HomeMy WebLinkAboutMBC 12/19/2000N-1- ICE
01 JI'M' 20- nib 1: 21E
k ', G_ �'
iiA14embgg',f ee�B�t:
TOWN OF MANSFIELD
Municipal Building Committee
Meeting Minutes of December 19, 2000
Richard Feeley, Chairman, David Young, Clerk, William Moore,
Eleanor McCarter, Secretary
Kenneth Gay, (8:30 PM) and James Liddick, (8:55 PM),
Attendees: Susan Michael Brown, Wallace Floyd Design Group
Walter Parker, Building and Grounds Director
Lincoln Lynch, School Business Manager
Meeting Commenced at 7:45 PM.
MANSFIELD HIGH SCHOOL
JTC Delay Claim — MBC received a letter from Michael Callahan requesting additional
compensation ($90K) for construction delays at Mansfield High School. MBC rejected this
proposal due to lack of documentation to support his claim. Chairman noted deficiencies in
JTC's Project Management that could have contributed to a delay i.e. no approved construction
schedule provided to date, insufficient manpower on site, and processing untimely change
orders, etc. Sue Michael Brown to forward a response to JTC rejecting this request.
Change Order Proposals — Review/Approval
COP#212A Ref. Credit to Delete Stove -top in Rm. 126 - ($228.00). MBC initially felt
credit value should be higher. Phil Ricci (JTC) proposed that the Town should not
request any additional credit amount due to conduit in this area that was
previously moved by JTC at no cost.
Status: Approved as recommended by WFDG.
COP#221 Ref. Replace Drinking Fountains at Corridor - $1,898.00/Unit Price.
Status: No action taken. COP to be combined with COP221A.
COP221A Ref. Replace Drinking Fountains at Gym and Corridor - $3,135.00/Unit Price.
Three existing fountains in gym and 8 fountains in corridors need to be made
handicap accessible. MBC asked JTC to provide quote on August 22, 2000.
Discussion was that the cost included in COP#221 and COP#221A (received this
week) is excessive.
Status: MBC asked WFDG to determine least expensive method of fountain
installation; recessed vs. surface mounted units. WFDG to ask JTC to
provide lump sum for installation of all fountains referenced in COP#221
and COP#221A.
COP#225 Ref. Revise Toilets in Rm. 236 & Rm. 240 to shorten distance for handicap
accessibility - Original cost of $19,202.00. Work includes two handicap stalls,
screen, grab bars, etc.
Status: MOTION to approve installation of resin toilet unit as indicated in
COP#225 for a reduced cost of $13,302.00.
DY/WM: Passes 4-0.
COP#226 Ref. Additional General Conditions - $28,728.00.
Status: Rejected. WFDG to issue notice to JTC.
COP#231 Ref. Additional General Conditions 10/5/00 — 10/11/00.
Status: Rejected. WFDG to issue notice to JTC.
COP#232 Ref. Additional General Conditions 10/12/00 — 10/18/00.
Status: Rejected. WFDG to issue notice to JTC.
COP#233 Ref. T&M off -sets to tie in the new diffusers necessary due to new ceiling grid
layouts - $6,657.00.
Status: Rejected. WFDG to issue notice to JTC.
COP#236 Ref. Additional General Conditions 10/19/00 — 10/25/00.
Status: Rejected. WFDG to issue notice to JTC.
COP#242 Ref. Additional General Conditions 10/26/00 —11/l/00.
Status: Rejected. WFDG to issue notice to JTC.
COP#243 Ref. Additional General Conditions 11/2/00 —11/8/00.
Status: Rejected. WFDG to issue notice to JTC.
COP#250 Ref. Additional General Conditions 11/9/00 —11/15/00.
Status: Rejected. WFDG to issue notice to JTC.
COP#251 Ref. Additional General Conditions 11/16/00 —11/22/00.
Status: Rejected. WFDG to issue notice to JTC.
COP#252 Ref. Additional General Conditions 11/23/00 — 11/29/00.
Status: Rejected. WFDG to issue notice to JTC.
COP#253 Ref. Credit for acoustical ceiling in Locker Rooms — ($421.00)
Status: Approved as recommended by WFDG.
COP#258 Ref. HVAC in Locker Room - $12,258.00.
Status: Rejected. Replaced by COP#258A.
COP#258A Ref. HVAC in Locker Room - $7,560.00.
Status: Approved as recommended by WFDG. Sue Michael -Brown advised
HVAC would be authorized Wednesday, December 20, 2000. Door Estimate
pending.
COP#259 Ref. Additional General Conditions 11/30/00 —12/6/00.
Status: Rejected. WFDG to issue notice to JTC.
COP#261 Ref. Locker Room Electrical Work - $7,191.00.
Status: Approved as recommended by WFDG. Sue Michael Brown to issue
letter to JTC to proceed with work.
Specialty Toilet Partition - David Young questioned status of a specialty toilet partition to be
installed by Project Coordinator to meet handicap access needs. Paul Letendre stated that he is
waiting for JTC to provide an aluminum angle. Installation will be scheduled as soon as part is
available.
Locker Room Proposal — MBC is still waiting for JTC to provide final cost proposals from
subcontractors. To avoid further delay, the Committee authorized WFDG and/or MBC
Chairman to approve all reasonable quotes received to date that relate to locker room
modifications. Sue Michael Brown stated that she would review proposals with TCI for
approval prior to authorizing work. Based on cost estimates received to date, WFDG and/or
MBC Chairman is allowed to authorize up to $60K total for this work.
Curb Cuts — Sue Michael Brown noted that COP#219 Ref. Installation of two additional curb
cuts in the amount of $5,000 was approved in Change Order #18, however this would not be
complete until Spring, 2001.
Paving — Sue Michael Brown commented that JTC is planning to pave this Thursday. MBC
warned that winter weather conditions may prevent work to be completed.
Bleacher Concerns — Building and Grounds Dept. reported workers are having extreme difficulty
opening bleachers and that one staff member has filed a Workers Compensation Claim. Walter
Parker questioned whether bleachers installed are the same or comparable to what is specified.
Sue Michael Brown to issue notice to JTC that the installation of new gym bleachers is
unacceptable. Bleachers do not work as specified. WFDG to request a manufacturer's
representative visit site to verify whether installation was done properly. Walter Parker plans to
get quotes for purchase of a mule to assist with opening.
Cracking at Gym — Structural Engineer visited site and determined that cracking is not structural.
Project Coordinator expressed opinion that cracks were existing prior to construction. Cracks
now show more due to recent wall painting.
Incomplete Contract Work - Discussion opened about a significant amount of incomplete
contract work. JTC needs to be notified.
• Site Work — Work is incomplete
• Landscaping — Work is incomplete.
• Re -pointing of Brick— Work is incomplete.
• Exterior Lights — Numerous new exterior wall lights are not working.
• Auditorium — Work is incomplete. Still waiting for Auditorium chairs to be delivered.
• Bathrooms near Auditorium — Work is incomplete. JTC is not cleaning properly.
As-Builts — David Young asked Sue Michael Brown to contact Paul Letendre to determine status
of As-Builts.
JTC/Change Order #18
MOTION to approve JTC/Change Order #18 in the amount of $24,308.00.
Passes: JUDY 5-0.
JTC/Application for Payment #23
MOTION to recommend payment to John T. Callahan & Sons in the amount of
$148,985.71 for work performed at Mansfield High School.
DY/JL: Passed 4-1. Ken Gay opposed.
WFDG Payments —Keyes Associates continues to be delinquent on fees owed to WFDG. Sue
Michael Brown advised the MBC of consequences of Keyes non-payment to WFDG affecting
future work on the School Projects. MBC will continue to pressure Keyes to forward payment
for services provided by their sub -consultant.
Punch List — Sue Michael Brown reviewed status of the Punch List for West and East Wing with
Phil Ricci, Ms. Brown noted some work remains incomplete.
Transformer - Walter Parker noted that the transformer at MHS is being replaced
MHS TRACK/FIELDS RENOVATION PROJECT
Reimbursement - Linc Lynch reported the School Dept. has received verbal confirmation from
SBAB that field work (including East St. fields) is eligible for 67% reimbursement.
Bid Documents - Mr. Lynch advised the MBC that Dave Fischer of Keyes Associates has been
contacted to help generate Design/Build documents. Due to pending legal action against Keyes
Associates, Rich Feeley encouraged the School Dept. to ask SBAB to deviate from policy and
permit selection of another Architect of Record for this work.
General Update - Meeting was held with Lincoln Lynch, School Business Manager Mike Ahern,
Special Project Director and John Moretti, School Superintendent. The follow issues were
discussed:
• School Business Manager to generate and provide MBC with a detailed line item budget.
• School Dept. can approve and process invoices within the project budget. Costs over
budgeted line item amounts need to be discussed with the MBC prior to work performed.
• MBC must be provided with copies of all approved invoices in a timely fashion.
• Construction Manager Responsibilities - Mike Ahern, Special Projects Manager will assume
responsibilities of Construction Manager for this project. Mike Ahern will track manhours
and bill School Dept. for work performed (included any utilization of in-house DPW staff).
East Street Field — MBC questioned construction costs being incurred for work at East Street
Fields. Mr. Lynch advised the MBC that soil test borings were scheduled at East Street without
his knowledge. Mike Ahern has been advised to notify the School Dept of all construction
activity prior work being performed. Linc Lynch stated that Phases of this project have been
prioritized and that per a School Committee vote, work at East Street fields is not to begin until
MHS Track/Field work is complete.
QUALTERS MIDDLE SCHOOL
Insurance Coverage — MBC has advised Linc Lynch that Substantial Completion of the QMS
Project was been issued some time ago. Contractor is no longer responsible to carry insurance
for QMS. Owner is now responsible for coverage. Linc Lynch to follow up status with Town's
current insurance provider.
Project Coordinator Files — Paul Letendre needs to review QMS Project Coordinator files, pack
and prepare them for turn over to Town. Files with transmittal slip to be given to Walter Parker,
School Buildings and Grounds.
Administration Office
• Missing Ceiling Tile — Rich Feeley asked Walter Parker to handle replacement of three
ceiling tiles and grid missing and/or damaged during work on Unit Ventilators.
• Carpet Replacement — Chairman visited site on 12-19-00. During Chairman's conversation
with Phil Ricci it was agreed that JTC would replace the carpet in the main administration
area and office hallway. Color selected by school office staff was Mohawk/Rueben's Red.
Agreement was made between JTC and MBC Chairman to provide aluminum thresholds at
each office doorway in administration in lieu of replacing area of carpet near elevator in
Library (previously damaged by construction activity). Chairman viewed carpet near library
and determined that carpet cleaning at Library is acceptable.
OccupancyIssues
• Egress Plan — Steve Chmura delivered copies of the QMS egress plan to MBC and Building
Inspector earlier today. Mr. Chmura indicated that a stamped affidavit original would be
provided at a later date. MBC transmitted a copy to Walter Parker for reference for
installation of emergency exit signage.
• Handicap Handrail at Cafeteria — Keyes forwarded a request for variance to the Architectural
Access Board (dated 12-11-00) to address Slope of Ramp (24.2.1 variance), Handrails on
Both Sides (24.5.1 variance) and Rail Extended Beyond Slope (24.5.4 Variance).
INVOICES
Keyes Associates - MHS
MOTION to recommend payment to Keyes Associates for Professional Services provided
by Keyes Sub -consultants through November 25, 2000. Total invoice amount of $5,373.56
includes the following; $2,873.07 to Wallace Floyd for locker room revisions plus $314.49
for outside expenses. Fee of $2,186.00 is owed to TCI for locker room revision work.
WM/JL: Passes 5-0.
Letendre Company - MHS
MOTION to recommend Payment to Paul Letendre, Project Coordinator for services
provided at MHS for weeks ending December 9, 2000 and December 16, 2000 in the
amount of $487.50.
DY/KG: Passes 5-0.
CSS Architect — FDMW Facilities Feasibility Study
MOTION to recommend payment to CSS Architects in the amount of $3,065.00 for work
relating to FDMW Facilities Building Plan Concept Options.
WM/DY: Passes 5-0.
School Specialty Products — MHS School Furnishings
MOTION to recommend payment to School Specialty in the amount of $20,373.66 for the
purchase of additional student desks and chairs. WM/JL: Passes 5-0.
School Specialty Products — MHS School Furnishings
MOTION to recommend payment to School Specialty in the amount of $6,618.92 for the
purchase of 28 science tables. WM/JL: Passes 5-0.
OTHER BUSINESS
Jordan/Jackson Roof Liti ag tion —Rich Feeley noted that the Town's expert witness Bob
Baboian, Baboian Associates was deposed by SMI's attorney on Monday (12-18-00). MBC
Chairman is scheduled for deposition this Wednesday, December 20, 2000 in Boston.
Meeting adjourned at 11 PM.
Respectfully Submitted,
Eleanor McCarter, Secretary
David Young, Clerk Date