HomeMy WebLinkAboutMBC 07/27/1999TOWN OF MANSFIELD
Municipal Building Committee
, ;_ Meeting Minutes of July 27,1999
0o cFr
Members Present } 13 Richard Feeley, Chairman, Jim Liddick, Clerk, Ken Gay
'4illiam Moore and Eleanor McCarter, Secretary
VA (R David Young — Excused
Attendees: Christina Sullivan, QMS Project Coordinator
Bob Vogel and Steve Chmura, Keyes Associates
Paul Letendre, MHS Project Coordinator
Jim May, Wallace Floyd Associates
Walter Parker, School Building & Grounds Director
Meeting commenced at 7:20 PM
CORRESPONDENCE
General
Ltr. to MBC from Steven MacCaffrie re: General concerns regarding school construction.
Mansfield High School
To MBC from Wallace Floyd Assoc. Re: Architects Bulletin Log.
To MBC from Wallace Floyd Assoc. Re: Status Log.
To MBC from Wallace Floyd Assoc. Re: JTC/Change Order #2.
Ltr. to Paul Letendre from TCI Re: Electrical Existing Conditions,
To MBC from Wallace Floyd Assoc. Re: Modifications to library ductwork/ceiling plan.
Ltr. to MBC from J.T. Callahan Re: Summer changes/Schedule.
Ltr. to MBC from J.T. Callahan Re: Response 7-12-99 Itr. from MBC ref schedule delays.
Ltr. to Wallace Floyd Assoc. from J.T. Callahan Re: Roof Submittals.
To MBC from J.T. Callahan Re: C.O.P. #25 Ref. Upcharge for quick door delivery in the amount
of $3,680.00.
To MBC from J.T. Callahan Re: COP #26 PR -022 Infill 2 doors @ room 179 in the amount of
$469.00.
To Wallace Floyd Assoc. from JTC Re: RFI #76 Ref. Grouting at Stair Wells.
Wallace Floyd Assoc. Architect's Bulletin 038 -SI Ref. Reissue of Drawing SE -8 from Keyes.
Wallace Floyd Assoc. Architect's Bulletin 039 -PR Ref. Modify pathway on south side new West
Wing Addition to include a stair.
Wallace Floyd Assoc. Architect's Bulletin 040 -PR Ref. Modify hallway connection at New
South Wing Addition to include (2) 4" CMU column enclosures.
Wallace Floyd Assoc. Architect's Bulletin 041 -CCD Ref. T&M to raise existing blower unit
associated w/ductwork in order to avoid conflict w/walk-in refrigerator & freezer in kitchen.
Wallace Floyd Assoc. Architect's Bulletin 042 -SI Ref. Issue of Floor Tile Pattern Plan Al -16.
Wallace Floyd Assoc. Architect's Bulletin 043 -SI Ref. Reissue of Drawing P-12 from TCI.
To Wallace Floyd Assoc. from J.T. Callahan Ref RFI #56 Quinn Brothers: Rail attachment to
the existing stair stringers.
To Wallace Floyd Assoc. from J.T. Callahan Ref. RFI #59 Yankee Sprinkler: Location of zone
controls.
To Wallace Floyd Assoc. from J.T. Callahan Ref. RFI #63 JTC: RTU on Cafeteria Roof.
To Wallace Floyd Assoc. from J.T. Callahan Ref RFI #73 Eagle Door/Hrdwre: Pre finish color
To Wallace Floyd Assoc. from J.T. Callahan Ref RFI #74 Eagle Door/Hrdwre: 5/8" cut size.
To Wallace Floyd Assoc. from J.T. Callahan Ref. RFI #76 Quinn: Grouting @ stair wells.
Qualters Middle School
Ltr. to MBC from J.T. Callahan re: Schedule/Changes
Ltr. to MBC from Steven MacCaffrie Re: Delay of response to door/hardware RFI
Ltr. to MBC from Steven MacCaffrie Re: Construction concerns at QMS.
Ltr. to MBC from J.T. Callahan Re: Changes/Schedule.
Ltr. to MBC from J.T. Callahan Re: Unplug Fire Box.
Memo to MBC from School Bldgs. & Grounds Re: Telephone lines for elevator.
Ltr. to Keyes Assoc. from J.T. Callahan Re: Request for Inspection for Elevator #1 in Z2.
Ltr. to Keyes from J.T. Callahan Re: RF1 #125 Ref. Kitchen floor drains.
To MBC from J.T. Callahan Re: C.O.P. #116 Ref. ASI -10 Padding @ Gym (Revised)
To MBC from J.T. Callahan Re: C.O.P. #168 Ref. Hollow Metal Frames.
To MBC from J.T. Callahan Re: C.O.P. #170 Ref. '/4" Tempered Glass
Ltr. to MBC from J.T. Callahan Re: Cheviot: Wood Blocking.
Ltr to MBC from J.T. Callahan Re: Missing Sprinkler/Heat Detector at Elevator.
MANSFIELD HIGH SCHOOL UPDATE
Schedule Delay Discussion re: letter from J.T. Callahan ref. delays to the MHS project. Jim
May commented that the reasons cited by JTC for causing delays were unsubstantiated. Issues
relating to lintels, metal flashing and hardware etc. were resolved weeks ago. Rich Feeley asked
Jim May to send letter of response to JTC.
HVAC — Project Coordinator noted existing clearance issues found throughout building.
Conduit is not properly supported. Electrical issues will be rectified.
Manpower — Paul Letendre reported that since the MBC's recent discussions with 7.T. Callahan
re: acceleration, manpower is increased and subcontractors have been more cooperative on site.
Supervision by JTC has also been more visible in the field.
Cafeteria — Project Coordinator stated that cafeteria should be ready Aug. 26, 1999.
Paul Letendre reported that most of the pending questions have been clarified. The ductwork is
ready for fabrication.
Libra — Sketches have been received relating to conflict with ductwork at Library. Issue is
resolved.
Chemistry Lab. — TCI reviewing location of new unit.
Force Main — Water shut-off is expected during the first week of August. Dig Safe has been
notified. Paul Letendre will notify Chris Sullivan and other necessary parties.
Change Order #2 — Change Order #2 was rejected as presented. MBC questioned status of large
outstanding credits due to the Town that were not reflected in the Change Order (i.e. ball field,
resinous flooring etc.) Jim May will follow up with Marc Jaoude to include the credits due.
MBC takes exception to all time increases to contract as indicated by JTC.
Roof Shingles — Original objective was to try to match roof shingles for MHS to the shingles
used at the Robinson School. Jim May stated that the roofer has not provided a shingle that
meets requirements. Proposal was rejected. Roofer to resubmit. MBC requested laminated
architectural shingles. Shingles must have 30 year warranty.
Gypsum Decking —Jim May commented that an allowance of 10,000 sq. ft. was carried to
destroy gypsum deck. Mr. May reported that the vapor barrier appears to have saved gypsum.
Credit to the Town is expected.
Perimeter Blocking — Mr. May reported that the existing perimeter blocking is being reused.
Credit is expected.
Roof Decking System Jim May noted that credit is also expected for the roof decking in the
South Addition.
Next MBC Meeting -Jim May noted that he would not be available for the next meeting of the
MBC as he is on vacation next week.
QUALTERS MIDDLE SCHOOL UPDATE
Door/Hardware Schedule —Construction Consulting complaint received re: Keyes delayed
response time to RFI. Steve Chmura commented that the issue has been pending a response
from Walter Parker as to the availability of doors from school stock. Mr. Parker commented that
doors are not core doors and therefore could not be used. Mr. Chmura will move forward to
resolve issue with Construction Consulting. New doors will be ordered. Estimated delivery for
doors will be approximately 4 weeks.
Accelerate Schedule — Project Coordinator commented that the acceleration period is through
Sept. 1, 1999. Half time pay rate is for trades only impacted by the SMI issue. Letter to be sent
from MBC to J.T. Callahan requesting a proposed acceleration schedule, specific trades
authorized to accelerate and required manpower to staff job.
Cafeteria — Work in the cafeteria is moving along well
Kitchen Floor Drain —Project Coordinator reported issue with approximately 6 drains specified
in Kitchen area. Some have flashing collars, some do not. Collars are necessary to prevent
leakage and have been ordered. Approximate cost $500.00.
Final Cleaning — School Dept. proposed that the school staff do final cleaning. Committee
responded that the contractor owns final cleaning by Contract. The Project Coordinator noted
that if school personnel help with the final cleaning they must be under the direction of the
Contractor for the hours required. Due to possible conflict in schedule and liability, it was
decided that the Contractor would do final cleaning.
Punch List/2"d Floor - Classrooms to be punched on Thursday, July 29, 1999.
Lockers — Lockers should arrive during the second week of August, 1999.
School Furnishings — Walter Parker reported that deliveries are expected the week of August 13°i
through August 16, 1999.
Elevator Inspection —Project Coordinator noted that a Request for Inspection has been made.
Chris Sullivan will call Signet to get phone lines delivered. Walter Parker has ordered 3 lines for
elevator. Telephone lines — Walter Parker questioned need for dedicated phone lines for Thyssen
Elevator. Dedicated lines are required by code. Chris Sullivan to follow up.
Unit Ventilators — 7 out of 9 are completed.
Windows — Cheviot Corp. is on site and currently working on the 2"a floor.
Fleet Environmental - Chris Sullivan reported that Fleet is performing abatement work
satisfactorily as expected. Fleet is expected to accept draft of agreement with the town as written
and amended by Attorney Russell F. Conn.
Project Administration — Project Coordinator commented that she has not been receiving written
correspondence from J. T. Callahan.
MOTION to move forward to order 100 pieces of 1/4" safety glass from Bristol Glass at
$48.00 each. Walter Parker to place order. KG/WM Passes 4-0
Meeting adjourned @ 9:20 PM
Respectfully Submitted,
Eleanor McCarter, Secretary
< ZA -t- �_ ��
Ames Liddick, Clerk
Date