TOWN OF MANSFIELD
Municipal Building Committee
Meeting Minutes of August 31, 1999
Members Present: Richard Feeley, Chairman, James Liddick, Clerk, Kenneth Gay,
William Moore, David Young and Eleanor McCarter, Secretary
Attendees: Steve Chmura and Bob Vogel (8:15 PM) Keyes Associates
Christina Sullivan, QMS Project Coordinator
Michael Callahan, Bruce Hanna, Phil Ricci and Marc Jaoude, JTC
James May, Wallace Floyd Design
Paul Letendre, MHS Project Coordinator
Walter Parker, School Buildings and Grounds Manager
Lincoln Lynch, School Business Manager
Michael Ahern, Special Projects Manager -Town of Mansfield
School Committee (all except Jean Miller)
Meeting commenced at 7:00 PM.
HUTCHINSON PROPERTY — Mike Ahern reported DPW plans to construct a 12' x
16' block building at the Hutchinson property site. Professional Engineer stamped
drawings are needed for file.
MANSFIELD SCHOOL PROJECTS
Final Building Inspections — MBC stressed critical need to have all inspections done prior
to opening of schools. Per Michael Callahan, inspection for Occupancy Permits for QMS
and MHS are scheduled to occur September 2, 1999.
MANSFIELD HIGH SCHOOL
JTC/Manpower - Michael Callahan introduced new Site Supervisor, Mr. Hanna replaces
Steven MacCaffrie in this position.
Kitchen — Contractor plans to have kitchen area open by September 15, 1999.
Cafeteria —
• Flooring to be installed this week. Need to empty corridors by Friday.
• Original Cafeteria window wall material was plate glass. New window wall is
installed. Glass was changed to safety glass.
• Need to check working condition of existing dish room fan.
Cleaning - David Young suggested School Dept. reduce back -to -school cleaning efforts
in corridors due to construction activity in this area. Linc Lynch and Walter Parker were
opposed to reduction in cleaning work however advised MBC that the School
Superintendent could make that decision. Walter Parker would supplement cleaning
efforts with S.O.S. Cleaning Service ($50/hr.).
( Temporary Occupancv — Concern raised regarding approval sign -off for Temporary
Occupancy Permit not provided by local Plumbing Inspector Connie Lajoie. Building
Inspector Nick Riccio had no occupancy issues.
School Meeting — MBC was advised of School Dept. plans to hold a large reception (500
guests) on Tuesday morning September 7, 1999
Lighting Issues - Decision made to delete additional lighting in new library addition.
Need to push Contractor to complete site lighting and baseball field fence.
Paving — Initial paving was installed yesterday (8-30-99). Tack coat was used. Per
contractor, line work to be installed within the next two days. Concern was raised re: line
coloring. This needs to be re -done.
Windows — Mock-up is complete.
Fencing — Fencing is being installed.
South Addition — Anticipated date of completion is November 1, 1999.
Acceleration — A lump sum of $15,000.00 was previously authorized for premium time
work necessary to enable school to open for occupancy in September, 1999. Concern
was raised by MBC that T&M work is being billed on premium time as well as other
abuses of agreement. General disagreement exists over how T&M acceleration work was
authorized.
QUALTERS MIDDLE SCHOOL
Administration — Administration Office moving in this Thursday.
Cafeteria — Installation of floor tile expected to be complete by end of day Thursday,
September, 2, 1999. Need School Dept. to seal floor at night.
Freezer — Jacob Leite scheduled to start freezer tomorrow.
Lockers — Lockers located in Zone H were installed earlier that day.
Existing Generator - Discussion opened as to whether the existing generator needs to be
replaced. Local Inspectors had initially discussed with TCI that replacement was not
required. School Dept. recently awarded a one year contract (7-1-99 to 6-30-00) to FM
Emergency Generator, Inc. the bid for Emergency Generator Service Repairs. In order to
purchase a new generator unit, F&M Generator would need to pull permit and provide
licensed electrician to install. Generator design also needed to relocate unit on site.
Chris Sullivan and Walter Parker to coordinate.
Fire Alarm System — Fire Inspector Joe Sarro expected to test fire alarm system
tomorrow. Chief Sliney, Lt. Towne and Lt. Sarro did walk-through last week.
Door Hardware — Walter Parker agreed to install door hardware in (8) existing
bathrooms.
Elevator Permit — Elevator occupancy permit not needed at this time. Issue raised
regarding heat detectors and/or smoke detectors needed. Code requirement is not clear.
Issue pending further investigation.
Auditorium — Contractor needs to install smoke detectors in Auditorium
Wood Shop — Contractor has fallen behind with work in this area
Gym — Question raised regarding School Dept. plans to hold 6th grade orientation in the
gym. Construction activity is currently ongoing in this area.
Sidewalk — Sidewalk currently being added.
Boiler Start-up — Bruce Hanna and Walter Parker to coordinate appropriate time to start
up new boilers early and do week -end burn -off of oil.
Window Fix - Issue re: windows installed in several locations will not fully open because
they hit a structural column or block wall. Decision was made to have Keyes Associates
issue directive to JTC to continue with window installation in order to have school open
on time this fall. MBC stressed that this directive was not intended to be an acceptance
of the window system design, but a necessary action to occupy the school in September.
Keyes and/or JTC will be held responsible for providing operable windows in accordance
with contract documents.
JTC/Application for Payment #14 - Review/Approval
JTC Requisition shows General Contractor is 91% complete. Discussion opened
regarding Overhead and Profit payment in the amount of $20,567.00. Concern was raised
regarding use of inappropriate premium time scale. Amount does not appear to reflect a
1 '/i time rate as allowed per contract.
MOTION to recommend JTC Application for Payment #14 in the amount of
$744,298.40 for work performed through August 31, 1999. Payment is pending
receipt of Contractor's Release of Liens and further review by Project Coordinator
and Architect regarding OT payment. DY/JL: Passes 4-1. Ken Gay opposed.
Electrical — Recent big effort by Eastern Electric was noted.
SCHOOL COMMITTEE MEETING
School Committee joined MBC for joint meeting at 9:10 P.M.
Attendees: E. Thornton, J. Sankey, M. Trowbridge, E. Giordano, J. Moretti, L. Lynch,
W. Parker, R. Franklin and R. Foster.
• MBC Chairman provided a construction update regarding Mansfield School
Renovation Projects.
• School Committee authorized Walter Parker to proceed with request to supplement
School Dept. cleaning efforts.
Meeting adjourned at 10:10 PM.
Respectfully submitted,
Eleanor McCarter, Secretary