Loading...
HomeMy WebLinkAboutMBC 04/13/1999TOWN OF MANSFIELD Municipal Building Committee Meeting Minutes of April 13, 1999 Members Present: Richard Feeley, Chairman, James Liddick, Clerk, Kenneth Gay, William Moore, David Young (8:00 PM) and Eleanor McCarter, Secretary Attendees: Walter Parker, School Building and Grounds Manager James May, Wallace Floyd Design Group Meeting commenced at 7:10 PM. MANSFIELD HIGH SCHOOL School Dept. Issues - Jim May met with high school staff and Principal to review construction related issues. School Department needs to submit any future change requests to the MBC in writing. MBC does not want direct requests made by JTC. Legal Opinion/Keyes Associates — MBC requested legal opinion re: Town's Direct Payment obligations under the present contract with Keyes Associates. Attorney Max Volterra responded that Chapter 39 Section 39F provides for direct payment demands for contracts awarded under Chapter 149. Since the Town's contract with Keyes Associates was not awarded under Ch. 149, Keyes Associates is liable to the Town for non-performance by Keyes or their sub -consultants. TV Studio — Bid date is 5/11/99. Paying — Press release was issued informing school parking lots will be closed for reclamation. BuildingPer ermit — MHS received full building permit. Wall Penetrations — Jim May to evaluate new wall penetrations and sealing of existing penetrations. Construction Schedule — Project schedule submitted by JTC is incomplete. MBC advised no further payments would be made to JTC until contractor submits a full construction schedule. Phase II - Summer Schedule reflects work in library, classrooms, and Bldg. & Grounds Office. School Furnishings — MBC advised the School Dept. to address issue of ordering school furnishings for QMS and MHS early. Lead times will vary based on the item ordered. Construction Meeting Minutes — Question raised regarding Architect's responsibility to record meeting minutes vs. Contractor. Comment made that issues may not always be presented fairly in having Contractor prepare weekly construction meeting minutes. MBC to check General Conditions re: Architect's responsibilities re: recording minutes. Need Architect to review minutes prior to issuing as final. COMPOST FACILITY General Update was provided by MBC member William Moore INVOICES Keyes Associates - QMS MOTION to withhold all payments to Keyes Associatesuntil notification that all Keyes' sub -consultants are paid up to do MBC receives written Letendre CompanX — MHS fount of $2,160.00 for Project is ending April 3, 1999 .0 1999 and Ap: 1999 ($1,200:00). ';` S of $2400.00 for ending April 10. ,1999. WM/JL: Passes 5-0 at 9:10 PM. tted, Secretary James E. Liddick, Clerk' 2/z/!�7-- Z-- E:7 z v Date