HomeMy WebLinkAboutMBC 10/12/1999TOWN OF MANSFIELD
Municipal Building Committee
Meeting Minutes of October 12, 1999
Members Present: Richard Feeley, Chairman (8:OOPM), James Liddick, Clerk, Kenneth Gay,
William Moore, David Young and Eleanor McCarter, Secretary
Attendees: Paul Letendre, MHS/QMS Project Coordinator
Lincoln Lynch, School Business Manager
Steve Chmura, Keyes Associates
Walter Parker, School Building & Grounds
John Moretti, School Superintendent
Meeting Commenced at 7:15 PM
CORRESPONDENCE:
General
Lin to MBC from School Dept. re: Invitation to Fields Committee Meeting 10-19-99.
Ltr to MBC from Gale Assoc. re: Jordan/Jackson Roof Testing.
Ltr. to Conn Kavanaugh, Rosenthal, Peisch & Ford re: Request for Documentation -SMI
Litigation.
Ltr. to Ammar Dieb from Richard Feeley re: Final Application for Payment to SMI.
Oualters Middle School
Ltr. to Keyes Assoc. from J.T. Callahan re: Request to add missing change orders.
Ltr. to Walter Parker from Paul Letendre re: Boiler room observations.
Ltr to J.T. Callahan from Keyes Assoc. re: Electrical issues at west wing.
Lin to Building Dept. from Keyes Assoc. re: Informing of location planned to install new
generator.
Ltr. to J.T. Callahan from Keyes Assoc. requesting deletion of wood flooring for gym addition
and credit for wood flooring material. Comment was made that the credit should include
material, installation and finish -work. Prep work will still be required. Steve Chmura to follow
up.
Ltr. to J.T. Callahan from Keyes Assoc. re: Directive to order one 60KW/ 120/208V Generator.
Request for COP including furnish and installation on site. Cost to also include temporary
generator set up for the duration of waiting period of delivery of new unit.
To MBC from J.T. Callahan Re: C.O.P. #190 Ref. Install Window in Classroom -$18,975.00.
To MBC from J.T. Callahan Re: C.O.P. #209 Ref. Circuit Breaker Heat Trace -$578.00.
To MBC from J.T. Callahan Re: C.O.P. #220 Ref. Temp. Metal Doorframe/Gym-$5,325.00.
To MBC from J.T. Callahan Re: C.O.P. #223 Ref. Flange kits for stairway light fixture $527.00.
To J.T. Callahan from Keyes Assoc. re: Summary of approved Change Order Proposals.
To MBC from Paul Letendre re: Project Coordinator Daily Logs.
Mansfield High School
Ltr. to MBC from J.T. Callahan re: Payment of September Requisition.
Ltr. to MBC from Paul Letendre re: Project Coordinator Daily Logs.
Ltr. to Walter Parker from Paul Letendre re: Vehicle traffic on front entrance ramp
QUALTERS MIDDLE SCHOOL
JTC/Change Order #13 — Steve Chmura requested approval of two additional C.O.P.'s to be
included in Change Order #13.
C.O.P. #196 Ref. Temporary Weather window coverage - $2,071.00.
Status: Approved as recommended by Keyes Assoc.
C.O.P. #215 Ref. Hollow Metal vs. Aluminum. Labor cost to Install 17 doorframes -$4,051.00.
Question was raised that work was previously identified as Proposal # 172. Keyes to notify JTC
that #172 is a void and to be replaced with COP #215.
Status: Approved as recommended by Keyes Assoc.
MOTION to approve J.T. Callahan's Change Order #13 in the amount of $40,580.00 for
Addition/Renovation work performed at Qualter's Middle School as recommended by
Keyes Associates. MBC rejects all references by J.T.Callahan regarding time extensions to
contract. Note that COP#196 should be added to SMI back charge list.
DY/WM: Passes 3-0.
JTC/Application for Payment — September — Chairman questioned Steve Chmura re: Release of
Lien waivers. At least nine appeared to be missing (Eastern, Cheviot, Debrino, Forbes Painting,
Thyssen Elevator, Yankee Sprinkler to name a few). Updated construction schedule from JTC
was not included with requisition.
MOTION to recommend payment to J.T. Callahan for Application for Payment #15 in the
amount of $349,872.00. Payment to be issued pending receipt of all missing lien waivers
and an updated construction schedule. DY/WM: Passes 3-0.
COP #220 Ref Temp Egress/Gym — J.T. Callahan turned over room without applying for
temporary occupancy permit. Temporary egress was required by code. Keyes to issue letter to
JTC re: due to their lack of forethought, JTC will be held responsible for installation of the
temporary egress at the gym.
Field Committee — MBC adjourned to Selectmen's Meeting Room to attend joint meeting of
Fields Committee and School Committee. John Moretti briefly announced that Keyes Associates
is preparing a prospectus for the Town of Mansfield regarding field space. MBC was invited to
attend the Selectmen's meeting on October 19, 1999 @ 8PM, where a proposal to create
additional indoor recreation facility would be presented by the School Dept. Mr. Moretti
informed the MBC of a suggestion being explored to convert the auditorium at QMS to a multi-
purpose room, similar to the Jordan/Jackson School. (Temp. seating, stage w/curtain, gym
flooring & teaching capabilities). Auditorium renovation is included in JTC contract. Project
Coordinator to verify whether new auditorium seating has already been ordered.
Contract Status — J.T. Callahan's contract for the QMS project is currently 90% complete
Landscaping near front ramp — David Young expressed concern regarding project drawings
showing extensive landscaping in the area intended for installation of the new generator. Steve
Chmura to send letter to Wallace Floyd requesting that they review landscape plan.
Elevator — Steve Chmura commented that JTC has refused to request an elevator inspection.
Thyssen Elevator installed cab in second elevator in September. Carpet was installed last week.
Waiting for electrical subcontractor to install heat and/or smoke detectors. Walter Parker
confirmed that he has coordinated elevator phones and direct line to police station. MBC asked
the Project Coordinator to pursue closure to issue with JTC. Elevator Pit #2 remains dry.
Manpower — Concern expressed over limited manpower being provided by J.T. Callahan and
Subcontractors.
Punch List — Keyes to have three staff members reviewing punch list items on October 13, 1999.
Project Coordinator noted that JTC has made little progress to addressing existing punch list
items.
Gym — Second finish coat on floor is complete. Mats to be installed next week. Project
Coordinator noted that gym should be completed for occupancy by Monday, October 25, 1999.
Comment was made that Walter Parker is still coordinating refinishing of gym bleachers. MBC
requested that Mr. Parker use proper protection for newly finished floor.
Gym Mats — Discussion opened regarding value of removal of gym mats. JTC to be responsible
for cost of surface mount mats less the cost of recessed mats.
Heat Trace — Opinion from TCI is that the heat trace is not functioning as designed. Issue may
be caused by improper installation. TCI requesting that a manufacturer's representative visit site
to evaluate. Project Coordinator to inform Plumbing Inspector, Connie Lajoie.
Site Li hg ting — Installation of wall packs in Zone 2 has begun. Poles are on site and should be
installed by next week. Project Coordinator informed the MBC of a suggestion made by the
Electrical Inspector that wall packs be wired to the emergency generator. Question raised as to
whether or not wiring is a code issue. Conditions will vary since MHS does not have wall packs.
Nurse/Guidance/Home Economics — All areas have been inspected and turned back over to the
School Department.
Roof Flashing — Estimated completion 1-2 weeks. Project Coordinator commented that the roof
would receive a warranty once work is completed.
Library — Completion is several weeks away.
Woodshop —Concern raised by woodshop teacher regarding slippery floor surface in woodshop.
Rich Feeley questioned whether the shop floor is scheduled for abatement. Project Coordinator
to verify. Suggestion was made to use mats at various workstations if floor is in good condition.
Hardware — Concern raised Re: School Dept. experiencing problems with installation of new
hardware. Project Coordinator to identify problem doors and follow up with Contractor. MBC
asked Steve Chmura to send JTC a memo on this issue.
Schedule — MBC told Steve Chmura that they expected his review of JTC's schedule to be
complete by 10-19-99.
Ramp Lightin — Project Coordinator reported that the opening for lighting is too large for
fixture. Keyes Associates to review installation options.
Cleaning — SOS $22,000 cleaning bill submitted for supplemental cleaning necessary to open
schools. MBC believes JTC owns all costs but will offer to pay 25% to address gray areas.
MANSFIELD HIGH SCHOOL
South Addition — Project Coordinator estimated work to be completed for occupancy by October
30, 1999.
Bay Window/Stairwell — Window in stairwell at South Addition is installed.
Elevator Truss — Principal at Wallace Floyd Associates reconsidered applying for waiver.
Project Coordinator noted that the paperwork is in process.
Inspections — Building Dept. approved occupancy permits for Library, Cafeteria and Rooms 211,
1 I IA and 11 IB.
Landscapins — Project Coordinator confirmed that trees would be installed in parking lot islands
this week. David Young expressed concern over documenting late planting and guarantee
issues.
Striping/Parking Lot — Discussion opened re: lack of proper line striping and signage. School
Dept. to forward letter to the MBC stating that issue is creating a safety hazard. Project
Coordinator will pursue immediate progress with JTC.
Hot Water Circulation System — Project Coordinator noted concern re: freeze -ups. TCI stated
that efficiency is reduced 30% by using glycol in system. South Addition is charged with 20%
glycol as recommended by Johnson Controls.
JTC/Application for Pam — JTC was advised that the MBC would not recommend payment
of any additional payment requisitions until outstanding credits are submitted.
INVOICES
Letendre Company -MHS
MOTION to recommend payment to Paul Letendre, MHS Project Coordinator in the
amount of $3,400.00 for weeks ending October 2, 1999 and October 9, 1999.
(QMS/$800 and MHS/$2,600) JUDY: Passes 5-0.
Staples-QMS
MOTION to recommend payment to Staples Business Advantage in the amount of $294.50
for purchase of (30) pencil sharpeners for QMS. DY/WM: Passes 5-0.
Office Innovations-QMS
MOTION to recommend payment to Office Innovations in the amount of $499.00 for the
purchase of (1) IBM Typewriter. WM/DY: Passes 5-0.
Valley Comnwnications-OMS
MOTION to recommend payment to Valley Communications in the amount of $1,262.00
for purchase of (2) JVC 32" Stereo TV sets. WM/DY: Passes 5-0.
WB Mason
MOTION to recommend payment to W.B. Mason in the amount of $246.86 for MBC
Office Supplies.
WM/DY: Passes 5-0.
Bristol Glass-QMS
MOTION to recommend payment to Bristol Glass in the amount of $1,680.00 for the
purchase of (35 panes) 1206 clear tempered safety glass to be installed in classroom doors.
DY/WM: Passes 5-0.
Meeting adjourned at 10:30PM
Respectfully Submitted,
Eleanor McCarter, Secretary
lom('
ores Liddick, Clerk
Date