HomeMy WebLinkAboutMBC 11/28/2000TOWN OF MANSFIELD
01 JN e6 F1,1 Municipal Building Committee
eeting Minutes of November 28, 2000
Vo,
Me4rW4r0*4V,EMhard Feeley, Chairman, David Young, Clerk, James Liddick,
William Moore and Eleanor McCarter, Secretary
Ken Gay - Absent
Attendees: Steve Chmura and Bob Vogel (7:30), Keyes Associates
Walter Parker, School Buildings and Grounds
Kenneth Larkin, Larkin Iron & Fence
Meeting commenced at 7:00 PM.
QUALTERS MIDDLE SCHOOL
Lintels - Ken Larkin questioned the MBC re: status of payment to Larkin Iron ($14K) for
an upgrade in the Lintel System that was not included per contract. Rich Feeley advised
Mr. Larkin that the Town has closed -out all Change Order work for a lump sum fee
already paid to JTC. Further discussion was that JTC had not provided any
documentation showing a revised lintel schedule, pricing and labor to the MBC for
review/approval. Mr. Feeley advised Mr. Larkin to pursue his claim with J.T. Callahan
and Sons. MBC asked Steve Chmura to meet with Ken Larkin to review backup
provided by Larkin Iron. Previous submittal was disorganized and rejected by Keyes.
7 -Day Notice to Complete Work —Keyes issued seven-day notice to J.T. Callahan &
Sons on November 20, 2000 to complete all work related to the QMS Project. Per Steve
Chmura, the package was sent via certified mail to JTC, and included all verified punch
list work. JTC received the notice Thanksgiving week.
Second Notice to Complete Work —MBC directed Keyes to issue second Seven -Day
Notice to complete remaining contract work as required. Keyes to address JTC response
dated 11-28-00.
Grease Tran — Grease trap still needs to be wired to panel. Chairman asked Keyes to
notify Eastern Electric to perform all necessary work per contract (including Kiln,
additional kitchen outlets, etc).
Closeout Documents/Training — Still waiting for JTC to provide kitchen closeout
documents and training.
Strobe Lights — Improper alignment of newly installed strobe lights needs to be corrected
to meet ADA requirements. $6,000 is currently being held on monetized Punch List for
this work.
Acid Waste Neutralizing Tank/Room 115 — Work is incomplete. Montle Plumbing
forwarded letter to MBC explaining why work was not completed.
Warranties — MBC questioned status of warranties provided by JTC. Keyes needs to
review list of warranties in hand and provide update to MBC.
Occupancy Permit Issues — Per local Building Inspector, the following issues need to be
addressed prior to issuance of final Occupancy Permit.
• Handicap Ramp at Rear Entrance — Keyes needs to request variance this week.
• Emergency exit lights needed at new wing missed on drawings - School Dept. to
secure Webber Electric to install lights ASAP.
• Handicap handrail at Cafeteria Entrance — Keyes needs to request variance this week.
• Slope of ramp at Cafeteria Entrance — Keyes to request variance this week.
• Egress to Courtyard — Keyes to provide revised plan by December 1, 2000.
Courtyard Issues — Walter Parker agreed to remove locks and existing exit signs from all
courtyard doors to satisfy safe egress requirements. Signs can be reused in new wing as
needed.
Pavin —Work is incomplete. Weather permitting, paving scheduled for December 2,
2000.
Handicap Ramp - Steve Chmura stated that the five foot platform is sufficient to meet
ADA requirements. Chairman asked Keyes to verify one in twenty slope. David Young
expressed concern that paving sketch issued to JTC does not reflect actual area shown.
Mr. Young raised concern about proper drainage. Loam in this area needs to be raised.
MBC asked Keyes to issue new sketch to JTC allowing time for JTC to review sketch
prior to paving.
Mechanical Punch List — Steve Chmura reported that the Mechanical Punch List is
complete. Mechanical O&M Manuals have not been provided as required per contract.
Unit Ventilators — Mclaughlin Mechanical is still waiting for delivery of re -ordered parts.
Johnson Controls is responsible for installation of switches. MBC reiterated that the units
must be started and tested after work is complete.
Expansion Joint —Rich Feeley and David Young viewed corrected expansion joint and
found installation acceptable. Chairman reported that three tiles (varying colors) were
damaged during reinstallation. Chairman asked Keyes to hold $1,000 to replace tiles.
Landscaping Punch List — WFDG has not been to site to review. Keyes needs to contact
Landscape Architect at Wallace Floyd and follow up.
Window Conflict — Due to a Keyes internal issue, no further action has been taken by
Keyes to resolve issue with windows obstructed by walls and/or partitions. Their
insurance company has not hired an independent review company.
Sidewalk Cracking —David Young raised concern about cracking in sidewalk located
where sewer main was replaced. Steve Chmura noted cracking at seven locations are
listed on Exterior Punch List. Mr. Young asked Steve Chmura to also review area in
front at bus loop where new sidewalk is depressed and cracking and add to Punch List.
JTC/Application for Payment — JTC did not provide documentation to MBC for
review/approval.
Bollards at Fire Lane — David Young commented that the contractor installed flexible
bollards at an incorrect location.
Auditorium Speaker — Walter Parker reported that the speaker in the Auditorium is
installed.
SMI Litigation — Chairman noted that a conference call with Legal Counsel, Town
Manager and MBC Chairman is scheduled for Thursday November 30, 2000 to discuss
status of litigation and possible settlement options.
MANSFIELD HIGH SCHOOL
Track/Field — David Young advised Walter Parker to verify field orientation is correct.
Orientation of ball field needs to be 15 degrees off North South.
Masonry Cracks - Walter Parker stated he has not seen Structural Engineer on site to
review masonry cracks as previously discussed. Rich Feeley asked Mr. Parker to
i document cracking noticed in gym and girls/boys locker room and forward letter to the
MBC. Mr. Feeley noted that the MBC asked WFDG to follow up on this issue last week.
Temporary Handrail — MBC to ask WFDG to issue directive to JTC not to paint
permanent handrails (credit) in lieu of installation of temporary handrails needed for
Town Elections.
JORDAN JACKSON ELEMENTARY
Roof—Litigation still pending. Max Volterra was given additional documentation
provided by Walter Parker for review earlier today. At that time, Mr. Volterra mentioned
concern raised by Titan's legal counsel regarding statute of limitations expiring with
regard to the roof litigation. As an interim plan, Walter Parker to contact Garland
Roofing for quote to coat roof.
INVOICES
DuPont Flooring Systems — QMS
Invoice of $800 for necessary carpet cleaning due to construction activity in
Administration, Library and Auditorium.
Status: Backcharge to JTC. MBC to notify Contractor.
Integrated Security — QMS
Invoice of $666.00 to replace lock at gym door and master key cylinder etc. due to
improper installation.
Status: Backcharge to JTC. MBC to notify Contractor.
Meeting adjourned at 10:10 PM
Respectfully submitted,
Eleanor A. McCarter, Secretary
David Young, Clerk �� Date