MUNICIPAL BUILDING COMMITTEE
Minutes of September 15, 1998
1�lembers," PFe'seiit: Richard Feeley, Chairman, Jim Liddick, Clerk, Ken Gay,
Bill Moore, David Young and Eleanor McCarter, Secretary
Attendees: Steve MacCaffrie, J.T. Callahan
Chris Sullivan, QMS Project Coordinator
Dan Freeman, Keyes Associates
Bob Gurek, Business Manager
Walter Parker, Mansfield Schools Facilities Mgr.
John Moretti, Superintendent of Schools
John D'Agostino, Town Manager
QUALTERS MIDDLE SCHOOL
Construction Schedule — Steve MacCaffrie provided a formal schedule to the MBC noting that
their would be some changes in dates. Upon review of the documents, the Committee found that
the schedule as presented, exceeds the 528 days allowed by contract to complete the project.
Suggestion was made to return the schedule to Keyes to review MBC concerns.
Fire Alarm Panel — Mr. MacCaffrie noted that to start work in zone 2 the fire alarm panel needs
to be relocated to the new entry.
Sanitary Product Dispensers — Walter Parker was unable to get units. After further research,
Chris Sullivan found 9 units indicated on finish schedule of contract. One dispenser shown in
boy's bath will be moved to girl's bath missing a unit. No dispenser is currently listed for
faculty bath. Cost to purchase is $330.00.
Credit Due —A mathematical error was discovered in Change Order #1. Credit of $1,000.00 will
be included on Change Order #2. Pencil requsition from J.T. Callahan due Sept. 22"a
Hollow Metal Schedule — Follow up re: status - Comment by Steve MacCaffrie that Keyes
Associates has approved the schedule as requested by J.T. Callahan.
Can to Gas Line — Existing dead gas line feeding south wing at Qualters found stuffed with rag.
Project Coordinator requested to have capped properly. Suggestion made to check with
Superintendent and principle to verify curriculum needs re: need for gas in that location.
Renderings — Committee asked Keyes Associates to prepare QMS Site Plan and Elevation for
school campaign presentations and Town use. Request made for a colored floor plan and colored
elevation showing 4 sides. Dan Freeman to contact Secretary upon completion. Town Manager
requested renderings be complete a.s.a.p.
Field Density Testing — Test results received. Discussion re: Invoice for $130.00 for soil testing
by Geisser Engineering on 8-24-98 at Qualters. Invoice to be submit through Keyes Associates.
Special Inspections —Dan Freeman noted changes in the 6t' Addition Building Code requires fee
for additional services incurred for Program of Structural Tests and Inspections.
MOTION to acknowledge Sarkis Zerounian as the Structural Engineer of Record and
recommend payment of $5,000 as indicated for services outlined in Program of Structural
Tests and Inspections. WM/DY Passes 4-0
Fire Inspections — Discussion with Town Manager re: fees for fire inspections. Fire Dept. has
indicated that inspections will be done on overtime. The MBC and Contractor believe monies
can be saved if inspections are done on duty. Steve MacCaffrie noted that J.T. Callahan has no
objection if an inspection needs to be interrupted for Fire Dept. to respond to call. They could
resume inspection afterwards. Mr. MacCaffrie estimated inspections to take 20-24 hours to
complete and would be done in phases. John D'Agostino to discuss issue with Fire Chief.
Li htin — Discussion re: response from TCI dated 8-25-98 evaluating keeping existing fixtures
vs. replacement. Dan Freeman recommended replacement of fixtures referring to TCI response
noting the following: replacement of existing fixtures will raise inadequate light level (Net up
charge of $660/classroom), existing fixtures and wiring are currently beyond life expectancy, and
Town would receive .50c on a dollar return for a credit.
MOTION to replace fixtures as recommended in 8-25-98 response from TCL
DY/WM Passes 4-0
Ceiling Tile Removal — Discussion re: C.O.P. #22 for removal of double ceiling. Estimated cost
$.50 per square foot. It was determined that the town owns ceiling removal not Universal
Engineering, as previously thought.
MOTION to recommend approval to remove double ceiling at QMS as recommended by
Keyes Associates in the amount of $21, 339.00
Data Cable — Contract requires G.C. run conduit only. End user responsible for coordinating
data contract for wiring to new location in south wing. Steve MacCaffrie noted that consideration
should be made to run cable while ceilings are down. Time delays now could risk computer
room being out of commission. MBC to send letter to Superintendent to advise. Ken Gay made
recommendation to make provisions to hang all loose wires at the same time.
Proposed Change Orders — OMS'
C.O.P.#14 ref: Temporary Locker Bases — Committee reviewed submitted time and materials.
Work in the amount of $1,128.00, was verified by Project Coordinator.
MOTION to approve of C.O.P. #14 in the amount of $1,128.00 for temporary locker bases.
DY/WM Passes 4-0
C.O.P.#11 ref: Sprinkler Changes -Information received from Tri-State Fire Protection Co.
$773.00 credit offered. Holding for recommendation from Keyes Assoc.
C.O.P.#17 ref. Gym Window Steel - Holding for recommendation from Keyes Assoc.
Review of C.O.P. #20 ref: Sheet S-8 Item 3 — Increases slope of roof to gym addition. Addresses
roof load issue i.e. snow and water.
MOTION to approve C.O.P. #20 in the amount of $1,088.00 to address roof load issues.
DY/WM Passes 5-0
C.O.P. # 21 ref: BR136/137 - Request to furnish and install ceramic tile in toilets. Proposal
rejected by Keyes Associates.
C.O.P. #24 —Rock Removal — Committee reviewed breakdown of costs indicated in proposal for
removing excess rock at QMS. Unit cost to remove per bid documents $16,922.50 discounted by
30% due to owner trucking of a portion of materials and less removal cost than specified after
review on site. Town's final cost $11,846.00.
MOTION to approve C.O.P. #24 in the amount of $11,846.00 for removal of excess rock.
WM/DY Passes 5-0.
Submittals — Dan Freeman to follow up with Ron Ashton re: status of outstanding submittals.
Schematic desmon for South Wing — Dan Freeman reed question from Superintendent re: number
of Science rooms. Schematic indicates eight rooms. Dan noted that there are currently seven.
Discussion re: flexible use of classrooms in South Wing.
Construction Schedule — Steve MacCaffrie noted to Committee that some work would be
completed out of sequence. Concern raised re: July 10`h start date indicated in contract, not
enough time to complete work for Sept. MBC to sent letter to Superintendent to see if work can
begin sooner.
Committee reviewed schedule later in meeting to find that construction schedule as submitted
exceeds the 528 days allow in contract. Estimated completion indicated May 2000. MBC to
send letter to J.T. Callahan requesting a revised schedule that meets contract guidelines.
Cash Flow — Steve MacCaffrie noted that cash flow summary will be forwarded with the
requisition.
Security Tag — Follow up re: status of tags for MBC and Town Manger for on site visits.
Project Coordinator will obtain necessary information names, address etc. and issue.
Builders Risk Insurance - Follow up to previous request by Steve MacCaffrie to be named as
additionally insured. Secretary still working with insurance agent to process. Mr. MacCaffrie
noted that under the construction section , the Town's policy does not cover lawns & plantings.
Form F — Dan Freeman returned portions of the financial information requested by the D.O.E.
Waiting for information from Ron Ashton re: Robinson School.
Curb Cut at OMS — Follow up to previous concern by David Young. Dan Freeman noted that
the curb cut was left high at this point but will be lowered.
Aluminum Doors/Storefronts — Follow up from Sept 1s` re: possible errors in the Scope of Work.
Issue still pending clarification from Ron Ashton.
Fire Alarm Panel — Question raised re: cause of problem determined. No determination has
been made as yet whether issue was related to work demo or existing situation. Waiting further
information from Walter Parker.
MANSFIELD HIGH SCHOOL
MHS Parking-- Committee reviewed the updated plan of proposed parking prepared by Kevin
McBride, Keyes Associates. Question raised by David Young re: line parking along ball field
left out as well as pole vault pit area. Mr. Young to follow up with Keyes Associates.
SBAB —Update provided by John Moretti. Mr. Moretti extended invitation to Jim Anderson,
S.B.A.B. to do walk through. Asked for any Committee members available to join them.
Re: Fencing/Bleachers at Memorial Park — Mr. Moretti noted that S.B.A.B is checking with state
auditors. Original proposal for school project does include portions of Memorial Park.
School Campaign — Ken Gay attended meeting called by Superintendent. MBC members
received a schedule, of the community forums being held, to promote school project before the
Oct. 26h Town Meeting. Mr. Moretti invited MBC to attend as many as they wish. The
Committee decided that the public forms at the high school were most important and should have
a representative from MBC present to field questions. David Young suggested that the
Committee review the school project finances together.
MHS Bid Addendum — Committee reviewed of Invitation to Bid. Discussion to include revised
wording further defining votes needed. MBC to contact Jim May, Wallace Floyd to further
define in addendum, date of Town Meeting as Oct. 26a' and Town wide referendum vote to be
taken within 45 days.
ROBINSON SCHOOL
Dishwasher Problem — Walter Parker stated there is no hot water in dishwasher. Mr. Parker
discussed use of hot water booster.
Communication Systems Inc. — Re: Intercom hook up to nurses office. Request made to Walter
Parker for further explanation of discrepancy of related invoices.
Invoices — Committee reviewed and recommended the following for payment:
Chris Sullivan QMS Project Coordinator $ 2,500.00 JUDY Passes 5-0
W.B. Mason Robinson Furnishings $12,810.45 JL/DY Passes 5-0
h
Corporate Express
Robinson Furnishings
$10,013.40
JL/DY Passes 5-0
Walker Specialties
Robinson Wind. Treatmt.
$ 5,995.00
WM/DY Passes 5-0
Keyes Assoc.
QMS- Serv. Thru 7-25-98
$36,993.72
DY/JL Passes 5-0
Keyes Assoc.
QMS- Serv. Thru 8-29-98
$ 7,394.00
WM/JL Passes 5-0
Keyes Assoc.
NMS- Serv. Thru 7-25-96
$ 5,968.00
WM/DY Passes 5-0
Geisser Engineerin¢ — Field test work performed at QMS for $130.00. Payment to be billed by
Keyes Assoc.
ROBERT E. WALSH WATER TREATMENT FACILITY
Update — Ken Gay noted everything is going well. Question raised by Mr. Gay as to whether the
water stop is being placed properly. Issue to be followed up with DPW.
Respectfully Submitted,
Eleanor McCarter, Secretary