HomeMy WebLinkAboutMBC 11/21/20000
�,
TOWNOF MANSFIELD
G 1 ,J€!i 2 a Pio 1 : 21F Municipal Building Committee
Meeting Minutes of November 21, 2000
D
Members Present: Richard Feeley, Chairman, David Young, Clerk, Kenneth Gay,
James Liddick, William Moore and Eleanor McCarter, Secretary
Attendees: Sue Michael Brown, David Burson, Wallace Floyd Design Group
Lincoln Lynch, School Business Manager
Michael Callahan, Phil Ricci, J.T. Callahan & Sons
Richard Coughlin, Coughlin Consultant Services
Commercial Painting Representative _
Meeting commenced at 7:15 PM.
MANSFIELD HIGH SCHOOL
Painting Dispute — Previous discussion with the MBC was that JTC would solicit services
of an outside consultant who would mediate the dispute over interpretation of who owns
painting of lockers and glazed block. Scope of mediator's responsibility would include
review of documentation, meeting with all parties to hear opposing views and possible
involvement in negotiation of a resolution. If mediator was mutually agreed upon, cost
for services provided by the mediator would be split between JTC and Owner.
JTC independently secured mediation services from Richard Coughlin, Consultant
Services. MBC was surprised to receive a "final" written opinion regarding the paint
dispute provided by Mr. Coughlin earlier this week. Based on discussion, Rich Feeley
commented that the investigative process performed by Mr. Coughlin was incomplete
and that the opinion given appears bias. It was determined that the mediator did not
review all pertinent documentation regarding the paint issue. The Mediator admitted that
he did not meet with anyone from Wallace Floyd Design Group or the Owner for their
input prior to making his final determination supporting the painter's claim.
Claim 11 Painting of Lockers:
• Required Site Visit - General Conditions section of contract mandates that all
subcontractors visit site prior to bid. Commercial Painting representative
admitted no one from their company visited site as required.
• Painting Method — Terminology in the Mediator's report states it is "customary" to
call for electrostatic method painting of lockers. David Young suggested it is the
Consultant and Contractor's "presumption" that the Town wanted electrostatic paint.
Because this method is not specified in specs., the Contractor assumed that painting
of lockers is not owned. Rich Feeley commented that proper investigation, of the
required work, was not performed by the painting Sub -contractor and that the
Contractor should have issued a Request for Information. Commercial Painting
Representative confirmed that no RFI's were issued.
• Chairman questioned Painter as to why pricing was lowered in re -bid. Commercial
Painting Rep. responded that pricing was modified based upon "new
quantities". Commercial had seen tally of original bid. Commercial Painting
Rep. said they had verbally communicated with WFDG and were told to "Bid it
as you see it".
Claim 2 Painting of CMU Block:
• Site Visit - All subs were invited to view site prior to bidding. Paint Subcontractor
chose not to visit site as recommended in specifications.
Finish Schedule - Mediator's report noted wording in finish schedule was changed
supporting paint was not required. Sue Michael Brown noted that Addendum #7
supercedes finish schedule stating that "all" surfaces are to be painted.
Credit due for Painting Glazed CMU - Since glazed CMU is not usually painted the
Subcontractor has not performed this work. JTC has not yet provided credit in the
amount of $35K. Cost estimate is based on quantity of glazed block not painted.
Commercial representative hopes to recoup 85% of cost for glazed block ($28K
plus JTC 15% mark up). MBC rejected this offer.
MBC held brief discussion with mediator. (JTC was asked to leave the room at this
time.)
Members expressed concern that the mediator is not receptive to reach middle ground
between both parties (JTC and Owner) and that several other factors should be taken into
consideration. Mr. Coughlin refused re -consideration of opinions given in his
original report. Mr. Coughlin advised the MBC of various scenarios to resolve issue
in binding arbitration and Superior Court. Mr. Coughlin left meeting at 9 PM.
General Meeting resumed with J.T. Callahan, Commercial Painting, Wallace Floyd
Design Group and Municipal Building Committee.
Negotiation Summary:
Commercial Painting made an agreement with MBC to electrostatic paint all outside
visible faces of lockers for a fee of $29K, with no additional mark up to JTC. In addition
the cost proposal for painting glazed block is now void. WFDG to issue change order by
Monday (11-27-00) to be included in JTC/Change Order #17. Chairman requested that
Commercial provide release of liens as required. WFDG and JTC to include cost of this
item in next JTC/Application for Payment.
Direct Payment Requests — Rich Feeley stated that JTC needs to immediately respond to
all outstanding direct payment requests.
Pavin —Original date (11-18-00) for paving work was not met by JTC. JTC noted that
paving is re -scheduled to Friday, November 24, 2000. MBC expressed concern
regarding quality of paving in freezing temperatures. David Young advised JTC that
contract documents specify 50 degrees ambient temperatures to proceed with paving.
Committee asked JTC to proceed with the following paving work this Friday (11-24-00)
and delay final paving until Spring, 2001.
0 Feather area of pavement in rear of MHS gym where asphalt was cut.
• Clarify handicap ramp requirements at QMS gym entrance with Architect and revise
pitch as necessary to meet occupancy permit requirements. Keyes needs to issue
sketch to JTC.
• Install necessary pavement to raise level where catch basins are located.
Handicap Access - Phil Ricci requested clarification of modifications made by local
Building Inspector to adjust the pitch at the rear door entry to meet handicap access
requirements. Phil Ricci is still waiting for Keyes Assoc. to provide a sketch previously
requested by JTC. New sketch from Keyes is to show a change in pitch from 1 and 12
pitch, to 1 and 20 pitch (one and twelve pitch would require additional cost for
installation of handrails.) MBC raised concern about paving the full width of entry, that
cars could drive and/or park right up to the door. David Young suggested that if the full
width of entry is paved, then bollards would need to be installed at entry way.- Also need
to strip area for fire lane.
Installation of Guardrail —Work is incomplete. David Young reported that the guardrail
at rear of NMS near gym is still not installed. Michael Callahan to follow up.
CMU — MBC questioned status of credit due from the mason subcontractor, for value of
glazed block in new addition. Need documentation from Wallace Floyd Design Group.
Bollards — Installation of flexible bollards at each end of Fire Access lane between MHS
and QMS is complete.
Change Order Proposal — JTC agreed that the final Change Order for the Qualters Middle
School Project would be complete in two weeks.
Seismic — Nashoba Steel disputes credit is due to Town for deletion of masonry seismic
work (2 side walls @ Gym, Auditorium SW and Locker Rooms). MBC asked Sue
Michael Brown to establish a cost value. JTC to follow up.
Existing Ceiling/Boys Locker Rm. — Commercial Painting reported peeling and failing
paint on the existing ceiling structure. Condition makes surfaces unsuitable and
unacceptable for painting. Discussion was to paint per contract.
Locker Room Changes — Still waiting for JTC to provide final Change Order Proposal for
locker room modifications. Michael Callahan expressed frustration in waiting for
Mechanical, Electrical and Plumbing subcontractors to provide cost proposals to JTC.
Plumber's Proposal — Still waiting to verify plumber's cost estimate. Plumber's
pricing includes credit at $1.00 per S.F. and new work at $1.50 per S.F. Plumber did
not attend a scheduled meeting with WFDG and JTC to discuss pricing.
Flooring — JTC submitted two floor proposals for review (COP#245 & COP#245A).
OPTION 1: COP#245 Ref. Floor system in girls locker room - $26,892.00.
Furnish and install Silikal MMA Color quartz flooring, with microban anti -microbial
additive and non -slip aggregate.
OPTION 2: COP#245A Ref. Floor system in girls locker room - $21,384.00.
Furnish and install RBC Industries epoxy color quartz flooring throughout. MBC
supports less expense method in COP#245A.
• Sprinkler — Sprinkler subcontractor is planning to begin work on Friday, November
25, 2000.
Change Order Proposal — Review/Approval
COP#191 Ref. Tie-in Clock to generator - $1,661.00
Status: Rejected by MBC.
COP#233 Ref. T&M offsets to tic in the new diffusers necessary due to new ceiling
grid layouts.
Status: Pending.
COP#235 Ref. Repair damage to soffit in Cafeteria/sand
Status: Pending.
COP#238 Ref. Demo of Marble Shower Stalls - $668.00.
Status: Approved as recommended by WFDG.
COP#248 Ref. Temporary exterior Railings for Town Election -$616.00.
Status: Approved as recommended by WFDG.
MOTION to approve COP#238 and COP#248 referenced above as recommended by
Wallace Floyd Design Group. DY/JL: Passes 5-0.
Status: Pending.
COP#204
Ref. Delete Work in rms. ($1,889.00)
Status: Pending.
COP#207
Ref. Delete installation of sink in Wood Shop Rm. #125 — ($681.00)
Status: Pending.
COP#211
Ref. 32' Beam/Lintel @ duct - $1,652.00.
Status: Pending.
COP#212
Ref. Delete stove top in 126 — ($153.00).
Status: Pending.
COP#212A
Ref. Delete stove top in 126 — ($228.00).
Status: Pending. Credit is too low. JTC to re -submit.
COP#220
Ref. Deletion of new stair at loading dock — ($600.00)
Status: Pending.
COP#220A
Ref. Deletion of new stair at loading dock ($750.00)
Status: Pending.
COP#222
Ref. Locker Room revisions
Status: Pending. Waiting for JTC to verify and provide final cost
estimate.
COP#226
Ref. Additional General Conditions
Status: Rejected by MBC.
COP#231
Ref. Additional General Conditions
Status: Rejected by MBC.
COP#232
Ref. Additional General Conditions
Status: Rejected by MBC.
COP#233 Ref. T&M offsets to tic in the new diffusers necessary due to new ceiling
grid layouts.
Status: Pending.
COP#235 Ref. Repair damage to soffit in Cafeteria/sand
Status: Pending.
COP#238 Ref. Demo of Marble Shower Stalls - $668.00.
Status: Approved as recommended by WFDG.
COP#248 Ref. Temporary exterior Railings for Town Election -$616.00.
Status: Approved as recommended by WFDG.
MOTION to approve COP#238 and COP#248 referenced above as recommended by
Wallace Floyd Design Group. DY/JL: Passes 5-0.
Auditorium Rama — Existing exterior "straight" ramp from Auditorium entrance door to
parking lot is not handicap accessible. Architect noted that the cost of modifications to
make this ramp handicap accessible would be excessive. Since the existing "curved"
ramp does meets handicap requirements, MBC asked Sue Michael Brown to direct JTC
to cover the straight ramp walk with dirt.
Auditorium Stage — Linc Lynch advised the MBC of a speculative report that the rigging
that holds the lights above the stage area is unsafe. Use of stage has been suspended by
the School Dept. until further notice. Issue is not related to construction activity.
Acid Waste — Walter Parker reported improper plumbing of acid neutralization tanks.
JTC to follow up.
Locker Room — Discussion re: installation of marble partitions at Gym Locker Room
removed during demolition. Suggestion was to have School Dept. handle after new floor
is installed.
Issue pending.
JTC/Change Order #16 — Review/Approval
COP#121 Ref. Remove existing AC for Seismic - $290.00.
COP9124 Ref. T&M Masonry demo and repointing - $10,542.00.
COP#214 Ref. T&M frame soffit at front lobby - $474.00
COP#224 Ref. Misc. Electrical Work - $2,639.00.
COP#228 Ref. Demo of concrete ramp at QMS Gymnasium - $2,000.00.
COP#229 Ref. Ceramic base in rooms 118B & 118C - $378.00.
COP#230 Ref. Misc. T&M work in Gymnasium - $850.00.
COP#239 Ref. Materials for handicapped toilet partition sliding - $101.00.
COP#240 Ref. Infill of exploratory CMU removal for seismic - $324.00.
COP#244 Ref. Sprinkler piping in Locker Rooms - $2,316.00.
MOTION to approved JTC/Change Order #16 in the amount of $19,914.00 as
recommended by Wallace Floyd Design Group. JL/WM: Passes 5-0.
JTC/Application for Payment — JTC did not provide paperwork for approval
QUALTERS MIDDLE SCHOOL
Inoperable Unit Ventilators — Johnson Controls/McLaughlin need to perform additional
work to unit ventilators #13, #14, #15 & #16. Johnson Controls is waiting for re-
shipment of switches to install. Original switches were misplaced on site. JTC needs to
follow up.
Grease Tran — Electrician did not wire grease trap due to it relocation from first floor to
basement. Rich Feeley noted that per contract unit is to be wired and connected to
electrical panel.
Carpet in Administration — MBC noted that the cost for carpet replacement should be
back charged to McLaughlin Mechanical due to damage caused by workers during
installation of unit ventilators.
Expansion Joint — Revised work is now complete. MBC has accepted revised work.
Meeting adjourned at 11:20PM
Respectfully Submitted,
Eleanor McCarter, Secretary
David Young, Clerk Date
4 `_ C)