Loading...
HomeMy WebLinkAboutMBC 03/14/2000Members Present: Attendees: wPPROVED, � TOWN OF MANSFIELD Municipal Building Committee Meeting Minutes of March 14, 2000 Richard Feeley, Chairman, James Liddick, Clerk (8:30 PM), Kenneth Gay, William Moore, David Young and Eleanor McCarter, Secretary Paul Letendre, MHS/QMS Project Coordinator Sue Michael -Brown, Wallace Floyd Design Group Steve Chmura and Bob Vogel, Keyes Associates Michael Callahan, Marc Jaoude, Phil Ricci, Paul Ciaramitaro J.T. Callahan and Sons, Inc. Walter Parker, School Buildings & Grounds Director Linc Lynch, School Business Manager Meeting commenced at 7:00 P.M. MANSFIELD HIGH SCHOOL Mechanical Systems - TCI was on site 3-8-00 to evaluate conflicts with installation of mechanical systems on the second floor Science area. TCI cited lack of coordination drawings and existing condition of electrical raceway installation as major conflicts for the mechanical contractor. Sue Michael Brown has forwarded written evaluation to JTC. Submittals - Wallace Floyd is still waiting to receive several outstanding submittals (either rejected or revise/resubmit). Sue Michael -Brown sent letter to Marc Jaoude on 3-8-00 requesting prompt response. Dates logged out go back as far as February 25, 1999. Transition Strips/Kitchen - Installation began six months ago and is still incomplete. Project Coordinator issued written notice to JTC 3-8-00 noting chipping of unprotected edges of quarry tile at several door openings (tile will need to be replaced). Missing transition strips are causing a trip hazard. Sewer Ejector Tank — Problems have been detected in the pit. JTC has been notified to correct issues with water and electrical conduit. Science Lab Sinks — Issue re: COP #145A Ref. Science lab sinks in the amount of $14,293.00 — Based on response from the School Superintendent, Rich Feeley informed JTC that the undersize sinks installed are insufficient to teach the Science program. JTC to investigate cost of restocking. Issue pending. Duct work at Girls/Boys Locker Rooms — Sue Michael Brown had issued directive to installation of duct work at locker rooms. MBC was advised that the proposed changes to the girls/boys locker rooms requested by the School Dept are on hold. Staff has not received authorization for the School Superintendent to make any changes. Lincoln Lynch directed the MBC to move forward with the contract as scheduled. MOTION to authorize Wallace Floyd to void their previous correspondence to JTC dated 3-6-00 and direct Contractor to proceed with duct work in girls/boys locker rooms per contract. JUDY: Passes 5-0. Change Order Proposals — Committee reviewed status of pending Change Order Proposals as submitted by Wallace Floyd Design Group. COP#33 Ref. Credit for engineering at ball field. MBC opinion is that a credit is justified for the value of reduced scope of engineering required. Rich Feeley commented that a similar fee was paid to JTC's engineer for $1,000.00 for atwo-inch discrepancy at QMS. Status: JTC to review. COP#69 Ref. Handicap Ramp — Issue Pending. Auditorium/Fire Protection - Per spec. the Contractor is to remove auditorium ceiling, install sprinkler system and replace ceiling and install new fixtures. Item is carried in Alternate #1. Michael Callahan proposed that the ceiling remain in place and that he uses the $10,000 demolition credit to engineer and stage sprinkler installation. Yankee Sprinkler would install sprinkler from above the auditorium to one foot below the roof deck. Committee's opinion was that a credit would be due to the Town for the value of work not performed (i.e. new ceiling). JTC to generate cost proposal. David Young raised question with regard to location of new lighting. Sue Brown to determine whether the new lighting can be installed at the existing locations. Vestibule — Per previous conversation with Jim May, the Contractor prepped the vestibule at MHS for installation of quarry tile. Based on 3-7-00 MBC Meeting, grate mats were to be installed. Sue Michael Brown indicated that cost to install quarry tile would be significantly less than the Committee expected based on square footage. MOTION to have Wallace Floyd direct the Contractor to install quarry tile based on pricing of $1,600.00. DY/KG: Passes 4-0. Roofing Systems - Roofing system installed in the West and South Additions is a substitution for original design. Discussion was that no cost or credit is due for change in scope of work. JTC/Change Order No.5 — The following COP'S were recommended by Wallace Floyd Design Group to be included in Change Order #5: COP#76 Ref. Caf & Libr. Ductwork and ceiling layout -$1,296.00. COP#81A Ref. Pulls at ext. doors 170C & 180C - $438.00. COP#83 Ref. Caf & Lib. Ductwork and ceiling layout - $5,216.00. COP#103 Ref. Remove epdm for roof top unit on Roof Area A - $4,607.00. COP#105 Ref. Paper Towel Dispenser - $164.00. COP#107 Ref. Trench for elec. Line to modify parking lot light - $915.00. COP#108 Ref. ACT at South wing stair - $137.00. COP#108A Ref. ACT at West wing stair - $509.00. COP#109 Ref. Repair ACT at South wing stair - $137.00. COP#110 Ref. Conduit for Library desk power & data - $924.00. COP#111 Ref. G4000 Wire mold & 3 exist. Power poles in 171 — $2,704.00. COP#112 Ref. Wiring for Maintenance Shed - $4,908.00. COP#113 Ref Electrical changes to Library - $686.00. COP#114 Ref. Wire sandwich warmer - $382.00. COP#116 Ref. Aluminum window travel - $260.00. COP#117 Ref. Gutter support brackets $1,500.00. COP#127 Ref. ACT in 270A, 280A, Louver vent in dr 170A, 180A -$893.00. COP#130 Ref. Modify truss in elevator shaft - $2,631.00. COP#134 Ref. ACT ceiling in room 280B - $169.00. COP9142 Ref. Substitute timberline shingles in lieu of MWM - $2,929.00. MOTION to recommend approve JTC Change Order #5 as recommended by Wallace Floyd Design Group in the amount of $31,741.00 for work performed at the Mansfield High School Renovation Project. DY/JL: Passes 5-0. JTC/Change Order No.6 - The following COP's were recommended by Wallace Floyd Design Group to be included in Change Order #6: COP#45A Ref. Credit for deletion of plumbing in 162, 127B — ($4,258.00). COP#102 Ref. Credit for roof deck removal and replacement — ($210,000.00). COP4146 Ref. Cylinder to doors 170C & 180C - $410.00. COP#150 Ref. New emu wet in rms. 128, 236 - $2,883.00. MOTION to recommend approve JTC Credit Change Order #6 as recommended by Wallace Floyd Design Group in the amount of ($210,965.00) for work performed at the Mansfield High School Renovation Project. WM/DY: Passes 4-1. COP#102/Roof Credit — Michael Callahan asked the Committee to allow the roof credit to be split over a two-month period. Town would receive $105,000.00 in the January Application for Payment and the same amount from the February Payment Requisition. MOTION to allow the MHS roof credit of ($210,000.00) to be reflected in JTC's Application for Payments over a period of two -months (Jan. and Feb., 2000). DY/JL: Passes 5-0. Application for Payment #14 — JTC did not have certified copies of the Application for Payment #14 ready for approval. Marc Jaoude to deduct cost to reflect'/2 roof credit ($105,000.00) and deliver certified copies to the MBC Office prior to noon on Wednesday. Committee authorized Chairman to approve pending verification from Project Coordinator. MOTION to recommend payment to JTC for Application for Payment #14 in the amount of $317,594.03 for work performed at MHS. WM/KG: Passes 3-2-0. QUALTERS MIDDLE SCHOOL JTC/Change Orders — The following COP's were recommended by Keyes Associates to be included in Change Order #16: COP#54A Ref. Relocate plumbing and venting for washer & dryer at Home Ec. for $4,172.00. COP#54B Ref. Relocate electrical supply for washer & dryer at Home Ec.- $1,529.00. COP#63 Ref. Furnish & Install Screens in elevator shaft - $761.00. COP#11 IR Ref. Winter Conditions- $27,500.00. COP#113A Ref. Time & Material for electrical switches - $611.00. COP#140A Ref. Furnish & Install Heat Detectors throughout crawl space for $11,999.00. COP#142 Ref. Furnish & Install Translucent panel cafeteria at Northern Elevation for $509.00. COP#163R Ref. Provide 50 AMP Breaker for electric kilns - $277.00. COP# 166R Ref. Provide 50 AMP Breaker for handicap lifts - $$401.00. COP#171A Ref. Acceleration -$15,508.00. COP#171B Ref. Acceleration - $22,457.00. COP#173 Ref. Move condensate piping to ceiling in BI classroom - $1,011.00. COP#174 Ref. Furnish & Install duct for new location of dust collector - $1,276.00. COP#178 Ref. Furnish & Install louver and sleeve for UV in room B1 - $392.00. COP#190A Ref. Window Repairs - $13,952.00. COP#299 Ref. Credit for work not complete. Itemized list attached. — ($60,000.00). MOTION to recommend approval of JTC Credit Change Order #16 as recommended by Keyes Associates in the amount of ($42,355.00) for work performed at the Qualters Middle School Renovation Project. DY/JL: Passes 5-0. COP#140A — Re: Heat detectors in crawl space, question was raised as to whether JTC mark-up costs were incorporated. Decision was to withdraw COP#140A in the amount of $11,999 from Change Order #16. Steve Chmura to notify JTC of revisions to credit referencing MBC Meeting minutes of 2-24-00. MOTION made that per the agreement made between the Town and JTC, no requests for Time Extension or Liquidated Damages will be considered for damages up to April 22, 2000 for internal work and May 13, 2000 for external work. Keyes to prepare a letter for JTC to sign. DY/KG: Passes 5-0. JTC/Application for Payment #19 —Steve Chmura reduced the total dollar amount of $163,022.63 to reflect withdrawal of COP#140A —Heat detectors in crawl space for work not done - $11,999.00. MOTION to recommend payment to J.T. Callahan & Sons Application for Payment #19 in the amount of $151,624.00 for work performed at the Qualters Middle School Project. WM/DY: Passes 5-0 Heat Trace — Montle Plumbing still disputing responsibility for heat trace not working. Committee disagrees based on Montle Plumbing installing 200 feet of pipe below crawl space instead of first floor level as per spec. Temperature would be cooler in crawl space. MBC requested that Keyes obtain a proposal from Montle Plumbing to install a re -circulation pump Window Conflict - Michael Callahan noted that he is setting up a meeting with Cheviot Corp. some time next week to discuss problem with window column conflicts. Mr. Callahan requested that the Keyes' Architect attend. David Young asked that the MBC also be notified of date and time. Linc Lynch asked that Walter Parker also attend. Gym Padding — MBC agreed to accept a credit for top oak trim piece. Cost to be applied to installation of vented base trim. Administration — Due to intrusive work necessary at administration area, David Young advised JTC to coordinate work dates with School Staff prior to work being performed. Punch List — Steve Chmura noted that the Zone 2 Punch List is complete. Mr. Chmura stated that there is a small list of finish items to be completed. Schedule Evaluation — MBC asked Michael Callahan to identify deadline dates for completion of the interior and exterior work remaining at Qualters. Mr. Callahan stated that the interior work would be completed by Saturday, April 22, 2000 and that the exterior work will be completed by Saturday, May 13, 2000. Cafeteria Expansion Joint — JTC agreed to pay for removal of floor tile and replacement. MBC agreed to pay for Contractor to adjust concrete to acceptable level. Auditorium - Michael Callahan noted that the auditorium failed inspection for a Temporary Occupancy Permit due to lack of operable handicap access to stage. • Handicap Chair Lift — The MBC expressed opinion the chair lift is unacceptable as installed. The lift significantly obstructs view from front seating area. Steve Chmura indicated that the handicap chair lift is required by the State Barriers Board. Mr. Chmura commented that installation of additional railings would also be required. Committee discussed options to reduce obstruction as much as possible. Linc Lynch agreed to deletion of one staircase if necessary. MBC directed Keyes to issue sketch relocating the lift. • Handicap Seating - Steve Chmura to issue sketch to JTC by Friday. Mr. Chmura noted plans to install a flat plywood platform covered with carpet. Keyes noted that per regulation all handicap seating must also have a companion chair attached. Change Order Proposals — Steve Chmura presented the following COP'S for review/approval relating to McLaughlin Mechanical: COP#251 Ref. Install heating unit paint storage - $2,819.00. Status: Approved as recommended by Keyes Associates. COP#218 Ref. Re -pipe oil pump set in boiler room - $799.00. Status: Rejected due to work performed for the convenience of Sub -contractor to install air handling unit. COP#217 Ref. Relocate condensation line in boiler room conflict elec. Panel - $1,097.00. Status: Approved as recommended by Keyes Associates. COP#250 Ref. Nurses area fresh air make-up ductwork. Status: TCI to review cost. JTC to revise and resubmit. No action taken. COP#249 Ref. Relocate Condensation line in Corridor B17A -$735.00. Status: Committee agreed to split original cost of $1,477.00 with JTC. Approved as recommended by Keyes Associates. COP#291 Ref. Dishwasher venting changes (balancing time) - $230.00. Status: Rejected by MBC. COP#274 Ref. Provide covers for old grate openings in brick around auditorium (Room #150 lobby area) - $1,043.00. Status: Rejected. School Dept. to perform necessary work. Meeting adjourned at 11:35 P.M. Respectfully submitted, Eleanor McCarter James Liddick, Clerk 411.00 Date