HomeMy WebLinkAboutMBC 12/08/1998TOWN OF MANSFIELD APPROVED
MUNICIPAL BUILDING COMMITTEE
Minutes of December 8, 1998
Members Present: Richard Feeley, Chairman, Jim Liddick, Clerk, Ken Gay
William Moore, David Young, and Eleanor McCarter, Secretary
Attendees: Dan Freeman, Keyes Associates
Chris Sullivan, QMS Project Coordinator
Jim May, Wallace Floyd
David Burson, Wallace Floyd
Meeting opened at 7:OOPM
CORRESPONDENCE:
Ltr. to J.T. Callahan, Mello Construction, and Interstate Construction from John D'Agostino
Re: Request to extend general bid for Mansfield High School Addition/Renovation Project.
FAX to Keyes from J.T. Callahan re: C.O.P. #I1 revised ref. Sprinkler changes (-$502.00) QMS.
Ltr. to Premier Roofing from J.T. Callahan re: Directive to repair existing stage vent system.
FAX to Keyes Associates from J.T. Callahan re: Quotes for Aluminum doors - QMS.
Ltr. to MBC from J.T. Callahan re: Heating loss issue at QMS.
Ltr. to Ken Gay from Board of Selectman re: Affirmative reappointment to MBC - expires 2004
Ltr. to Keyes from J.T. Callahan Re: Security issues at QMS. MBC waiting for Ron Ashton to
respond re: status of fence installation.
FAX to Keyes from J.T. Callahan re: C.O.P. G.C. #60 ref. Tapered Insulation in the amount of
$19,387.00 — QMS.
FAX to Keyes from J.T. Callahan re: C.O.P. G.C. #70 ref. Roof Blocking in the amount of
$788.00. Add due to document discrepancies. Jim Liddick raised concern re: Project
Coordinator authorizing T & M for roofer may be interpreted as implied extra work. Chris
indicated that issue is between roofer and contractor.
FAX to Keyes from J.T. Callahan re: C.O.P. GC#71 ref. Roof Blocking in the amount of
$925.00 — QMS. Add due to drawing discrepancies.
FAX to Keyes from J.T. Callahan re: C.O.P. GC#72 ref. Grease Trap changes — QMS in the
amount of $850.00. Relocation of the grease trap shown under sink, moved to boiler room.
Connie Lajoie directed to be moved within 20 ft. plus blow down.
Ltr. to Keyes from J.T. Callahan re: C.O.P. #72 ref. Grease Trap — QMS
FAX to Keyes from J.T. Callahan C.O.P. GC73 ref. Accessory Changes in the amount of
$1,342.00 - Chris Sullivan noted that further changes are required for QMS.
FAX to Keyes from J.T. Callahan re: C.O.P. GC#75 ref. Z4/3 Mid Roof Blocking in the amount
of $237.00 — QMS. Additional blocking and refasten existing not per contract.
FAX to Keyes from J.T. Callahan re: C.O.P. GC#76 ref. Glass Skylight — QMS in the amount of
$1,347.00. Cover existing skylight (glass block) to allow for roof enclosure — final billing.
FAX to Keyes from J.T. Callahan re: C.O.P. GC #77 ref. Bathroom Vent Changes in the amount
of $3,568.00—QMS.
FAX to Keyes from J.T. Callahan re: C.O.P. GC#80 ref. Roof Blocking in the amount of
$401.00 — QMS. Added roof blocking due to drawing differential -Z6 mid roof.
FAX to Keyes from J.T. Callahan re: Waiting for response to Acid Waste RFI. —QMS.
FAX to Keyes from TCI re: Response to Acid Waste RFI signed by Ron Ashton, directing to
proceed time & materials to make corrections and connections to system - QMS.
Ltr. to Tri-State Fire Protection from J.T. Callahan - Determination by Chuck D'Olympia
regarding valve from the electrical closet -Issue to be discussed at QMS job site meeting 12-3-98.
Ltr. to Walter Parker from Chris Sullivan re: Ordering knox box for QMS. Chris Sullivan is
waiting for Walter Parker to respond.
Memo to all Depts. from Town Accountant — Warrant closing early for December holidays.
Ltr. to Eleanor McCarter from Wallace Floyd re: Suggested wording to be used in requesting
General Contractor's to extend their bids for the MHS Project for an additional 30 days.
FAX to Town Manager from Mello Construction — Agrees to extend bid re: MHS Project.
Ltr. to J.T. Callahan from Chris Sullivan re: Request to direct Premier Roofing to install U Seals.
Ltr. to Rich Feeley from Ron Reardon/Dan Etter (QMS staff) — Thank you to J.T. Callahan &
construction crew for participating in food drive to Mansfield food pantry.
FAX to Keyes from J.T. Callahan re: Response from Montle Plumbing and Heating re: cutting
and patching to be done under protest - QMS.
FAX to Keyes from J.T. Callahan re: Hardware keying. Chris Sullivan to follow up at 12-10-98
QMS job site meeting.
Mail Receipt — To J.T. Callahan from Town Manager/MBC — Re: 7 day notice to address
outstanding construction issues at the Robinson School,
U.S. Census Bureau form — Request for information re: Qualters Middle School Project.
Memo to Chris Sullivan from Walter Parker — Re: Request for clarification re: temporary
termination of Gas train-QMS. Chris Sullivan responded to Mr. Parker with written clarification.
Ltr. to MBC from J.T. Callahan re: C.O.P. #83 ref. Johnson Control bill in the amount of
$802.00 for new door opening required for heater unit at QMS.
Ltr. to Keyes from J.T. Callahan re: Wardrobe Unit Letter. Wardrobe units interfere with the new
roof drains in the zone 2 classroom addition. Ron Ashton to supply relocation sketch.
Ltr. to Premier Roofing from J.T. Callahan — Gym ceiling repairs - Notification of dates
Approved — 12-24-98 to 1-3-99.
Ltr. To Debrino Caulking from J.T. Callahan — Request for clarification re: Existing Louvers
FAX to Premier Roofing from J.T. Callahan re: request for pricing for skylights - QMS
Ltr. to Chris Sullivan from Lincoln Environmental re: Limited Removal Action of Petroleum
Impacted Soil at QMS. Proposal to remove #2 fuel oil. Total cost $5,350.00.
Ltr. to MBC from Keyes re: Recommendation of approval for Change Order Proposals: #66,
#67, #72 #73 and #76 to be included in next change order. MBC approved 5-0.
QUALTERS MIDDLE SCHOOL UPDATE
JTC/Change Order #54 — Discussion opened re: C.O454 ref. Relocate wall and build for
reinstallation of washer/dryer at QMS — Total amount of proposal $9,325.29. Dan Freeman to
follow up with Chuck D'Olympia, TCI regarding the proposed relocation of the wall.
Comment was made by David Young that correspondence from J.T. Callahan varies in format.
All changes submitted by J.T. Callahan for approval should be submitted as a Change Order
"Proposal" to Keyes Assoc., not a Change Order to the MBC. The MBC will take action only on
Change Orders reviewed and recommended by the architect.
Oil Tank Removal — Chris Sullivan reported on the status of contaminated soils found by J.T.
Callahan, while excavating near cafeteria at QMS. David Young noted that the original tank was
removed in 1993. Rich Feeley noted that following any Class 1 tank removal, the area must be
certified clean. Ms. Sullivan described the fuel substance, as sticking to all surfaces around it.
Ms. Sullivan also noted that during excavation, construction crews hit perched water, which also
appears contaminated. Lincoln Environmental provided an estimated not to exceed cost of
$14,000 for contaminated water removal. Ms. Sullivan noted that the estimated amount does not
include soil removal. An estimated 9 cubic yards of material has been removed. Based on the
description of the substance, Ken Gay commented that it may be #4 oil. Chris Sullivan reported
that preliminary tests indicated a number #2 fuel. Issue pending further investigation.
QUALTERS MIDDLE SCHOOL UPDATE:
Change Order Proposals
C.O.P. #71, #72, #75 and #80 ref. Roof Blocking
Status: All proposals for roof blocking are rejected by Keyes at this time.
C.O.P. #60 Tapered Roof Insulation
Status: Ron Ashton to review. Dan Freeman noted that there was poor
coordination at Keyes Assoc. regarding this issue.
C.O.P.
#66
Valve replacement @ S. wing/Boys toilet
$ 409.00
C.O.P.
967
Cover existing sky lights
$ 168.00
C.O.P.
#72
Relocation of Grease trap and vent
$ 850.00
C.O.P.
#73
Revisions to Toilet Accessories
$1,342.00
C.O.P.
#76
Cover existing glass bloc skylights
$1,347.00
Total of #66, #67, #72, #73, & #76
$4,116.00
MOTION to approve the following Change Order Proposals as recommended by Keyes
Associates in the amount of $4,116.00 DYIWM Passes 5-0
C.O.P. Status Update - Dan Freeman distributed an updated C.O.P. log to the Committee. Jim
Liddick questioned Mr. Freeman regarding numbers missing from sequence. Mr. Freeman noted
that information could be still in the works and change order proposals coming. He will verify.
Status of RFI responses — Dan Freeman commented that Keyes is still waiting for some answers.
Dan Freeman to call TCI to have them attend job site meeting to resolve some issues.
Aluminum Doors - Doors are needed at the Front & Gym entries. The allowance carried was
$30,000. Mr. Freeman stated that the estimates came in high. Scope of work was cut, but did
not include hardware. Dan Freeman noted that 4 door sets are needed at front entry and 6 at the
gym. Cost was estimated at $7,700 per door frame, hardware excluded
Project Manager — Dan Freeman noted that he has received verbal notice that Steve MacCaffrie
will be leaving J.T. Callahan. December 28th will be his last day. Replacement not yet known.
Maso — Chris Sullivan reported that 14 Masons were on site at QMS. Masonry foundation
work should be finished this week.
Door Frames — Ms. Sullivan noted that frames came today.
Front Ramp — Chris Sullivan noted that the ramp was rubbed out by masons. Ms. Sullivan
reported that finish was now smoothed out and looks great.
Door Enclosures — Ms. Sullivan reported that temporary door enclosures are now air tight.
Kitchen Coordination — Jim Liddick questioned status. Dan Freeman reported that comments
from Crabtree McGrath are being incorporated.
Knox Box - Lt. Sarro had previously directed Walter Parker/School Dept. to install knox box at
QMS. Ms. Sullivan referenced her FAX to Walter Parker. When asked as to the status of the
delivery, Mr. Parker noted that he had not ordered it yet. Chris Sullivan to re -FAX request to
Mr. Parker.
Sprinkler System Valve replacement — Mr. Freeman reported that coordination drawings were
supposed to be provided by contractor. They were not. Dan Freeman noted that communication
within TCI seemed to be an issue re: location of placement. Rich Feeley questioned who owns
it. Valve was moved. Change order is expected.
Head End Room — Rich Feeley questioned status of coordination — Ken Gay requested that Dan
Freeman check HVAC concerns re: Music storage to be made from copy room. There is no
HVAC currently in that space.
Re: Space B9 - It was noted that a floor drain & gas line were found. If creating a chase wall
then relocation of gas line will be necessary.
Faculty baths — Chris Sullivan noted that baths are due to be back on line for December.
Schedule — Dave Young asked if subs have been given a copy of the schedule. Dan Freeman to
verify.
J.T. Callahan — Suggestion was made by David Young to have representatives from J.T.
Callahan come to the next MBC meeting to explain their management structure for MHS. Due
his past experience, Dan Freeman suggested MBC send letter to JTC requesting Mike Callahan
not be associated with this job. Noted poor performance on other community projects. Rich
Feeley noted that he would need legal grounds to do so.
Duct Pipe —Ken Gay questioned status re: duct pipe that served old front entrance. Chris
Sullivan noted that they are exploring other alternatives to resolve issue.
ROBINSON SCHOOL
School Furnishings — Committee received a request for additional furnishings needed from Leo
Sciarappa, Principal. School Furnishing budget has been used. MBC to forward to Bob Gurek
for determination as to how to handle financing. David Young asked if schools could fund the
expense out of the $180,000 account.
Epoxy floors — Rich Feeley noted that J.T. Callahan has responded stating that repairs will be
completed in December.
MANSFIELD HIGH SCHOOL
MHS Project Coordinator - Committee reviewed resumes; secretary to schedule 4 interviews.
Notice to Proceed — MBC reviewed draft of Notice to Proceed to be sent to J.T. Callahan from
Town Manager.
Status of Documentation - Richard Feeley asked Jim May as to the status of documentation for
MHS. Mr. May reported that the drawings and specs went to Fire Dept. last week. They are
currently waiting for Fire Dept. plan. Mr. May noted that the Building Dept. would not review
plans until Fire Dept. has reviewed them.
Independent Structural Review — MBC to send a letter to Albin PilBlad, P.E. Structural Engineer
requesting quote for peer review of MHS.
Original plans — Rich Feeley requested that Wallace Floyd have one conformed set of drawings
sent to the MBC. The Contractor is to receive documents in the same format as was what was
issued during the bid period.
Painting Bids - 2 copies of the same addenda were issued during the time of bidding. Paint bids
were disqualified due to some contractors picking up the first addenda and others picking up
after additions to the plans. The allowance carried for paint is $200K. MBC agreed to move
forward to re -bid. Jim May will coordinate. Mr. May stated that notification will be given to the
the Central register and all previous bidders.
Coding System - David Young reiterated the need for all correspondence to be clearly identified
as to the name of the project. The suggestion was made to use the letters "HS" to mark
correspondence to identify the High School.
Abatement - J.T. Callahan will need the documents from Universal Engineering re: abatement.
Contract documents will need to be reproduced. MBC to notify Ammar Dieb that the MHS
Project is going forward and request that they prepare contract documents to send to the
contractor re: abatement — J.T. Callahan to get the 3 bids needed.
MHS Bid Withdrawals - Jim May will draft letter to release bids for TM to send out.
Wallace Floyd - Rich Feeley discussed several issues with representatives from Wallace Floyd
regarding the High School Project:
• Management Structure - Jim May, David Burson, and Ammir Degany, will be involved in
the high school project. Jim May will be our primary contact.
• Correspondence - Richard Feeley requested that the MBC be copied on all correspondence
relating to the MHS Project.
• Job Site meetings — Rich Feeley noted that meetings are held weekly. Jim May will be
attending. It was noted that the civil and structural is done by Keyes.
• Payment — Rich Feeley questioned Wallace Floyd as to payment procedure. David Burson
noted that they bill 5% out on CD's.
• Review of Change Order Proposal/Change Order — Rich Feeley explain the procedure in
reviewing C.O.P's prior to the submission of a Change Order for any item.
• Pre Construction Meeting — Date has not yet been determined.
MHS Contract - David Young asked that Jim May address Bob Mangiaratti's directive to include
all addenda with the contract documents. Jim May suggested that the contract include request for
schedule
Fencing — David Young requested a response as to what is specified for site security i.e.. fencing
in the High School Specs. Jim May to follow up.
Parking — It was noted that parking during construction is currently designated in rear of MHS.
Jim Liddick suggested that School Dept be notified re: loss of ball field spring 1999.
TV Studio at MHS - Dave Burson noted that they have met with Cable Access TV — They are on
line for Construction costs. MBC has not yet been directed to coordinate construction of this
project. Discussion re: Location
NEW BUSINESS -
Charter Revisions: David Young distributed and reviewed a written response to the proposed
revisions to the Charter. Board of Selectman is planning to hold a public meeting with Town
Boards/Committees and Charter Review Committee. David Young noted that positive changes
could be made to the Charter via a warrant article on town meeting floor.
MOTION to accept the statement as written by David Young on behalf of the Municipal
Building Committee. The statement will be submitted to the Board of Selectman and Town
Manager re: Revisions to Town Charter. JL/WM Passes 5-0
Respectfully submitted,
Eleanor A. McCarter, Secretary
Mmes Liddick, Clerk Date