TOWN OF MANSFIELD
Municipal Building Committee
Meeting Minutes of August 10, 1999
�#}berks FtitEe'�rfa Richard Feeley, Chairman, Jim Liddick, Clerk, Ken Gay
William Moore, David Young and Eleanor McCarter Secretary
Attendees: John Moretti, Mansfield School Superintendent
Paul Letendre, MHS Project Coordinator
Jim May, Wallace Floyd Associates
Christina Sullivan, QMS Project Coordinator
Steve Chmura, Keyes Associates
Michael Callahan, Bruce Hanna, Tony Messina, and Marc Jaoude
J.T. Callahan & Sons Inc.
Meeting commenced at 7:00 PM.
CORRESPONDENCE
General
To MBC from Bea Kearney re: Dept. telephone billing -August
To all Depts from Karen Doucette re: Breast Cancer Walk — October 3, 1999.
Qualters Middle School
Ltrs. to JTC & Keyes from William Moore re: Request to include two week look ahead schedule
and critical RFI's in Construction Meeting Minutes.
Ltr. to Keyes from J.T. Callahan re: July Requisition for Payment.
Ltr. to JTC from Keyes re: Responses to RFI #101, #107, #108, #112 and #113.
Ltr. to MBC from J.T. Callahan re: Intrusion Alarm System.
Ltr. to MBC from J.T. Callahan re: RFI #127 ref. Montle: Storm Drain Piping Rm. GT -G.
To MBC from J.T. Callahan re: C.O.P. #171 ref. Acceleration
To MBC from Keyes re: Construction Meeting Minutes #53.
To MBC from J.T. Callahan re: Change Order #12.
To MBC from J.T. Callahan re: Application for Payment #13 (including construction schedule).
Mansfield High School
Ltr. to Keyes from Wallace Floyd Assoc. re: Receiving copies of Keyes invoices submitted to
the Town of Mansfield for payment.
To Fire Dept. from Paul Letendre re: Proposed locations for fire extinguishers/new additions.
Ltr. to J.T. Callahan from Paul Letendre re: Electrical sub contractor QRW Company) showing
lack of urgency to complete scheduled work.
Ltr. to Wallace Floyd from Paul Letendre re: RFI's difficult to read. Request for original copy.
Ltr. to J.T. Callahan from Paul Letendre re: Raising existing kitchen clean-out/floor drain covers.
Ltr. to Wallace Floyd from Paul Letendre re: Disparities found between finish paint schedule and
specs.
To MBC from J.T. Callahan re: RFI #85 ref. Costa #10 — revised brick detail.
To MBC from J.T. Callahan re: RFI #86 ref. Commercial: Glazed CMU w/block walls.
To MBC from Paul Letendre re: Project Coordinator Daily Log Reports.
To MBC from WFA - Bulletin #050 -SI Ref. Color change to kitchen quarry tile.
To MBC from WFA — Bulletin #051 -SI Ref. Structural steel member sizes at the in -fill framing
@ existing greenhouse curb.
To MBC from WFA — Bulletin #052 -SI Ref. Proposed locations for Fire Extinguishers in South
and West wing additions.
To MBC from WFA — Bulletin #053 -SI Ref. TCI response: Concealed supply ductwork does not
require Class 135 insulation.
To MBC from WFA — Bulletin #056 -CCD Ref. Directive to proceed with raising existing
kitchen clean out and floor drain covers to meet height of new quarry tile.
To MBC from WFA- Bulletin #055 -CCD Ref. Directive to subcontractor to proceed with
painting in kitchen and cafeteria.
To MBC from WFA — Bulletin #054 -PR Ref. Norfolk Mechanical: Request for cost proposal to
install necessary valves and components for re circulation system.
QUALTERS MIDDLE SCHOOL
Cafeteria Issues:
• Flooring - Contractor plans to install quarry tile in cafeteria this Friday (8-13-99).
• Kitchen Equipment — MBC questioned status of equipment delivery. Paul Ciaramitaro
verified that equipment is in warehouse. Pieces are arriving daily to site.
• Drywall - Per JTC, drywall is installed. Contractor is putting up seven soffits. Per JTC, work
to be completed by Wednesday. Two large soffits remain to be completed.
• Ceiling - Work should start by Monday. Issue raised re: extended ductwork. Sizing does not
fit through grid. Remaining ceiling work to be performed the week of Aug 23, 1999.
• Kitchen Flooring - Tile needs to be installed. Estimated timeframe for installation is 3-5 days.
• Walk in freezer units — MBC noted that quarry tile is owned by JTC under walk in area and
directed Contractor to proceed with work.
• Additional ductwork was done for lighting.
• Sprinkler - Complete.
• Columns - Michael Callahan noted that JTC has additional crew scheduled to install covers
for columns this week -end.
• Rain leader - Suggestion was made by MBC to enclose the rain leader that follows steel
column in cafeteria as soon as possible.
Windows — Installation is incomplete. Contractor advised MBC of a manpower issue. Installer
needs more time to pull together crews. MBC stressed that installation of instructional room
windows are priority to open school for September. Stairwell windows are secondary priority.
Per JTC the South Wing could be done by end of week and the West Wing windows by middle
of next week.
Lintels - Issue was raised re: status of lintels. JTC responded that window lintels are fine in most
locations, however all I'` floor windows are being reinforced. Sarkis Zeronian previously
determined that 2"d floor would be left as is. Comment was made that the Structural Engineer
has not reviewed windows recently. JTC has asked Keyes to contact Structural Engineer to visit
site and review.
Window Conflict - Discussion re: windows being installed in conflict with walls and/or columns
making them inoperable. Bob Vogel argued that operable windows are not "technically" required
and that fresh air is increased with installation of new unit ventilators. Superintendent John
Moretti commented that the current window installation is unacceptable. MBC reiterated to
Keyes Associates that long term, the School Dept. and MBC would be held accountable to the
community as to why the windows do not open. A temporary fix is critical to enable school to
open in September however, MBC Chairman asked that Bob Vogel explore a permanent long
term fix to make windows operable. JTC stated no interest in installing any more windows at
this time. Keyes Assoc. directed JTC to proceed with installation of windows per contract.
Nurse' Area — JTC reported major holdup, in waiting to receive responses to RFI's re: piping to
be abated, moved, and ductwork changes. Estimated date to complete this work is Sept. 10,
1999.
Soundproofing issues — Windows are currently higher than ceiling height. Ceiling will be
lowered to complete installation of lights. Sash may need to be removed. Central Ceiling Inc.
recommended to vault ceiling up and boxed window. Estimated cost $7,000.00. MBC asked
Chris Sullivan to direct contractor proceed with this work.
Generator — School Dept. intent is to replace existing generator. MBC requested that Project
Coordinator contact Inspection Services to discuss condition of temporary permit.
Sills — Chairman reported that sills are falling apart. JTC does not own resetting slate sill.
Summer Acceleration — MBC expressed frustration with subcontractor's providing insufficient
manpower during regular work hours. Agreement was made to authorize specific trades (i.e.
McLaughlin, Cheviot, Electrician,) to increase work forces to address critical needs required to
re -open school Fall, 1999. Chairman requested JTC provide a project schedule and print out of
staff working on Saturday.
Schedule Issues:
Final Cleaning Z2 — Scheduled for Wednesday July 11, 1999. JTC responsible for final
dusting. Subcontractor will be on site.
• Lockers — JTC noted lockers are not on site and therefore will not be installed by opening of
school.
• Punch List — Z2 to be provided to Keyes Assoc. by August 12, 1999. JTC to complete by
August 25, 1999.
• Paving - scheduled for Aug. 30a'. Town event (Mansfield Family Day) is scheduled to use
parking lot area on August 28, 1999. MBC to notify JTC and requesting final paving after
August 28, 1999.
Elevators:
Elevator #1— Request for final inspection. TCI indicated smokes/heats devices are not
needed by code. Thyssen VP indicated that smoke detector in heat room and hoister is
required. Keyes Associates to verify and follow up.
t • Elevator #2 — Issue re: leaking water in existing foundation. Debrino has been contacted by
JTC two previous attempts to fix leaks were unsuccessful. Issue pending.
• Phone line to elevator— Chris Sullivan to contact Signet re: hookup,
Backflow Preventor — JTC to direct subcontractor to install per contract.
Heat detector/Crawl Space — Waiting for plan from TCI re: additional heads required by Fire
Dept. (Lt. Sarco). Keyes to follow up with TCI. Chris Sullivan noted that there is no crawl
space located in South Wing.
Wall finishes - JTC noted that finishes would not be complete prior to school opening.
Loose Wiring — Issue raised re: existing wires not secured properly. Use of lines unknown.
Keyes to determine who owns. Work to be completed based on Time & Materials.
Gym Ceiling — Previous issue re: damage to ceiling caused by contractor. Test repairs in two
locations is complete. Bob Vogel approved gray satin paint. Complete repair is expected prior to
school opening.
Project Administration — Project Coordinator expressed frustration about the lack of
correspondence from contractor. Michael Callahan directed Marc Jaoude to copy Project
Coordinator, MBC and Keyes.
Change Order #12 — Committee reviewed Change Order number 12 including
#69A Install Hollow Metal Frames Change Order Proposals previously approved by MBC.
MOTION to approve JTC/Change Order #12 in the amount of $164,412.00.
JL/DY: Passes 5-0.
JTC/Application for Payment —MBC asked if Release of Liens have been provided. Project
Coordinator confirmed that JTC has copies. Marc Jaoude to deliver to MBC in the morning.
MOTION to recommend payment to JTC for work performed at Qualters Middle School
in the amount of $924,972.68. DY/JL Passes 5-0.
MANSFIELD HIGH SCHOOL
Project Schedule — Project Coordinator reviewed schedule as provided by JTC. David Young
pointed out that site work not identified on schedule. Roof membrane needs to be included.
Elevator also not included.
Cafeteria Flooring — Tony Messina commented that quarry tile will be started on Monday. RLM
Flooring estimates 3 days to complete work.
Manpower —Project Coordinator commented that JTC has been working Saturday doing site
work plumbers, electricians, and roofers. Letter received from subcontractors requesting
accelerated rate of pay.
Cafeteria — Tony Messina stated that the cafeteria would be ready to occupy by Sept. 6, 1999.
Subcontractor owns sealing VCT. Michael Callahan commented that a temporary wall may be
needed between courtyard and existing cafeteria. School Superintendent is aware and does not
object to temporary wall.
Kitchen —
• Large soffit wall needs to be built.
• Tony Messina reported that oven hood, freezer and refrigerator will not be delivered until
August 20'.
• Ansil system is needed for hood.
• Shipping date for stainless steel counters is August 16, 1999.
• RTU3 — Units to be set
Inspections — Paul Letendre contacted plumbing and electrical inspectors requesting site visit to
identify issues that contractors may need to be address in kitchen and cafeteria to obtain
temporary occupancy permit. A representative from J.R.W. is on site to resolve code issues.
JRW is not authorized to receive accelerated rate of pay.
Glazed Block — Complaint from Commercial Painting re: finish in kitchen and other areas. Jim
May commented that the intent was that all walls would be painted. Commercial will be directed
to proceed under protest. JTC has requested a bond but has not yet received.
Force Main — Change order work projected as 4 days took longer than expected.
Work is complete. Control package for new tank is included inside pump chamber tank. No
provisions for alarm on new tank. Tony Messina noted that an alarm system is in the building to
alert high water. JTC does not own. Committee agreed that alarm to building is needed. Jim
May to follow up.
Roof Hatch — Discrepancy found at top of spiral stair. It was determined 3 x 2 x 6 dimensions is
fine.
Job Site Meeting — Scheduled for Monday at 10:30 PM. JTC to return on August 23, 1999 MBC
agenda.
Site Fencing — Chairman expressed concern re: lack of fencing. Fence taken down for mason.
Michael Callahan noted that JTC would reinstall fencing.
Roofing —'/2 completed with area A. Shingles will be on Wed. site 8-I1-99.
Project Coordinator noted that work forces would be augmented.
Sprinkler - Per Project Coordinator, work is complete in South Wing.
Paving - Binder coat to be installed next week. Haller Testing to do compaction test.
Kitchen/Plumbing —Plumbing in Kitchen area is roughed in.
Elevator — Signet system is in place. Bldg. & Grounds has not contacted anyone to date. Paul
Letentre will call Bell Atlantic to set up dedicated line for elevator located in South Addition.
Condition of Elevator pit is dry. Chairman asked that the Project Coordinator investigate state
requirement of smoke detector/sprinkler head needed.
INVOICES:
1 STOP BUILDING SUPPLY - QMS
MOTION to recommend payment to 1 STOP BUILDING SUPPLY in the amount of
$2,306.00 for temporary window protection needed at Qualters Middle School. SMI to be
back -charged in the amount of $2,206.00 for 158 sheets of structural wood sheathing.
JL/DY Passes 5-0.
Mini Warehousing Inc. - QMS
MOTION to recommend payment to Mini Warehousing Inc. in the amount of $80.00 for
storage rental for the month of August, 1999. JL/DY Passes 5-0.
Meeting adjourned 10:45 PM
Respectfully Submitted,
Eleanor McCarter, Secretary