TOWN OF MANSFIELD
MUNICIPAL BUILDING COMMITTEE`
MINUTES OF OCTOBER 6,1998
Members Present: Richard Feeley, Chairman, Jim Liddick, Clerk, Ken Gay
_ William Moore, David Young and Eleanor McCarter, Secretary
Meeting Opened 7:00PM
CORRESPONDENCE
• FAX to MBC from Wallace Floyd re: Plan List- Jim May provided a list (as of
October 5, 1998) of Sub Bidders who have take out plans for the High School project.
FAX to MBC from Wallace Floyd re: Questions on ball field and bleachers
• Deposits for Plans (QMS) - Checks received from AirGraphics (from those not
returning plans) are now property of the Town of Mansfield. All checks were
brought to the Treasurer's office for deposit. Checks received for shipping plans
($30.00 ea.) will be applied to Miscellaneous Income. Keyes will bill Town for the
same amount.
• FAX from Chris Sullivan requesting Keyes to provide sketch & RFP to re -install
washer/dryer at QMS and issue to J.T. Callahan for pricing. Direction to make
provisions for reinstallation was given by the MBC at Sept. 29a' meeting.
F • FAX from J.T. Callahan re: Proposed C.O.P #33 ref temp doors in the amount of
$2,806.00 for front entry at Qualters
• Ltr from Chris Sullivan re: Explanation of water main break at MHS
• Ltr from Dept. of Education re: Updates on School Building Assistance Program.
Request for Project # form needs to be completed for MHS and returned to initiate
grant payment schedule.
• Ltr from JTC — re: Problem with specification for handicap lift to add cost to project.
Space constraints for installation of specified Handicap lift. Request for change order
for Gareventa in the amount of $7,864.00 for 2 inclined platform wheelchair lifts.
• Copy of FAX to Keyes from JTC re: Waiting for accent brick approval -urgent
response requested.
• Copy of ltr. to Keyes from JTC — re: damage to entrance ramp. Keyes to send letter
to Suburban with cc: Ammar Dieb, Universal. There may be back charge for damage
caused by Suburban.
• Copy of ltr. to John Spath from Keyes re: Waiting for response on joist fabrication.
• Ltr to JTC from Eastern Contractors re: September Requisition.
• Ltr to Keyes from JTC re: Sign change request. Discussion opened by Dan Freeman
regarding moving sign. Mr. Freeman commented that the school sign is not in good
condition. The Committee may want to consider new sign.
• Ltr from JTC to Keyes— C.O. proposal for changes for finishes to patch to match. The
MBC requested clarification regarding the number of baths in question 2 vs 26.
• Ltr from Keyes to TCI — Directive from Keyes re: use of ceramic tile in related bath
and request for quote for use of glazed block.
I
f- • Ltr from JTC - Re: tile patch to match. Request for final determination.
• Copy of Ltr to Town Manager from Ken Hassler - Mr. Hassler was appointed Project
Manager of the SCADA System for the Walsh Well;project. Article prepared for
Town Meeting for $117,000 to cover equipment andengineering of SCADA Project.
• Ltr from Michael Callahan re: Proposed delay claim of $20,000 for the QMS Project.
• Ltr to Bill Maher from Chris Sullivan re: Moving HELP panel/keypad at QMS.
. Ltr--to-MBC from Dick Battles, TC1 re: Request to=substitute-Victaulic pipe for the hot
water system at QMS. Based on past experience of a committee member having
leakage problems, motion was made by Jim Liddick to stay with welded system.
ROBINSON ELEMENTARY SCHOOL— --
Wonderworks/Norway Maples - The 3`d bid was received from Walter Parker for
purchase and installation of trees at the Wonderworks play area at the Robinson School.
MOTION to accept McGuire Landscape as low bidder for the purchase and
installation of 7 Norway Maples in the amount of $1,856.28 DY/JL Passes 5-0
MBC to send notification letter to Walter Parker to move forward with coordinating
purchase and installation of trees. Trees are to be planted in locations as indicated on
sketch provided by David Young.
MANSFIELD HIGH SCHOOL
Fencing/Bleachers at Memorial Park - Received copy of letter to John D'Agostino from
J. Moretti re: Renovation to Memorial Park. SBAB will not support reimbursement. Mr.
Moretti will recommend Town Manager not to move forward with warrant article for
Town Meeting.
Asbestos Allowance - Richard Feeley read letter sent on behalf of MBC -re: feasibility of
having a $300,000 allowance for asbestos abatement at MHS. Coordination and payment
of the work to be handled by GC. MBC prefers the hygienist be retained and paid by the
Town.
Insurance - Suggestion made to make sure our agent has a copy of the insurance section
of contract. The Town should have builders risk insurance specific for the high school.
Bus Loon - Discussion re: GC to carry allowance. Letter to be sent to Jim May to
include tack coat and top coat parking space line stripping next addendum.
Invoices - Committee reviewed and approved the following:
MOTION to approve to The Sun Chronicle - Advertisement: MHS Invitation to bid
in the amount of $470.64 DY/JL Passes 5-0
MOTION to recommend payment to M.D. Stedson Co. in the amount of $8233.44
for the purchase of Cleaning Equipment for Robinson School. M.D. Stedson Co. is
part of O.S.O. bid package. JUDY Passes 5-0
MOTION to recommend payment to RISO Products of Boston in the amount of
$5,650:00 for purchase of one riso graph and stand for Robinson School. RISO is
part of O.S.O. bid package.
DY/WM Passes 5-0
Review of Meeting Minutes
Minutes of May 5, 1998
MOTION to approve as amended
DY/JL Passes 5-0
Minutes -of Aug. 25, 1998
MOTION to approve as amended
JL/WM Passes 5-0
Minutes of Sept. 1, 1998
MOTION to approve as amended
DL/WM Passes 5-0
Minutes of Sept. 8, 1998
MOTION to approve as amended
WM/DL Passes 5-0
Minutes of Sept. 15, 1998
MOTION to approve as amended
DY/WM Passes 5-0
Minutes of Sept. 22, 1998
MOTION to approve as amended
WM/JL Passes 4-0-1
Minutes of Sept. 29, 1998
MOTION to approve
DY/WM Passes 5-0
Budget Evaluation
• CIP Meeting Update — Bill Moore gave update from CIP meeting held on Oct. 1�`.
• School Projects — Jim Liddick reviewed updated spreadsheet figures for school
projects. Mr. Liddick noted that Construction Administration — re: NMS is indicated
in design fee. Discussion to consolidate into more general categories such as
architect, testing, project coordination, furnishings & contingency. Projection was
made for high school bids to come in $8.6 to $9.0 million.
Age of Roofs — Committee members questioned age of the roofs are at QMS & MHS.
MOTION to send letter to Bob Gurek requesting immediate response requested re:
document the age of roofs in place at QMS and MHS. DY/WM Passes 5-0
Compost facility— Based on last conversation with Lee Azinhiera — Scheduled bid
estimated for Spring 1999. Secretary to copy all related correspondence, for MBC point
person, Bill Moore
Police Station — Discussion re: problems reported with HVAC not covered under
warranty because units were not maintained. Richard Feeley noted that CAM was to
replace all filters and should be responsible for any replacement/repair necessary.
Respectfully Submitted,
Eleanor McCarter, Secretary
James Liddick, Clerk