MUNICIPAL BUILDING COMMITTEE
SEPTEMBER 30, 1997 9l OCT 22 Fi t: 30
MINUTES
PRESENT: William Antoine, Richard Feeley, James L dr ick David `Y I§g —
Members of the Municipal Building Committee, Frank Colella, Norman Mahana, Dianne
Royle — Members of the Board of Selectmen, Richard Boucher — Acting Town Manager,
Robert Mangiaratti — Town Counsel, Roger Hoit — Architect — Strekalovsky and Hoit,
Maureen Doherty — Municipal Building Committee Secretary
MINUTES:
The following minutes have been submitted for review:
August 19, 1997 - held
September 9, 1997 —held
September 9, 1997 — Executive Session for content only
The following invoices have been submitted for approval:
Vendor
Project
Amount
Vote
Mini wharehousing,
Inc.
Robinson
$ 60.00
Held
Strekalovsky and
Hoit
Police Station
$ 2,778.75
Held
Walter Parker
Robinson
$ 2,600.00
RF/DY 3-0-0
JT Callahan & Sons
Robinson
$785,661.05
DY/RF 3-0-0
CHANGE ORDERS:
The following change orders have been submitted for approval:
Vendor
Project
Change
Order
Amount
Vote
JT Callahan & Sons
Robinson
#31
$ 370.00(DY/RF
3-0-0
JT Callahan & Sons
Robinson
#32
$ 1,300.00(DY/RF
3-0-0
JT Callahan & Sons
Robinson
#33
$ 2,379.24(DY/RF
3-0-0
JT Callahan & Sons
Robinson
#34
$ 5,528.40(RF/DY
3-0-0
JT Callahan & Sons
Robinson
#35
$ 484.30
/DY 3-0-0
JT Callahan & Sons
Robinson
#36
$ 5,949.60(DY/RF
3-0-0
JT Callahan & Sons
Robinson
#37
$ 8,765.52(RF/DY
JT Callahan & Sons
Robinson
#38
$11,249.77(RF/DY
CORRESPONDENCE: All correspondence has been held for 10-7-97
General
• A memo to all department heads from B. Kearney — Columbus Day holiday
MBC Minutes — September 30, 1997 Page 1 of 5
Town Hall
• A memo to all departments from R. Boucher —Heating System Problems
• A memo to R. Mangiaratti from R. Hoit RE: Town Hall Chiller Noise
Police Station
• A fax to S & H from BBC RE: painting submittals
• A memo to Municipal Building Committee from BBC RE: Notice of Delay
• A memo to J. Liddick from A. O'Neill RE: Fume Hood
• A memo to J. Liddick from A.
O'Neill RE: basement wall
• A memo to J. Liddick from A.
O'Neill RE: electric outlets
• A memo to J. Liddick from A.
O'Neill RE: data outlets
• A memo to J. Liddick from A.
O'Neill RE: Window
• Daily Reports — September 15
— September 19, 1997
• Change Order Proposal — No.
5 - $21,228.65
School Proiects
• A memo to the Municipal Building Committee from J. Moretti — State of Fields
Reports
• A memo to the Municipal Building Committee from J. Moretti — Memorial Park
• A memo to Municipal Building Committee from L. Azinheira JJ — Irrigation Well
• A letter to J. Liddick from S. MacCaffrie - Landscape
• A letter to J. Liddick from S. Loeper — Landscape
• A letter to Keyes Associates from S. MacCaffrie — Exit Device Delay
• A memo to the Municipal Building Committee from Irene Ekstrom — Food Services
• A copy of an RFI for Site Wiring Lighting
• A memo to the Municipal Building Committee from L. Sciarappa RE: Nurses' Office
furnishings
• A memo to the Municipal Building Committee from L. Sciarappa RE: Window
Treatments
• Daily Reports — September 15 — September 26
Joint Meeting — Board of Selectmen and Municipal Building Committee
Member Young and Town Engineer Azinheira reviewed the site drainage for the Town
Hall. A preliminary study is being performed for the results of a two-year and ten-year
storm. Mr. Azinheira stated that because of the introduction of a new low point at the
entrance of the Town Hall Connector this area is being flooded because the pipes on the
main street are being surcharged. Mr. Azinheira stated that the entire line is being
surcharged. He stated that they also explored the possibility of installing a back flow
preventor and the installation of a higher manhole, which drains into a different location
to alleviate any future flooding at the front door. There was discussion regarding the cost
MBC Minutes — September 30, 1997 Page 2 of 5
of all options. The minimal cost of just materials for the connector would be at least
l $6,000; this "guesstimate" does not include the pipe, structure or back flow preventor.
The acting town manager asked about directing the flow towards Union Street.
Selectwoman Royle asked who was responsible? The Town Engineer stated that the
creation of the new low point caused the problem. Mrs. Royle asked why wasn't this
fault ever brought forth before. Chairman Liddick questioned this same thing. Atty.
Mangiaratti clarified Mrs. Royle question by stating that the question should have been
asked if the Town's system would be adequate to handle the flow of the site. Chairman
Liddick stated that the design engineer was obligated to ask the question but not obligated
to correct the Town's system. Member Feeley asked if the Town Engineer should have
been responsible for researching this. Atty. Mangiaratti stated that the cost of fixing the
drainage problem would ultimately be the responsibility of the Town. Mrs. Royle stated
that we have considerable changed the contour of the building by lowering the site by at
least on level. She asked the architect why he didn't acknowledge the possible problem
with a grade reduction. Mr. Hoit stated that he was unable to respond to this question at
this time. Chairman Liddick stated that the right questions might or may not have been
asked. Mrs. Royle stated that she is upset with the fact that the Town always has to bear
the financial burden. She asked if the architect could bear some of the cost. Atty.
Mangiaratti stated that the previous drainage just flowed off site. Member Feeley stated
that the present inadequacy of the town system has found an outlet in the lower manhole
in front of the connector. Atty. Mangiaratti asked if the design team should have caught
this system inadequacy. He stated that no matter what — he stated that the town would
ultimately be responsible to pay for this value added, however, he feels that we need to
f explore the possibility if this would cause additional costs by fixing this now. Atty.
Mangiaratti stated that we need to look into the possibility of errors or responsibility of
correction. The Town Engineer stated that the proposed solution at the time of
installation would be different now. Atty. Mangiaratti stated that we need to review the
specification for the civil engineer and ask them to respond. Selectwoman Royle asked
what measures could be taken immediately. The Town Engineer suggested that a back
flow preventor could be added. The problem with this drain is due to intensity and
duration. Member Young asked if there was support in the room to move forward to fix
the problem. Atty. Mangiaratti asked if Town staff could do this. Mr. Azinheira asked if
the Department of Public Works could price this out. The Town Engineer stated that if
he has the time he was capable to design this. Selectman Colella stated that he feels that
the MBC and the Town Engineer are not responsible for this problem, he feels that the
architect and the design engineer should be responsible and the to correct this. Mr.
Colella stated that we shouldn't pay any money or take any measures to fix this. Atty.
Mangiaratti asked if he wanted us to research this problem for arbitration. Mr. Hoit was
questioned if he had any records pertaining to the permitting process and approval
process with the drainage system. Selectman Mahana asked if the Town Engineer could
look into developing estimates. The Chairman directed the architect to contact his civil
engineer and get back to the committee tomorrow. Atty. Mangiaratti stated that he would
await direction.
NOTE: The Committee voted to go into executive session to discuss pending litigation
MBC Minutes —September 30, 1997 Page 3 of 5
r There was discussion regarding the air conditioning unit at the Town Hall — Sound
readings were done September 16"i. There was discussion on the report from Acentech
regarding the measured operational noise levels. The acting town manager stated that he
did not feel that this was adequate. Member Antoine stated that the chiller unit was
adequate for this building. The suggested DEP regulations state that the machine cannot
be above lOdB above the ambient level. There was only one time it was more than 1 dB
above the regulatory allowed level. There was discussion regarding the type of heating
and cooling system. Mrs. Royle stated that we have a level of responsibility to insure the
happiness of neighbors. Selectman Mahana stated that he hears a lot of negative
comments from the community. Selectman Mahana asked that the MBC give a solution
for the problems so that the cost benefits can be weighed and measured. There will be a
hearing with the Board of Health within a month for the noise violations with the chiller.
Atty. Mangiaratti stated that there needs to be a policy decision. Chairman Liddick stated
that he is concerned with the amount of money that was being spent in addition to the
contract on an overtime basis.
POLICE STATION:
Member Feeley gave an update of the hazardous waste clean up for the police station.
The estimate clean-up price is approximately $50,000. Member Feeley stated that there
was a $12,000 change order for wall finishing in the cell. The architect will review this
item. There was discussion regarding the prices for the additional consoles in the
dispatch room. There was discussion regarding the installation of the raised floor for the
purpose of running cables. There was also discussion concerning the location of the
telephone connections. The telephone panel will stay where it is. An additional chase
will be added through the vault area for future use. Member Feeley asked about the data
cable. There was a question regarding the specifications for the exhaust fan in the lab.
MOTION: To approve the colors for the police station (RF/DY) 3-0-0
The chief stated that he also approved the colors.
SCHOOL PROJECTS:
The following items were submitted for review on the Robinson School Project:
• Certificate of substantial completion
• PCO #41— Kitchen Electrical - $2334.52
• PCO #44 — Aluminum Door - $19253.70
• PCO # 45 — Fire Dampers - $6055.24 —Mr. Parker asked why these weren't included
in the contract.
• PCO # 46 — Sprinkler Changes - $2736.72 — There were several sprinkler heads that
were not included in the vestibules of the Robinson School.
• PCO # 47 — T & M Plumbing - $ 2916.00
• PCO # 48 — VCT Requirements - $2828.91.
MBC Minutes — September 30, 1997 Page 4 of 5
• PCO # 49 — Kindergarten Roof - $31,163.03 — this came up because of the need to
remove the old roof. There was some question regarding the structural integrity of
the roof. The Building Department didn't have a comment regarding the removal of
roof. Mr. Parker gave an overview of this problem. He also stated that he felt that the
cost of the shingle removal was expensive. Chairman Liddick asked if Titan could
furnish back-up for their numbers. Mr. Loeper asked if the Committee could vote on
this next week.
• PCO # 51—Unsuitable soil - $27752.00
• PCO #52 — Piping Changes - $3134.21
• PCO #53 — Relocate Equipment - $3182.90
• PCO #54 — Wiring Change - $1347.02
• PCO #55 — Added Masonry - $4750.92
• PCO #56 — Added Structural Steel $4901.04
• PCO #57 — T & M Electrical $5819.36
• PCO 458 — Stone Replacement $2564.50
• New breaching —for boiler room: Mr. Loeper stated that the lead time is
approximately 6 weeks, however, he would like to get direction so that he can make
the roof penetrations prior to the heating system. It was the opinion that the
contractor would do the patching. OWTION: To direct the contractor to go forward
with two stacks for breaching DY/RF 3-0-0)
• The Committee reviewed the letter to Mr. Ashton from 7TC regarding the exist
devices as outlined in change order #45. Mr. MacCaffrie stated this item was
specified incorrectly in the specifications.
There was discussion concerning the abatement work in the crawl space in the Qualters'
Middle School. This work may be included in the general contractor's contract. This
would relieve any coordination issues between two contractors being on site.
The committee discussed the need to direct Keyes to commence work on QMS and MHS
(A letter will be send stating that Keyes is authorized to proceed W/O information
promised on Aug. le - it will need to be negotiated at a later date)
There was discussion regarding the completion of ball field.
MOTION: To adjourn at 11:48pm (DY/RF 3-0-0)
Respectfully submitted,
Richard Feeley — Clerk