HomeMy WebLinkAboutMBC 10/13/1998TOWN(OIF MANSFIELD
MANSFI"MUNICIPAL BUILDING COMMITTEE
"" Minutes of Qrtpbei 13,1998
Members Present: Richard Feeley, Chairman, James Liddick, Clerk, Ken Gay
William Moore, David Young, and Eleanor McCarter Secretary
Attendees: Bill Frasier, McLaughlin Mechanical Services, Inc.
Michael Belanger, Victaulic Regional Sales Manager
Dan Freeman, Keyes Associates
Chris Sullivan, QMS Project Coordinator
Bob Gurek, Business Manager
Walter Parker, School Facilities Manager
Meeting commenced at 7:00 P.M.
QUALTERS MIDDLE SCHOOL
Substitute nioine— Based on past personal experience by a Committee member, there was
concern re: leakage using Victaulic pipe for the hot water heating system. Committee
voted on 10-6-98 to direct TCI to go with a welded system. Bill Frasier and Mike
Belanger explained the advantages and capabilities in using Vicaulic pipe. Previous
gaskets limited to 180 degrees, can now accommodate 230 degrees. The MBC was
satisfied with reasons given to use Victaulic pipe and approved use. Mr. Frasier will
resubmit his letter to TCI requesting use of Victaulic. Jim Liddick requested that the
letter be project specific and gasket specific for use at Qualters.
Clean Out — Project Coordinator reported that Keyes missed some areas. Plumbing code
requires installation of full size clean out for bathrooms. T&M will be verified by Ms.
Sullivan and submitted to MBC. Montle Plumbing to submit RFI with update. Project
Coordinator will review with TCI.
School Entrance — Ms. Sullivan noted that the front new entrance was opened for use.
Heat Trace — Chris Sullivan indicated that Town owns heat trace on hot water lines. Ms.
Sullivan noted that Connie Lajoie, Plumbing & Gas Inspector has concern based on
previous experiences at the Robinson School. Copy of submittal was provided. He
would prefer a much more expensive recirculation pump system.
Sills- Ms. Sullivan noted that under civil engineering "Order of Conditions" a drawing is
missing from addendum indicating HDPE pipe. Plan to be approved/modified was not in
the addendum and not approved by DEP. Dick Lewis to review for conservation
approval.
Safety Prop
grams - Frank D'Censo from J.T. Callahan doing safety programs relating to
the construction activity at school.
Breeching Deleted - Chris Sullivan reported that Universal Engineering had deleted
breeching in mechanical room. Ms. Sullivan indicated that the Mechanical Sub does not
own new insulation on breeching. Jim Liddick raised questions regarding repeated
coordination problems with Universal.
Damage to Front Ramp - Request to have Callahan submit cost proposal to repair of
"one" concrete panel. S.M.I. will be held responsible for damages. Dan Freeman to
follow up.
Security Issue - Students were reported this week trespassing through crawl space area
after school hours. Walter Parker alleged that S.M.I. removed grates from windows
without replacing them. David Young suggested that S.M.I. be contacted and questioned
about the status of grates on site at the time they did their work. Richard Feeley noted
that the Project Coordinator has made J.T. Callahan aware of the situation and also
responded to the memo from Jack Hagerty re: School Security.
Harold L. Oualters Memorial Tree — J.T. Callahan was preparing to remove the tree,
when notified by school staff, of the tree's significance. The tree was relocated intact by
J.T. Callahan. David Young requested that Steve MacCaffrie check on a fertilization
program. Change order coming.
Poly vs Plywood issue — MBC currently waiting response from Ammar Dieb re: using
plywood versus polyethylene to secure on windows after asbestos abatement. J.T.
Callahan installed plywood on 4 front windows. Project Coordinator met with Ammar
Dieb and Charles Smith, S.M.I. Both are aware that things need to be done.
School Roofs - Bob Gurek responded to a letter from Richard Feeley re: age of roofs.
Mr. Gurek indicated that the Qualters roof is 18 yrs. The High School is 12 yrs. 6mos.
Kitchen Equipment Concerns — Discussion re: memo from Dawn Florence, Director of
Food Service re: various concerns relating to kitchen equipment. Information was given
to Dan Freeman to discuss with Crabtree MaGrath.
Air Quality at OMS — Concerns re: health problems reported by students at Qualters.
Bob Gurek reported two asthmatic students having severe difficulty breathing at school.
Mr. Gurek was asked to provide MBC with further details re: the student's health
background.
• Masonry work - Grinding was estimated to be completed on Saturday. Steve
MacCaffrie reported that masonry work is being done on weekends. Air quality
should be improved when masonry work ceases.
• Re: odors coming from bathrooms. Steve MacCaffrie noted that sewer gasses are
coming up from trap near locker room. Mr. MacCaffrie noted that water is needed in
traps.
Eastern/Baystate —Chris Sullivan noted that Eastern's cooperation has improved. All
submittals have been received.
Water Main Breaks — J.T. Callahan will cover costs of break at QMS. Discussion re:
water main break at high school. Water Department disputing bill with J.T. Callahan for
their services for the break at the Mansfield High School. MBC to pay high school bill.
Aluminum Doors/Storefront — J.T. Callahan has received the drawings from Keyes that
they were waiting for.
Zone 2 and connection drawings - engineer had information for Ron Ashton. Revised
layout drawing to match existing conditions being developed.
Proposed Change Orders — The Committee reviewed status of proposed change orders
submitted by Keyes Associates.
COP #7 Ramp Lighting — Status: Waiting for response from TCI.
COP#11 Sprinkler Changes — Status: Waiting for response - Credit $773.00
COP#16 T&M Valve Replacement — Status: Approved by Keyes
COP# 17 $2,251 Gym window support — Status: Approved by Keyes
COP Existing gas cap $134.00 — Status: Approved by Keyes
COP #10 Fire Alarm electrical changes $9,601.00 Status: Approved by Keyes Assoc.
Committee members questioned whether wiring will be covered at no additional
cost to install fire alarm panel in final location. Dan Freeman noted that the
change of location was directed by the Mansfield Fire Department.
Review of Pending CO's as submitted by J.T. Callahan:
• Abatement securing walls — SMI to be back -charged for abatement wall protection
$297.00.
• New Landing at Home Ec. — Status: Dan Freeman to follow up.
• No vent in electrical room — Status: TCI Approved.
• Temp front entry door — Status: Temporary doors were installed and are in use.
• Test Pits — Status: Completed excluding Water Dept. bill.
• Status: Mason entry work — positional underdrain had to be added.
Wheelchair lifts — Horizontal lift needed. Chris Sullivan provided MBC with back up
information re: change of original specifications indicated for Vertical lift. Steve
MacCaffrie noted that an additional vertical lift would still be needed at auditorium. Rich
Feeley requested we get price proposal from Garaventa.
Tapered Insulation — Ron Ashton working on Premier Roofing. Dan Freeman to follow
up regarding, roof personnel doing work.
Ceramic tile — Dan sent letter to J.T. Callahan with directive to install ceramic tile as
stated. J.T. Callahan letter of response stated that, the work would be done under
protest. Jim Liddick referenced the question of ownership in documents and suggested to
.... ....-._._--.-..- .-. .
Steve MacCaffrie, a compromise be made to resolve this issue. Dan Freeman to get
l proposed change order from RLM including the $500 credit per bathroom, plus estimates
for work in new baths and new existing. Steve MacCaffrie confirmed that the mason
would provide pricing for glazed block. J. T. Callahan to put together a proposal to
negotiate with RLM.
---- -- Delay Claim —Representatives from-J.T.-_Callahan to attend MBC meeting -on October -
27'h to address possible delay damages. The -scheduler from J.T. Callahan to visit site to -
calculate delay claims.
Hot Water Heater — Chris reported that they can not get new heater into area indicated.
Doorframe opening not big enough. %Unit currently being stored in shop. Chris Sullivan
has investigated alternatives with -Ron Ashton. Suggestion made that insulation jacket
can be removed to move it in horizontal Work may take all day.
Construction Schedule - Richard Feeley asked that Dan Freeman send a letter to the MBC
confirming that Keyes has reviewed and approved the construction schedule as submitted
by J.T. Callahan.
ROBINSON ELEMENTARY SCHOOL
Zarrella Heating —Walter Parker noted that Zarrella has been unresponsive. Steve
MacCaffrie will follow up.
WALSH WELL UPDATE
Ken Gay commented that everything seems to be going very well. Tata & Howard and
DPW are scheduled to provide their monthly update at the October 20th MBC Meeting.
INVOICES — The Committee reviewed and approved the following:
Motion to approve payment to Chris Sullivan, QMS Project Coordinator for the
weeks ending Oct. 10th and Oct. 17th DY/WM Passes 5-0
Respectfully Submitted,
Eleanor A. McCarter
2 1 iii a
JAies Liddick, Clerk Date