HomeMy WebLinkAboutMBC 12/02/199711 ;
Municipal Building Committee J (f
MINUTES
December 2, 1997
MEMBERS PRESENT: Chairman Liddick, Members Feeley, Moore and Young
Maureen R. Doherty — Administrative Secretary
GUESTS PRESENT: John D' Agostino — Town Manager, Chief Arthur O'Neill —
Police Department, Chief Edward Sliney — Fire Department, Walter Parker — Project
Coordinator — Robinson School, William Madan — Chairman - Board of Selectman
INVOICES:
The following invoices have been submitted for approval:
JT Callahan — Requisition # 15 — Robinson School $ 297,157.88
No action was taken on this requisition because additional information was needed from
the architect.
General
• A copy of the financial statements for Municipal Building Committee budget,
- Municipal and School projects for the month of November.
• A memo to all depts. From R. Boucher RE: Change of Payroll Information
Police Station
• A letter to the M.B.C. from BBC Co., Inc. RE; Police Station Completion date
• A copy of a quote form from Cyber Comm for Police Station Communications
• A copy of a memo to E. Sliney from A. O'Neill RE: dispatch area
Fire Station
• A memo to the Municipal Building Committee from E. Sliney RE: Punch List items
('The committee discussed this memo these items will be added to final list)
Town Hall
• A memo to the M.B.C. from R. Mangiaratti RE: close-out clause for final change
order
School Proiects
• A copy of a memo from J. Sarro to D. Freeman RE: QMS — Sprinklers
• A letter to the M.B.C. from S. MacCaffrie RE: Substantial Completion —Robinson
• A letter to the M.B.C. from S. MacCaffrie RE: Ball Field Berm
• A letter to the M.B.C. from S. MacCaffrie RE: Finish Paving
MBC Minutes 12-2-97
Page 1 of 4
• A letter to the M.B.C. from S. MacCaffrie RE: Electrician's Response to Kitchen
Consultant's punch list
• PCO # 71 — Heat tracer/circulation pump $4,219.07 (Member Feeley asked if there
was any way that a hot water heater could be installed in this side of the building)
• PCO #90 — Gym divider - $1,926.73
Police Station Project:
Chief Sliney and Chief O'Neill were present to discuss the quote proposal from Cyber
Comm. for communications work at the Police Station.
Chief O'Neill gave an overview of the dispatch area for the Police Station. The Police
station console needs to be activated prior to the deactivation of the console that is
located at the Central Fire Station. The Chief stated that he spoke to E911 for a
conversion date of January 5th or 6th. Members Young and Feeley stated that their
recommendation would be to schedule this after January 15th. Chief O'Neill commented
on the relocation of the console at the Central Fire Station. There was discussion
regarding the costs of the transportation of the console at the Central Fire Station. The
MBC asked where the costs of the Central Fire Station would be coming from. Member
Feeley stated that over $6,000 in change orders were a result of a lack of input during
programming concerning the second console. The committee asked about the need for
two consoles. Chairman Liddick stated that the missing link was what was needed to run
central dispatch. He stated that the MBC fulfilled the requirements to have the building
ready for both consoles. Member Young stated that moving costs should be covered by
the individual department budgets not project budgets. Chief O'Neill stated that he has
only paid for the move and not any hook-up costs. Member Young asked Chairman
Madan what should we do with these costs and if we should take the costs from the
Central Fire Station Project. Chairman Madan stated that he would like to have the
project completely finished. Chief Sliney will be contacting Cyber Comm. regarding the
prices that were submitted. The Chief s will review their budgets and respond back to the
Committee.
Member Feeley stated that he relayed comments from MEMA director Bob Button
regarding the allocation of space in the new station. Mr. Button has stated to Member
Feeley that he is pleased with his new space and his communications.
Member Feeley gave an overview of the Police Station Project. There was discussion
regarding the extension letter.
Member Young stated that he would like to schedule the moving date to be January 24th
or after. The committee would like to insure that this project is totally completed prior to
move -in. There was discussion regarding the installation of the sink in the photo lab.
Member Feeley stated that we need to have a specifications developed for the sink and
plumbing. Chief O'Neill stated that the hood and the sink must be located in the same
room. Member Feeley will verify this with the project representative and the contractor.
Chairman Liddick asked if all the hardware and equipment was on site. Member Feeley
MBC Minutes 12-2-97
Page 2 of 4
stated that the cell doors are not on site as of this date. Member Feeley stated that there
are a number of outstanding issues. Chairman Liddick asked Member Feeley to have a
complete inventory of the items that are not on site.
Chairman Madan asked about the paving costs. The draft memo was revised and
forwarded to the Town Manager. The Municipal Building Committee has $10,000 in the
project budget for paving and line stripping. The bills forwarded from DPW exceeded
this amount. The Committee will ask for direction from the Town Manager.
Mansfield Resident Carl Klemmey asked about the installation of fire doors through out
the station. Member Feeley will research this item at the next job site meeting.
The Committee reviewed the request for an extension from BBC. Member Feeley will
speak with the architect at the job meeting and ask that BBC is official notified that they
have passed the contract date.
FUZE STATION:
Member Young reviewed the memo from Chief Sliney regarding the punch list items at
the West Mansfield Fire Station. The following are the remaining punch list items:
A/C training, Overhead door coils, landscape and lawn installations. Warranty:
pavement settlement and crack in tile in public bathroom.
TOWN HALL:
The Town Manager reviewed the progress of the closeout of the project with the
Committee.
ROBINSON SCHOOL PROJECT:
Chairman Liddick reviewed the procedure for submitting of change orders. The
Committee discussed their displeasure with Keyes.
MOTION: To send a letter to Keyes regarding the change order procedure.
(DY/RF 4-0-0)
Representatives from Keyes will be scheduled on the December 9U' agenda to discuss
procedures and future school projects.
The committee reviewed the Certificate of Substantial Completion for Area "A"
MOTION: To approve Certificate of Substantial Completion for Area's A and
C & D) (DY/RF 4-0-0)
The Committee reviewed the proposed budget for the Municipal Building Committee
office for FYI 999.
MBC Minutes 12-2-97
Page 3 of 4
MOTION: To approve the Municipal Building Committee FY 1999 —Budget
(DY/RF 4-0-0)
Member Young gave a status report on the fracture trace study for the Jordan/Jackson
Well Progress.
MOTION: To adjourned at 10:45pm (RF/DY 4-0-0)
Respectfully submitted:
Richard Feeley
Signature of Chair
MBC Minutes 12-2-97
Page 4 of 4
97 -a -o
Date of Acceptance - Vote