TOWN OF MANSFIELD
Municipal Building Committee
Meeting Minutes of April 6, 1999
Members Present: Richard Feeley, Chairman, James Liddick, Clerk, Kenneth Gay,
William Moore, David Young and Eleanor McCarter, IN
Attendees: Ron Ashton, Keyes Associates
Michael Callahan & Marc Jaoude, J.T. Callahan & So
Christina Sullivan, QMS Project Coordinator
Walter Parker, School Building and Grounds Manager
Mark Cook, DPW Highway Manager
Michael Ahern, Special Projects Manager, Town of Ma
Meeting commenced at 7:00 PM.
QUALTERS MIDDLE SCHOOL
Force Main - Wastewater force main from pumping station under bus loop at big
again about 40 feet from public sewer. Location of break is about 2 feet from pre
caused by T.T. Callahan. Mark Cook and Mike Ahern (DPW) to investigate feasi
4" PE pipe through 6" transite pipe. DPW to obtain (2) two price quotes.
Kitchen Needs Walter Parker reported request from Dawn Florence, School Kit
Director asking to switch Vulcan stove specified by contract to Garland stove (ga
would result in $1600.00 cost savings.
MOTION made subject to receipt of a specific letter from School Kitchen Se
AMC approves School Dept. request to substitute the Vulcan brand stove (sp
con
Mia
MG
and
DY
Priti
grin
Mc
Parker advis
T local Fire 1
iorize $280(
Idle School.
5-0.
Walter Par]
School Del
to authorize
nested by S
Windows — Delivery of all
extras incurred.
Auditorium Louvers - Still
1 stove unit. DY/WM: Passes 5-0.
broke
eak/fix
pulling
a key box is needed for Mansfield High School and Qualters
)ector.
) for the purchase of a key box for Mansfield High School
ehool Department to coordinate purchase.
asked MBC cover $31.00 expense for additional construction
ent of $31.00 for additional copies of construction
Dept. WN/KG Passes 4-1. David Young voted against.
are due next week. Cheviot to pay JTC for cost of
price for auditorium fire louvers.
Heat - Committee discussed deletion of overhead heat units from original QMS entrance way as
there are sufficient heating units in the area.
Sidewalk Concerns — Question raised regarding sidewalks moving up and down. Question raised
whether movement was due to frost.. Additional concern was raised about possible trapping
water. Need to follow up with Michael Callahan and Marc Jaoude (JTC).
Gym Ceiling Repair — Issue re: significant spalling in gym ceiling caused by subcontractor's use
of improper size materials. Test patch on QMS gym ceiling to be done during April 1999 school
vacation. Project Coordinator Chris Sullivan is investigating possible alternative repair options.
Roof Flashing JTC submitted Premier Roof revised cost in the amount of $138,000.00 vs.
$102,000.00. Reason stated for increasedamount was because Dan Freeman (Keyes Assoc.)
advised that MBC had rejected $5,000.00 cost requested by JTC. MBC only asked for back up
at that time (i.e. up-to-date Release of Liens). Amount to be further evaluated.
JTC Mark-up Charge JTC requested higher mark up be allowed; 15% for work performed on T
& M basis and 8% for sub -contractors. JTC wants 20% to cover excessive administration costs
on small projects. Comparable Keyes' Projects are 17.5% and 8%. Per JTC, no one else has
questioned mark up percentage on their projects. Rich Feeley responded that most T&M work is
for unforeseen conditions. Very few for lump sum proposal rejections. Montle really only
subcontractor not realistic with quotes. No chane to mark-up approved. Marc Jaoude to submit
cash flow for QMS and MHS. '
JTC/QMS Requisition' for Payment #9
MOTION to approve 'payment ito J.T. Callahan & Sons in the amount of $636,139.83 for
construction' work related to the Qualters Middle School Renovation Project. Application
for Payment' includes the following COP'S #27, #77, #84, #88, #108, #112, #118, and #120.
DY/WM Passes 5-0.
MANSFIELD HIGH SCHOOL
Paving — JTC to reclaim parking lots working around light poles.
Fencing Ken Gay noted fence in rear to secure construction site was not installed by JTC.
ROBINSON ELEMENTARY SCHOOL'
Punch List Need final Punch List signed off from Keyes Associates. Per Ron Ashton, this will
be resolved in two weeks.
• Bollards - Walter Parker installed bollards at gas meter required by local inspector.
• Certificate of Occupancy`- Still need final Plumbing Inspection.
• Epoxy Floor Re: unsatisfactory colors. Need to correct color or request credit.
• Utilities — Architect to generate unilateral change order for utility credit due to Town.
• Dead trees have still not been replaced by contractor.
• Cost incurred for freezer repair $610.00.
0 Dishwasher electrical tie-in. Walter Parker to coordinate work.
OTHER
Request for Legal Opinion — Town Counsel (Max Volterra) to issue opinion to MBC about
issuing direct payments.
Meeting adjourned at 10:30 PM.
Respectfully submitted,
Eleanor McCarter, Secretary