HomeMy WebLinkAboutMBC 06/25/1996MUNICIPAL BUILDING COMMITTEE
JUNE 25,1996
MINUTES
C,-_
''_ ; . 4;
MEMBERS PRESENT: William Antoine, Lawrence Carpenter, Richard Feeley,
James Liddick, David Young, William Williams, Andres Gazzolo, Judith Scott, Emil
Giordano, Donald Nicoletti
MEMBERS ABSENT: Arthur O'Neill, Edward Sliney
GUESTS PRESENT: Chris Marion Asst. to the Town Manager, Norman Mahana
Selectman, George Dainis - School Committee, Anthony Consigli, Greg Burns - Consigli
Construction Corp., Roger Hoit - Strekalovsky and Hoit, Frank Monti, Adam Petronio -
CAM HVAC, Louis Bartolini - Clerk of Works, Ron Ashton - Keyes Associates, Robert
Mangiaratti - Town Counsel, Burton King - Brockton Enterprise,
MINUTES: The Minutes of June 18, 1996
MOTION: Approved as amended. (Antoine/Liddick 4-0-1 (Antoine))
The following invoices were submitted for payment
Consi ' Cons. Co.
I Town Hall
1224,175.18
WW/WA 6-0-0
Consi h Cons. Co.
W. Mans. Fire
40,879.57
LC/WA 6-0-0
Maureen Doherty
June Payroll - MBC
1,149.86
RF/JL 3-0-0
Louis Bartolini
Clerk Payroll
2,300.00
WA/JL 5-0-0
CORRESPONDENCE:
General
• A memo to MIIA Members RE: Reporting Claims - FY 96
Municipal Proiects
• A letter to A. Consigli from D. Young RE: Outstanding items for projects
• A letter to A. Consigli from B. Cook (FYI:MBC) RE: Outstanding items for projects
• A memo to D. Young from E. Sliney RE: Removal of Window - W. Mansfield
(approved by W. Williams)
• A memo to W. Williams from L. Fish RE: Request for window in recreation office
(approved by W. Williams)
• A letter to P. Detrolio fiom W. Williams RE: Invitation to meeting
• A letter to K Mangiaratti from W. Williams RE: Keyes - School Projects
• A letter to R Mangiaratti from W. Williams RE: Keyes - School Projects - Meeting
MBC Minutes - 6-25-96 Page 1
• A memo to W. Williams from R. Mangiaratti RE: Keyes -School Projects -Meeting
( • A letter to R Mangiaratti from M. Doherty RE: Information request - Keyes
• A fax to D. Freeman from M. Doherty RE: EFB application
• Meeting minutes from TCI RE: Chapter 60 meeting
Clerk's Reports
• Town Hall - 6-17 - 6-21-96
• West Mansfield Fire Station 6-17 - 6-21-96
Reviewed draft memo's concerning West Mansfield Fire Station site issues, and request
for prices to complete work.
MOTION: To approve draft memos and send to architect. - (Antoine/Liddick)
5-0-0
(7:15 - A. Gazzolo arrived)
The Committee held a discussion with Consigli, CAM HVAC, Strekalovsky & Hoit to
resolve the outstanding items on the West Mansfield Fire Station and the Mansfield Town
HallProjects.
(7:25 A. Consigh and G. Burns arrived)
West Mansfield Fire Station:
The Committee, Architect and Representatives from Consigli reviewed the letters from the
MBC and the Building Office in regard to outstanding issues.
• Approved shop drawings on wood joist framing
• Approved shop drawings on exterior sheathing
• Approved drawing SK -1 - needs architects stamp
• Metal stud framing - questions on fastening and concern with the way it
sits on sill plate (Lightgage metal stud shop drawing)
• Approved shop drawings on remedial anchor bolt fastening
• Additional bids for installation of sprinkler system
• Project schedule reflective of actual work being performed
• Concern that the contractor is not following procedure as set forth in
the specifications and in accordance with the plans.
Discussion on the above mentioned items occurred, it was the consensus of all in
attendance that the items should be forwarded to the Building Inspectors Office as soon as
possible (Consigli stated that most items can be forwarded by the end of this week) R.
Hoit will have to issue an affidavits to certify any changes that have occurred.
MBC Minutes - 6-25-96 Page 2
(7:40pm - N. Mahana arrived)
Consigli is not unwilling to do the requested paperwork. Consigli noted that the Building
Inspector's Office should contact, the Superintendent, then to the Project Manager, then
the owner of the Company. The Asst. Building Inspector presently is speaking with the
subcontractors on the job as well as calling the structural engineers and other project
related professionals, this has resulted in some confusion on what needs to be submitted.
(7:55 R. Feeley arrived)
Sprinkler system prices - Two additional prices are needed and will be submitted by
6/28/96.
Project Schedule: updated June 17th - the schedule is fluctuating due to personnel shifting
from the Town Hall to the West Mansfield Fire Station
There will be no problem to be completed by September. Vinyl will be installed, roof
installed, and windows done by the end of July.
Member Liddick asked if there are any items that need to be submitted. Consigli and R
Hoit believe that all major items are done.
(8:05 - R. Mangiaratti -G. Dainis arrived)
TOWN HALL
• CAM HVAC -RESOLUTION
• Approved shop drawings and samples of plaster - detail on corner beading
• Approved shop drawings for ductwork coordination
• Approved shop drawings and samples on brick, color and stone
• Installation of mechanicals
• Carpet manufacturer - prices for change from 32 ounce to 26 ounce carpet
• Project schedule reflective of actual work being performed
• Concern that the contractor is not following procedure asset forth in the specifications
and in accordance with the plans.
The Committee and representatives from CAM HVAC discussed the documentation for
layout and coordination for the HVAC sheet metal and piping work, There were some
questions on the coordination of other subs concerned with this installation. Roger will
stamp the submitted drawings. The drawings were submitted to Consigli - for
coordination.
One issue was the duct work - the other was the equipment, this is a concern with the
design and the credit issue. TCI has approved all the work. This may be an issue for the
mechanical inspector. The Town Manager asked when this can be submitted to the
MBC Minutes - 6-25-96 Page 3
mechanical inspector. - should be submitted within two days. There was a question as to
whether the shop drawings will be signed and stamped by the Engineer or TCI. The
location on the roof top units has been resolved and there are no structural issues
remaining.
Color of brick, and block submitted and the samples were delivered to the MBC meeting
tonight.
Windows will not be available until October. Exterior masonry, will be coordinated with
the new connector. Steel should be available with a week or so. The schedule was
reviewed with the contractor and a revised schedule will be forwarded to the MBC.
Consigli asked for a detail sketch on filling of the holes in the chase. R. Hoit asked for a
submittal to review.
Discussed the carpeting, samples for the 26 and the 32 ounce carpeting will be submitted
to the Architect to review. The MBC requested that there be a submittal for references.
The Color samples will be presented at the July 9, 1996, meeting.
The next Construction meeting is scheduled for 7-2-96, at 7:30am. Displeasure was
expressed by the Town Manager over the participants that missed the meeting of June
25th.
School Proiects•
(R. Ashton - 9:05, E. Giordano, D. Nicoletti,)
Emergency Finance Board - Keyes was asked to fill out the application for the Town
Treasurer. There were a lot of details needed for renovation. Keyes will drop them off to
MBC office at the end of the week.
Ron Ashton gave a brief summary of the staff meeting with the Robinson School.
Material Selections will be presented to the MBC. They reviewed the location of the
access road for the heavy equipment. The Principal had concerns and they can be
addressed in the specifications.
Discussions were held on access with a badge program it will be handled through the
individual subcontractor. A log sheet will be kept and a request will be made for the
superintendent of each subcontractor to remain consistent. A resolution needs to be made
on the phasing, badges, disturbances, and parking. Member Liddick doesn't want to get
too detail oriented in the specifications, but wants the basics covered.
Town Counsel, Robert Mangiaratti, gave an overview on the request for suspension cost.
Art. 8.2 specifically addresses this issue. He believes that the Town owes some money,
but the amount is in question. The Town Counsel suggested getting time sheets and more
detail on the back-up data to determine what is a realistic price. If parties cannot come to
MBC Minutes - 6-25-96 Page 4
terms then arbitration is always an alternative. The scope of the dispute is very limited.
Member Liddick stated he would like this item to be documented with the time sheets and
other records submitted for our review. It was the consensus of the committee to have this
documentation so that all items can be addressed and it can be reviewed by Town
Counsel. The Town Manager would like this to be handled by the Town Counsel.
School Committee member Dainis asked for the tasks to be detailed by job number. The
burden on proof is on the claimant. This is important to justify this as public servants for
the Town.
Status of the Jordan/Jackson Roof was reviewed with Town Counsel. This project has
been closed out with Granger. This appears to be a product warrantee problen-L The
School department and the MBC will research this item. and give the information to the
Town Counsel.
Jordan/Jackson wells were discussed. The Town Engineer is reviewing the well on East
Street Fields. The committee asked who will be responsible for the preparation of the
RFP. The AMC feels that this RFP will need to be prepared by a professional. The Town
Manager was requested to get a status update. The MBC stated that they will not move
forward with the well at the Jordau/Jackson School until the East Street well project is
addressed.
The Committee reviewed the minutes from the Chapter 60 meeting. School Committee
member Emit Giordano will contact TCI in reference to a point of clarification.
MOTION: To adjourn at 10:20PM (Carpenter/Antoine) Unanimous
Respectfully submitted,
lAwx-
Maureen R. Doherty -
Administrative Secretary
s
Signature of Mair
—
Date of Acceptance - Vote
MBC Minutes - 6-25-96 Page 5