QUALTERS MIDDLE SCHOOL
JTC Delay Claim - Rich Feeley questioned Keyes Associates regarding the status of back-up
documentation previously requested by the MBC. to be used for discussion with JTC on
2-29-00, i.e. incomplete contract work, rejected work, schedule evaluation/winter conditions and
credits due to the Town.
Credits — Project Coordinator reviewed 16 total credits to date due to the Town. MBC added four
additional items for consideration.
1.
Relocation of MHS Sign ($2,500.)
2.
Delete 2 removable bollards at front entrance ($4,000.) due to drainage issues.
Comment was made that knock -down type bollards are costly.
3.
Deleted wall/door at nurse's area ($3,500.)
4.
Delete 2 nurses cubicle curtains ($3,000.) One not provided.
5.
Skylights infill — Question re: authorization ($9,200.)
6.
Boys locker room benches ($2,000.)
7.
Terrazzo Flooring ($11,000.)
8.
Removal of mechanical equipment above auditorium ceiling ($9,000.)
9.
Credit for not recessing entrance mats (Original mats placed incorrectly and infilled.)
Difference between surface vs. recessed plus prep work ($6,375.)
10.
Temporary aluminum entrance doors ($2,200.)
11.
Deleted Project Coordinator trailer ($2,500.) to date. Jim Liddick suggested that Paul
Letendre prepare a spread sheet showing a detail of trailer expenses i.e. phone, electricity,
heat, computer, etc. David Young asked that JTC be informed of the rental fee amount
accumulating for each additional month.
12.
Value of roof penetrations shown over and above drawings ($18,000.)
13.
Clerk's software not provided ($1,000.)
14.
Auditorium seismic work ($15,000.)
15.
Contractor's failure to provide proper dust protection creating need for outside cleaning
service ($22,000.)
16.
Credit for VCT vinyl base not completed per finish schedule ($24,000.)
17.
Sound panels in cafeteria ($2,700.)
18.
Repair to damaged oil line - Delle Fimine Corporation ($2,665.)
19. Heat loss ($7,500.) due to lack of door sweeps and other enclosures.
20. Custodial Assistance — Chairman questioned whether to include QMS staff overtime.
Walter Parker would need to provide cost value.
David Young asked that Paul Letendre obtain written confirmation from Walter Parker that the
School Dept. is in agreement with the proposed credits. Jim Liddick reiterated that both Paul
Letendre and Steve Chmura should be prepared at Tuesday's meeting (2-29-00) with back up to
support the proposed credit values. Committee agreed that credits could be negotiated with JTC
if necessary.
Rejected Work —Committee members were in agreement that the Contractor is expected to
complete all rejected work. Steve Chmura reviewed a list of rejected work with the members
present.
• Expansion joint/Cafeteria —Floor joint is not level.
Bathrooms — Discussion re: Use of a one -foot accent strip to repair jagged edge of tile
installed in gang bathrooms. Keyes to determine if all bathroom tile work is complete.
Heat Trace — TCI noted that Montle Plumbing deviated from contract drawings with regard
to location of installation of piping. Heat Trace does not function as designed. Keyes to
issue notice to Montle Plumbing that work is rejected due to improper installation. Montle
Plumbing to also be advised to correct issue by either relocating pipe as designed or by
adding a re -circulation pump at no cost to Owner.
• Computer room cabinets re: tile work. Workmanship is unacceptable.
Window System Installation - Bob Vogel commented re: a conversation with Cheviot. Parts
are currently on order to disable window units that are completely obstructed and replace
them with fixed windows. Issue with some classrooms have windows with significant
column blocks is still being addressed by Mr. Vogel. Chairman questioned Mr. Vogel as to
what directive Ron Ashton gave to JTC re: Shop Drawings. Mr. Vogel responded that Ron
Ashton's notes re: Shop Drawings, indicate that the Contractor is to coordinate all locations
of windows.
• Door to right of Administration Area — Fix is unacceptable. Keyes Associates has directed
JTC to raise door frame.
• Padding at gym to be raised. Work rejected.
• Ceiling/Cafeteria —Acoustic panels don't match at differing ceiling heights. Work rejected.
• Acoustical Tile -Question raised as to whether acoustical tile was removed by JTC. Per
contract, Contractor is required to patch to match ACT.
Major issues for discussion MBC Meeting of 2-29-00:
• Roof Unit Pricing — Committee agreed along with confirmation from legal counsel that the
unit pricing issue re: MHS roof is a non-negotiable issue.
Winter Conditions Claim — Discussion was that JTC did not start Zone 2 when they could
have. JTC was allowed access to several areas in advance of their schedule, which would
have alleviated delays. Based on the original schedule JTC must have been aware of some
work planned during the winter months and must have carried some winter conditions in
their bid. Discussion was to negotiate winter conditions claim to gain further action with
regard to credits and incomplete/rejected work. Chairman Feeley expressed opinion that JTC
has not offered enough strong support to their claim for winter conditions to date.
• Liquidated Damages - Bob Vogel confirmed that per contract, the Contractor is not entitled
to compensation for General Conditions for an extension of time beyond the contract. Cost
of General Conditions is already included.
• Construction Schedule - JTC is currently 73 days past contract deadline as of today. Potential
liquidated damages to Town at 73 days (as of today) times $500.00 per day equals
$36,000.00 to date.
Manpower — David Young asked that Paul Letendre prepare a list of documented manpower on
site from December 1999. Average manpower on site is 11 since 12-1-99.
Plan of Action — Committee discussed agenda items to be included at the MBC meeting schedule
for Tuesday, February 29, 2000. Tentative agenda is as follows:
TOOPM MANSFIELD HIGH SCHOOL
Sue Michael Brown/David Burson, Wallace Floyd Design Group
Question as to whether roof issue will be discussed before or after discussions
with JTC. Rich Feeley to contact David Burson.
7:30PM QUALTERS MIDDLE SCHOOL
J.T. Callahan and Bob Vogel, Steve Chmura, Keyes Associates
Winter Conditions
Punch List
Incomplete work
Rejected work
Time extension/liquidated damages
Credits due to Town
Mansfield High School Roof Issue
Meeting adjourned @ 10:OOPM