Minuets of Pre -Construction Conference 5/13/B8
Present: James Russell -Minute Man Eng
Marguritte Russel -Minute Man Eng
David Bruni- Sachem Electric
David Fisher- Larson Assoc:
Judy Epstein-Dcsiqn Partnership
Wilson Raines -Design Partnership
Peter Koczera-Koczera Painting
Donald Snell -Montle Plumbing
Colin Cauldwell-MBC/Chair Library Trustees
Frank Guardabascio-MBC
Steven W. MacCaffrie- MBC Chairman
M,
1. Meetings on site will be at the direction of the Architect
and the Architect will take the notes to he distributed by the
General Contractor.
2" The Contractor advised that he needed the lal relocated as
well as the height of the wires to be checked for truck traffic
on and off the site
\ J" It is noted that Empire Masonry has not returned their
con+ract.The NBC requested that they be kept informed and would
assist if necessary
4. It was requested by the Architect that the sub -contractors
that are working on the site be represented at the weekly
meutings.Meetings with the Architect would he weekly and that
the General Contracter meet with the MBC ton one evening per
month
5. It was pointed out to all Present that the fees are not
waived on this project and that all sub -contractors would he
responsible for their permits and fees
6" It was pointed out that the mobilization areas are under the
control of the General Contractor,
7" It is noted that the testing agency is American Testing fd&m
Braintree and that their specific requirements would be
addresed by the Architect as the work progresses
8" The MBC requested that if any parties had problems they were
to be notified immediately to see that they are resolved in the
best interests of the project and would attempt to be
. responsive to the needs of the project so as not to impede the
� Arogress of the work
+
�
9. It was pointed out that their may be storage space available
at the Town garage( this was checked and upon proper
� lotifjcation the space is available)
10" Discussion of loam and chip storage indicated that the area
behind the Town Garage may be avajlab]e"This storage is at the
option of the General Contractor and will be at no cost to the
Town. This is to facilitate the movement of the contractor on
the site"(this is approved upon proper notification of the
highway dept)
11 It is indicated that site clearing will commence Monday and
that the Arcitect and Landscape Architect will be on site
Tuesday to review the clearing line
12 The General Contractor was advised to contact the
conversation agent as he proceeded with work"