mansfield Fire Station - May 31, 1996
Town Hall - May 31, 1996
CORRESPONDENCE:
General
• A memo to all departments from L. Gallagher - RE: End of Year Encumbrances
• A memo to all Boards and Committees from T. Pereira RE: Selectmen's Meetings
• Memos to All Boards and Committees fiom W. Williams RE: Town Meeting
• Emergency Procedures - Town Hall and West Mansfield Fire Station
• A memo to D. Whitehead from M. Doherty - MBC Guest Column - June
• A memo to all Boards and Committee from W. Williams RE: Water Policy
MBC Minutes 6-11-96 page I
• A memo to Board of Selectmen, W. Williams from D. Young RE: Capital Plan Update
and Budget Report
• A memo to R. Button -MEMA from D. Young RE: 6-18-96 Meeting
• Memo to Payroll from D. Young & W. Williams -yearly increase -secretarial
Town Hall
• A letter to G. Burns from R. Hoit RE: Response to questions by Consigli - Chairman
Young, has concerns with the lack of patching, members carpenter and Feeley feel
that the holes do not have to be patched. With the duct work being installed, there is
little air penetration in this area.
• A letter to G. Bums from R. Hoit RE: wall board and soundproofing. Member Feeley
stated that Consigh had a problem with the soundproofing going above the hung
ceiling line. There was a question about the envelope insulation.
• Statement of Facts from the ZBA RE: Town Hall Appeal
Schools
• A letter to R. Goddeau from A. Marin RE: Snow Guards - JJ - Snow guards are not
completely installed
• A letter to. B. Cook & S. Burke RE: Permit Issues -No response from B. Cook
• A memo to D. Young from S. Burke RE: Permit Issues - Robinson School
• A letter to D. Young from D. Freeman RE: Robinson Start -up costs
Field and Clerk Reports
West Mansfield Fire Station:
Project Submittal Log - 5/20/96
Anchor Detail Clarification 6/3/96
Shop Drawing - lightgage metal 6/4/96 (Concern with the slab not being true.)
Concrete Test Reports 4/24,26/96, 5/24/96
Clerk Reports 5-28-96 - 6/7/96
Mansfield Town Hall
Project Submittal Log - 5/20/96
Concrete Test Reports 4/22/96
Clerk Reports 5-28-96 - 6-7-96
Member Feeley gave an update on Construction meeting. Consigli will be invited on the
6-25-96, meeting to discuss the project schedule for both rraeeti;gs d
West Mansfield Fire Station: concerns were discussed with the header breaks being
located over the windows, and the costs and labor associated with the installation of the
plywood around the perimeter of the fire station.
Town Hall: concems with the installation of the ductwork, and the leveling of the floors
in the comer offices of the first level. Member Carpenter stated that the floor material was
MBC Minutes 6-11-96 page 2
a visible known condition and the cost of leveling should have been factored into the bid
price.
The color scheme for the W. Mansfield Fire Station was reviewed. The Committee will
ask the architect to submit a rendering of the colors so that we may have them reviewed
by the Fire Chief and the Town Manager.
SCHOOL PROJECTS -
Jordan/Jackson:
Mr. Rick Goddeau - Director of Buildings and Grounds gave an update on the snow
guards and reviewed photos of the roof conditions at the Jordan/Jackson Elementary
School Complex..
The MBC will wait until they receive all the roof proposals before they make a decision.
General Electric (GE) will replace the bulbs in the hallway lights the ballast are also
manufactured by GE . Suggestions were made to replace the ballast or to ask GE to
replace. Mr. Goddeau was asked to write to the company and notify them that this
condition of the light bulb burn out may be due to a non -compatible ballast and ask them
to confirm that these the items are compatible.
The Committee briefly discussed the status of the well installation at the Complex. DPW
will be handling this. The Committee will ask the DPW Director for a status report.
Capital Plan School Projects:
Mr. Ron Ashton suggested that Keyes and Robinson School staff and MBC project
representative should have a meeting to discuss any items as there was a change in
personnel from when the school was originally designed. The site issues were discussed.
The walkway near the wetlands may need to be reviewed by the ConCom.
The schedule was reviewed. The Committee was concerned over the actual construction
start-up date. It was the consensus of the Committee that the bid schedule was acceptable,
there may be some minor modifications.
Discussed the Chapter 60 work in relation to the Robinson School; lighting renovations,
domestic hot water, energy management system and water conservation measures are the
items that will be addressed.
The Committee reviewed the Safety Concerns with the Principal of the Robinson School.
There was a meeting scheduled for Friday -June, 14, 1996 and several items that were on
Mr. Sciarappa's list can be addressed at that time.
There was a discussion concerning the start-up costs associated with the project and the
Committee reviewed reactivation fee request. Discussed the process used to determine the
MBC Minutes 6-11-96 page 3
fee. Committee made comments such as the price was higher than what was anticipated.
Discussed reasons for charging interests, Chairman Young feels that the reactivation fee is
reasonable. �{10 r, cull +he
MOTION: To authorize the Keyes to reactivate the project with an all
inclusive start-up fee of $25,000.00 (Carpenter/Feeley)
discussion: concern was expressed with definition as back-up for the invoice Questions
were asked in regard to the reactivation fee with the QMS and MHS. Members Giordano
and Nicoletti asked that no other fees for reactivation fees be associated with these
projects. Member Nicoletti voiced strong opposition to the implementation of any other
fees it and stated that this should be resolved now. Member Carpenter wants to keep
moving forward - and set-up another meeting to resolve the financial issues. Costs will be
forwarded to the MBC prior to the June 18th meeting. Motion was withdrawn.
Mr. Dainis, School Committee commented on the costs of start-up and close -down.
MOTION: To adjourn the meeting at 10:22PM (Carpenter/Liddick)
Unanimous
Respectfully submitted,
Maureen R. Doherty -
Administrative Secretary
Signature o Chair
Date of Acceptance - Vote
MBC Minutes 6-11-96 page 4