HomeMy WebLinkAboutBOS MINUTES 4-16-2014Board of Selectmen Minutes
April 16, 2014
Present: Jess Aptowitz; Chairman, Doug Annino; Vice Chairman, Kevin Moran; Clerk, George
Dentino. Olivier Kozlowski and William Ross: Town Manager
Chairman Aptowitz called the meeting to order. Chairman Aptowitz reminded that this meeting is
being broadcast live by Mansfield Cable Access and taped for future broadcast.
Mr. Moran read the call for the annual Town Election into the record.
Mr. Moran distributed the most recent punch list for the Board's review. Mr. Ross explained that
the most pressing issue is the wearing course of asphalt, which is scheduled for Friday, April 18t"
and that the remaining items listed cannot be completed until the final wearing course is
completed. Mr. Ross felt this could be completed prior to Town Meeting and if it was not the
Article would be pulled. He explained there is sufficient money being held that if the developer
failed the Town would then use those funds (approximately $70,000) to pay for the final lift.
Chairman Aptowitz asked if the Board was to approve this would it be pending sign off by Town
Officials (Shaun Burke, Rick Alves and Mike Ahern) to which Mr. Ross reported yes. Chairman
Aptowitz questioned what the motion should be as there are punch list items still unresolved and if
the Board should sign the plans. The Mr. Ross stated that nothing is final until Town Meeting acts
on it. Mr. Moran felt a motion could be made to accept the public way and could post prior to
Town Meeting to withdraw if the list is not completed. Mr. Moran also noted that the Board has
handled street acceptances numerous times but never to this degree.
Motion: To approve the laying out of Camden Lane pending the completion of the checklist and
sign all necessary documentation at the acceptance of the motion (Moran/Annino)
Discussion:
Mr. Annino did not feel comfortable signing the plans and Mr. Dentino agreed. Mr. Kozlowski
felt it made logical sense to approve the public way subject to the provision that the Board sign the
plans when all items have been completed. Mr. Moran would like to vote.
Motion: To approve the laying out of Camden Lane pending the completion of the checklist and
sign all necessary documentation at the acceptance of the motion (Moran/Annino) PAILS 2:3
Armin, Dentine, Kozlowski NAY
Motion: To approve the acceptance of Camden Lane subject to the completion of the final punch
list where the Board will then sign the plans (Kozlowski / Annino) PASSES 4:1 Dentine, NAY
To clarify, Chairman Aptowitz stated the layout of the road has been approved subject to getting
the sign off from Town Officials.
Board Of Selectmen's Meeting April 16, 2014
Page 1 of 15
Mr. Ross explained that William McDermott is donating part of 18 Martha's Way to the Natural
Resources Trust. Because the land needs to be sub - divided, as it is one parcel now, there is a $450
permit filing fee for the Planning Department. Both Mr. McDermott and Leonard Flynn, from the
NRT, are requesting a waiver of that fee since the land is being donated to a non - profit for
conservation purposes. Through discussions with Shaun Burke, Town Planner, Mr. Ross noted
there are no out of pocket expenses associated with this fee other than staff time. It was Mr. Ross'
opinion to support the waiver.
Chairman Aptowitz asked if this has been done in the past to which Mr. Ross noted that in the four
years that he has been here this situation has not come up.
Mr. Dentino asked why the land would need to be split. Mr. Ross explained that it is due to the
deed where it currently only has one and would need to be split. Mr. Dentino asked if the land
continued beyond where it is being split to which Mr. Ross was unsure. Mr. McDermott, who was
in attendance, explained it is a 15 acre lot where he has been working with Leonard Flynn of the
NRT to donate approximately seven plus acres. He noted there is a legality to create this land for
the NRT and the expense to engineer it. Mr. McDermott is willing to work with those aspects but
would like the fee to be waived. He noted the land is part of the Wading River and he would then
develop a one house lot on the remaining acres and is in the permitting process for that as well. Mr.
McDermott pointed out the site on GIS for the Board.
Chairman Aptowitz inquired as to why Mr. McDermott would not just create the one house lot on
the entire property and if the issue is taking the seven acres off the land value for tax purposes to
which Mr. McDermott explained the biggest reason is the original owner of the property's
intention was to donate some of the land. When Mr. McDermott purchased the land he agreed to
follow his original direction to donate some of the land.
Mr. Kozlowski noted that at the end of the day, if the Board did not allow the fee waiver, Mr.
McDermott could still go through with his plans and donate the seven plus acres and pay the $450
fee.
Motion: To waive the fee
PASSES 5:0
Present are Russell Barnaby and Bob Palmer, development partners for Chocolate Factory, LLC.
Mr. Barnaby noted that he and Mr. Palmer, given the feedback received from their last
presentation to the Board, had BKA Architects from Brockton, design a proposed Master Plan of
the property per Mr. Annino's request.
In reviewing the site's Master Plan Mr. Barnaby spoke to: the parking capacity for the proposed
mixed use property (80% residential and 20% commercial /retail including a professional medical
building located in the front of the property) could hold approximately 400 — 450 parking spaces,
which will utilize most of the property but yet it will still have a functional layout. Mr. Barnaby
noted they are looking to have a restaurant, perhaps Italian, as well as a chocolate store. Mr.
Palmer referenced a building in the back of the property, which was built in 1942, due to its age it
will be kept for historic tax credit purposes but will probably be used for storage or amenities
(work -out room, community theatre). Inside the Butler Building (11,000 — 12,000 square feet),
metal building built in 1989, and see as industrial/commercial use such as a brewery. Mr. Barnaby
Board Of selectmen's Meeting April 16, 2014
Page 2 of 15
felt it was important to note that there is about seven acres of lightly wood land that is currently not
being used on the property to which Mr. Ross noted that is the location of the water main
easements. Mr. Barnaby also reported that 47 Maple Street is for sale (across from the Oakland
Street property, which is about ten acres) and would be an interesting location for an innovation
center which are usually located in densely populated areas such as Cambridge or Boston. Mr.
Barnaby reported that Chocolate Factory LLC is speaking with two universities about the concept
of an innovation center and intend on keeping a casual dialog until the proposed Chocolate Factory
LLC project is approved at Town Meeting.
Mr. Armin asked about the size of the innovation center to the footprint to which Mr. Palmer
noted the footprint is about 20,000 square feet and Mr. Barnaby reported the innovation center
would be approximately 30,000- 35,000 square feet over two stories. He also noted that it is
important to have feedback from the Town.
Mr. Dentino appreciated the presentation and pinpointing the buildings and their potential usages.
He felt it clearly showed that the group is looking for the highest and best use. Mr. Barnaby noted
that this has been a great learning experience for them as well and thanked the Town Manager's
office for their knowledge and assistance.
Mr. Moran stated the reality is that this particular building will not be used as industrial use and he
is looking at the best possible use of the land and liked the direction that Mr. Barnaby and Mr.
Palmer are taking. Mr. Moran referenced the incubation cell concept that are currently being
offered in New York (tax freeAen year start-ups in incubator zones near state universities and
campuses) and in his business travels is now seeing these advertisements in Memphis. He felt it is
a very innovation approach. Mr. Barnaby stated that Mansfield really needs to leverage its
location.
Mr. Kozlowski asked if the footprint took into account what is of record (water mains, ect.). Mr.
Ross explained that according to the Town's GIS, the water main easements are the only utilities
that the Town is aware of but it is possible that the southerly most of those two mains may not be
active and need to be confirmed. Mr. Ross felt the first objective is to move along with the
renovation of the buildings and as time goes on and demand is there look to this other area so that
we have time to address it.
Chairman Aptowitz again asked about the residential units to which Mr. Barnaby reported 130
units (55 two bedrooms) who also noted an updated fiscal analysis has been submitted. Mr.
Barnaby noted that by State law they will have the option not to rent to school aged children (over
the age of five years) that will share a bedroom with an adult. Chocolate Factory, LLC also did
extensive analysis of the net increase of school aged children for the proposed development, which
can be found in the updated fiscal analysis that will be posted on the Town's website. Chairman
Aptowitz clarified that this is not a rezoning Article but a reuse Article. Mr. Ross added this
Article will only allow for the application for reuse which the Planning Board will then take over
and scrutinize. He also explained that there are historic buildings that are worth preserving and
maintaining that are landmarks in the community and some that are not but this specific building
was particularly mentioned in the Strategic Plan on how to reuse it.
Mr. Kozlowski asked if the units are all in rental form or if there were any condos to which Mr.
Barnaby explained that the market is strong for rentals and they are hoping to utilize and put this
building on the National Register of Historic Places with the Parks Service which requires that for
Board Of Selectmen's Meeting April 16, 2014
Page 3 of 15
five years the tax credits are used for rental units. He also noted the apartments will be market rate
with the exception of affordable units mandated by the Town.
The propose layout of the proposed Chocolate Factory site will be downloaded onto the Town's
website. Mr. Barnaby thanked the Finance Committee for their input as well. Steve Schoonveld,
Vice Chair of the Finance Committee, thanked Mr. Barnaby and Mr. Palmer for working with the
Finance Committee and submitting the updated analysis. Mr. Schoonveld felt it was all positive
whether it was 12 students or 20 students entering into the system. He thanked them for their
extensive efforts and noted the Finance Committee would be voting on the Article at their meeting
on April 17'h.
Mr. Schoonveld did note it would be helpful to have a similar analysis completed for Articles 20,
The Board began review of Articles I — 19. Present ter this discussion are Jol
Finance Director, Scott Feeley and Steve Schoonveld from the Finance Committee.
Article 1: Town Budget
Mr. Ross noted this is a 0.87% increase over last year's budget.
Discussion:
Mr. Dentino wanted to be sure the Town was taking $500,000 out of Free Cash and putting it into
the General Fund to which Mr. Ross responded yes. Chairman Aptowitz noted it is the Free Cash
from year ending June 30, 2013. Mr. Moran noted this is part of a plan worked out with the School
Department, Municipal side and Finance Committee to reduce the Free Cash plug.
Motion: To approve Article 1 as presented (Moran/Kozlowski) PASSES 5:0
Article 2: School Budget
Chairman Aptowitz noted the budget is set for $44,239,757.
Mr. Dentino noted that the $500,000 was being moved from Free Cash to the General Fund.
Motion: To approve Article 2 as presented (Moran/Kozlowski) PASSES 5:0
Article 3: Sale of Electricity
Chairman Aptowitz noted this is statutory language from Chapter 164 of Mass General Law.
Motion: To approve Article 3 as presented (Moran/Kozlowski) PASSES 5:0
Article 4 — Motion 1: Budget for Water Department
Motion: To approve Article 4, Motion 1 as presented (Moran/Kozlowski) PASSES 5
Article 4 — Motion 2: Budget for Waste Water Department
Motion: To approve Article 4, Motion 2 as presented (Moran/Kozlowski)
Discussion:
Mr. Dentino asked if the Unfunded Liability, Indirect Costs and Capital Outlay are just for the
Water Department to which Mr. Ross noted yes and is true for all of the Enterprise accounts.
Motion: To approve Article 4, Motion 2 as presented (Moran/Kozlowski) PASSES 5:0
Article 4 — Motion 3: Airport
Motion: To approve Article 4, Motion 3 as presented (Moran/Kozlowski) PASSES 5:0
Board Of Selectmen's Meeting April 16, 2014
Page 4 of 15
Article 4 — Motion 4: Parking Enterprise Fund Revenue
It was noted by Mr. Stanbrook that the wording of the dollar amount was incorrect and a revision
was needed.
Motion: To approve Article 4, Motion 4 subject to correction noted (Morarr/Kozlowski)
Discussion:
Mr. Dentino asked if the $50,000 for Capital Outlay was due to the payment system. Mr. Ross
explained that the Mr. Dentino is referring to is in 2014 and was due to the BETA study. Mr.
Dentino stated the BETA study went beyond the limits of the parking enterprise account to which
Mr. Ross answered yes, from the standpoint of moving in and out of that location — an extension of
parking on that site.
Motion: To approve Article 4, Motion 4 subject to correction noted (Moran/Kozlowski) PASSES
5:0
Article 5: School Sheet Sewer Interceptor Project
Mr. Ross explained that the project is complete but there is still the authorization for that amount.
This Article will take that off the books and means the Town no longer has exposure for debt.
Motion: To rescind the authorized, but unissued balance of $270,000 for the for the School Street
Sewer Interceptor Project, which is no longer needed to complete that project (Moran/Kozlowski)
PASSES 5:0
Article 6: Transferring of Funding Items Between Town Departments
Motion: To move the sum of $540,554.61 be transferred or appropriated from the funding sources
listed to increase and or decrease the appropriations for the Municipal Town departments as shown
for the ensuing 12 month period beginning July 1, 2013 as voted pursuant to Article I and Article
4 of the May 7, 2013 Annual Town Meeting (Mr. Moran read each line item as presented)
(Moran/Kozlowski)
Discussion:
Mr. Dentino stated if a department had other expenses back in 2013 and are transferring from
Personal Services to Other Expenses a year back, if the other expenses had been funded correctly
(to the number) that would have been Free Cash, Mr. Ross stated there cannot be an overage in an
appropriation — it must be balanced but if there is an underage it would go to Free Cash. Mr.
Stanbrook stated each year is its own and must be reconciled within that year.
Mr. Dentino inquired as to the Parking/Parking Enterprise items to which Mr. Ross stated that was
a correction where the $50,000 should have been taken out of Retained Earning at the beginning of
the year but it did not happen. He stated the DOR recommended doing it now or the Town would
not be able to set the tax rate.
Motion: To move the sum of $540,554.61 be transferred or appropriated from the funding sources
listed to increase and or decrease the appropriations for the Municipal Town departments as shown
for the ensuing 12 month period beginning July 1, 2013 as voted pursuant to Article I and Article
4 of the May 7, 2013 Annual Town Meeting (Mr. Moran read each line item as presented)
(Moran/Kozlowski) PASSES 4:1 Dentino NAY
Mr. Dentino did not like that it was an all or nothing Article
Article 7: Eliminating Deficits Existing at the End of FY2013
Board Of Selectmen's Meeting April I6, 2014
Page 5 of 15
Motion: To move the sum of $3,985.05 be transferred from Free Cash in the treasury of the Town,
to eliminate the deficits existing at the end of Fiscal Year 2013 as of June 30, 2013 in the accounts
listed (Mr. Moran read the accounts) (Moran/Kozlowski) PASSES 4:1 Dentino NAY
Mr. Dentino did not like utilizing Free Cash,
Article 8: To Pay Unpaid Prior Year's Bills
Motion: To move the sum of $22,642.41 be transferred from the funding sources listed to pay the
unpaid prior year's bills as shown (Mr. Moran listed the unpaid bills and the funding sources)
(Moran/Kozlowski) PASSES 4:1 Dentino NAY
Mr. Dentino did not like utilizing Free Cash and asked, with respect to Parking, what ParkMobile
was to which Mr. Ross explained it allows for commuters to pay parking bill over the internet via a
cell phone. A change in staff in the DPW was the cause of the numerous bills unpaid. Mr. Dentino
approved of the ParkMobile service.
Article 9: Abatements and Exemptions (Overlay) Accounts
Motion: To move the sum of $1,072.66 be transferred to and from the listed Allowance for
Abatements and Exemptions (Overlay) accounts as set forth (Mr. Moran listed the sources and
destinations) (Moran/Kozlowski) PASSES 5:0
Article 10: Defray the Expenses of the FY2017 Triennial Revaluation of all Town Properties
Motion: To move the sum of $40,000 be transferred from the closed General Fund articles set
forth to be spent by the Town Manager to defray the expenses of the FY2017 Triennial
Revaluation of all Town properties (Moran/Kozlowski) PASSES 5:0
Article 11 — Motion 1: Airport Land Acquisition and /or Avigation Easements and Tree
Clearing
Motion: To move the sum of $7,150 b appropriated, to be expended by the Mansfield Airport
Commission for the purpose of airport land acquisitions and /or avigation easements and tree
clearing; and to meet this appropriation, $7,150 be transferred from Airport Enterprise Fund
Retained Earnings (Moran/Kozlowski) PASSES 4:1 Kozlowski NAY
Article 11 — Motion 2: Airport Paying Town Portion of Costs Related To Obstruction
Removal at Mansfield Airport
Motion: To move the sum of $51,000 be appropriated, to be expended by the Mansfield Airport
Commission for the purpose of paying for the Town's portion of the costs related to obstruction
removal at the Mansfield Airport as per the Airport Master Plan; and to meet this appropriation,
$51,000 be transferred from the Airport Capital Improvement Account authorized by Article 11 of
the May 7, 2013 Annual Town Meeting (Moran/Kozlowski) PASSES 4:1 Kozlowski NAY
Article 11— Motion 3: Airport Administration Building
Motion: To move the sum of $193,899 be appropriated to be expended by the Mansfield Airport
Commission for the purpose of paying for the Town's portion of the costs related to a new
administration building at the Mansfield Airport; to meet this appropriation, $85,707 be
transferred from the Airport Capital Improvement Account authorized by Article 8 of the April 24,
2012 Annual Town Meeting and $108,192 be transferred from Airport Capital Improvement
Account authorized by Article 9 of April 24, 2012 Annual Town Meeting (Moran/Kozlowski)
PASSES 5:0
Board Of selectmen's Meeting April 16, 2014
Page 6 of 15
Article 12 — Motion 1: Capital Improvement Projects
Motion: To move the sum of $651,678 be appropriated to be spent by Town Manager for the
various listed Capital Improvement Projects for the Town of Mansfield, including all costs
incidental and related and to meet this appropriation, $651,678 be transferred from Free Cash in
the treasury of the Town, the sums listed being intended to be estimates of the individual items but
the amount to be appropriated being the one line item in the total amount of $651,678 and the
Town Manager be authorized to distribute such funds in such a mariner as may be needed to
accomplish the list of items, provided however, that each item contained in the list set forth be
undertaken and that any excess funds be available because one or more of the listed items cost less
than was estimated and not because an item intended to be purchased is not so purchased
(Moran/Kozlowski) PASSES 4:1 Dentino NAY
Chairman Aptowitz inquired about the cruiser to which Mr. Ross noted this vehicle would be
purchased and not leased and assigned to investigation or non - patrol and would have a longer life
than three years.
Mr. Dentine takes issue with the utilization of Free Cash. Mr. Kozlowski asked where Mr.
Dentino felt the Free Cash should go to which he responded he would answer at the conclusion of
the Article review.
Article 12 — Motion 2: Capital Improvement for Fire Department
Motion: To move the sum of $298,000 be appropriated to be spent by Town Manager for listed
Capital Improvement Projects for the Town of Mansfield including all cost incidental and related
thereto; and to meet this appropriation, $270,000 be transferred from the Mass. General Laws
Chapter 44 Section 53E %2 Ambulance Fee Revolving Fund and $28,000 be transferred from the
Mass. General Laws Chapter 44 Section 53E '/2 Radio Master Box Fee Revolving Fund
(Moran/Kozlowski) PASSES 5:0
Article 12 — Motion 3: Road/Bridge Sidetivallr/Repairs/Replacement Project
Motion: To move the sum of $2,000,000 be appropriated to be spent by the Town Manager for a
Road/Bridge Sidewalk/Repairs/Replacement Project including the payment of all costs incidental
and related thereto, and to meet this appropriation, the Treasurer, with approval of the Selectmen,
is authorized to borrow $2,000,000 to pay costs of the
Road/Bridge/Sidewalk/Repairs/Replacement Project, under and pursuant to Chapter 44, Sections
7(5) and 7(6) of the General Laws or pursuant to any other enabling authority, and to issue bonds
or notes of the Town therefor (Moran/Kozlowski)
Discussion:
Mr. Dentino noted this is the Town first Article of borrowing for $2,000,000.
PASSES 5:0
Article 12 — Motion 4: Capital Improvement Projects — School
Motion: To move the sum of $637,000 be appropriated to be spent by the Town Manager with the
approval of the Mansfield School Committee for the following Capital Improvement projects for
the Town of Mansfield including all costs incidental and related thereto; the sums shown are
intended to be estimates of the individual items but the amount to be appropriated is the one line
items in the total of $637,000; and further that the appropriations be made available for
expenditure immediately upon passage of this Article and to meet this appropriation, the Town
transfer from Free Cash in the treasury of the Town the sum of $637,000 (Moran/Kozlowski)
Discussion:
Board Of Selectmen's Meeting April 16, 2014
Page 7 of 15
Mr. Annino asked what the current cost of the Robinson Window Project is to which Mr. Ross
stated approximately $1.1 million. Chairman Aptowitz noted it is not so much the windows but
the caulking. Mr. Annino took issue with this cost. The Chairman asked Mr. Ross to follow up on
the exact current cost, the status of the project and any expected future cost.
Mr. Feeley, member of the Finance Committee, explained that this project came in phases and
noted this should be the final phase. Mr. Feeley noted the Capital Committee was concerned with
the entire process as was the Finance Committee where a rigorous process will need to be
implemented where projects and its items and costs are heavily scrutinized and more questions are
asked.
PASSES 5:0
Article 12 — Motion 5: Wastewater - Related Inflow and Infiltration Removal
Motion: To move the sum of $300,000 be appropriated to be spent by the Town Manager for
Wastewater - related Inflow and Infiltration Removal costs including the payment of all costs
incidental and related thereto; and to meet this appropriation $300,000 be hereby appropriated
from Wastewater Enterprise Fund Retained Earnings (Moran/Kozlowski) PASSES 5:0
Article 12 — Motion 6: Wastewater - Related Design/Build Treatment Plant Phase II
Motion: To move the sum of $3,400,000 be appropriated to be spent by the Town Manager for
Wastewater - related Design/Build Treatment Plant Phase II costs, including the payment of all
costs incidental and related thereto, and to meet this appropriation the Treasurer, with the approval
of the Board of Selectmen, is authorized to borrow $3,400,000 to pay costs of the Wastewater
Design/Build Treatment Plan Phase II Project, under and pursuant to Chapter 44 Section 7(1) of
the Mass. General laws, or pursuant to any other enabling authority, and to issue bonds or notes of
the Town therefor (Morau/Kozlowski) PASSES 5:0
Article 12 — Motion 7: Capital Improvement Projects — Water Department
Motion: To move the sum of $340,000 be appropriated to be spent by the Town Manager for the
following Capital Improvement projects for the Town of Mansfield including all costs incidental
and related thereto; the sums shown are intended to be estimates of the individual items but the
amount to be appropriated is the one line item in the total of $340,000 and to meet this
appropriation, the Town transfer from Water Enterprise Fund Retained Earning the sum of
$340,000 subject to the item description of "Water Main" be changed to "Water Meter"
(Moran/Annino)
Discussion:
Chairman Aptowitz asked for further clarification of Vehicle #58 to which Mr. Ross was unsure.
The Chairman wanted further information prior to voting. Mr. Moran recalled it was a reasonable
expenditure. Mr. Kozlowski asked if the Town was purchasing additional Water Meter Radio
Readers to which Mr. Ross noted it is a part of a replacement schedule plan where they are
reaching a point of replacement. Mr. Kozlowski asked if they run out to which Mr. Ross noted the
technology continuously changes. Chairman Aptowitz would also like additional information
regarding the Water Meter Radio Readers. Mr. Moran felt that these items are each vetted by
numerous Committees before they get to the Board (Finance, Capital Improvement, Planning,
School and Building). Mr. Feeley noted that there is a robust amount of information on these items
which the Committees have available. If the Board would like additional information, in the
future, they will be able to accommodate that request. Mr. Moran noted that the Capital Budget
was completed in December.
Board Of Selectmen's Meeting April 16, 2014
Page 8 of 15
FAILS 1:3:1 Annino, Dentino, Kozlowski NAY and Aptowitz ABSTAIN
The Board will reconsider their vote when more information is available. Mr. Ross will have that
for next week's board meeting.
Article 12 — Motion 8: Water - related Maple Street Water Main Replacement Project
Motion: To move the sum of $1,325,000 be appropriated to be spent by Town Manager for the
Water - related Maple Sheet Water Main Replacement Project, including the payment of all costs
incidental and related thereto, and to meet this appropriation the Treasurer, with the approval of the
Board of Selectmen, is authorized to borrow $1,325,000 to pay costs of the Maple Street Water
main Replacement Project, under and pursuant to Chapter 44 Section 8 of the Mass. General Laws,
or pursuant to any other enabling authority, and to issue bonds or notes of the Town and further
that this appropriation be made available for expenditure immediately upon passage of this Article
(Moran/Kozlowski) PASSES 5:0
Mr. Dentino would like to note the Town is now borrowing $1,320,000.
Article 12 — Motion 9: Capital Improvement - Parking
Motion: To move the sum of $150,000 be appropriated to be spent by Town Manager for the
Capital Improvement projects for the Town of Mansfield including all costs incidental and related
thereto; the sums shown are intended to be estimates of the individual items but the amount to be
appropriated is the one line item in the total of $150,000 and to meet this appropriation, the Town
transfer from Parking Enterprise fund Retained Earnings the sum of $150,000 (Moran/Kozlowski)
Discussion:
Mr. Annino asked about the Mansfield Avenue improvements to which Mr. Ross noted it is due to
the redirection of traffic, sidewalks and restriping the streets for parking.
PASSES 4:1 Dentino NAY
Mr. Dentino's NAY vote reflects the Parking Garage Feasibility Study. There was a discussion
focused on whether these Articles should be voted via a la carte or all /nothing. Mr. Ross reminded
the Board that amendments can be made on the floor but Mr. Dentino felt that was very involved
for the residents and needs to be in writing.
Article 13: Completion of Capital Projects
Motion: To move the sum of $81,593.84 be transferred from the listed unexpended amount of
money that were initially borrowed to finance capital projects that are now complete, and for
which no further liability remains, to pay costs of the new purposes listed, each of which is a
purpose for which the Town is authorized to borrow for a term equal to or greater than the term or
terms for which the amounts to be transferred were originally borrowed, as permitted by Chapter
44 Section 20 of the Mass. General Laws (Moran/Kozlowski)
Discussion:
Mr. Annino asked if the cost of the gym wall was known to which Mr. Stanbrook thought it was
between $875,000 - $900,000 but would get the exact figure. PASSES 5:0
Article 14: Residents to Receive An Additional Real Estate Tax Exemption
Motion: To move that for Fiscal Year 2015, Mass, General Laws Section 4 of Chapter 73 of the
Acts of 1986 as amended by Chapter 126 of the Acts of 198, which allows residents to receive an
additional Real Estate Tax Exemption of 100% on Clauses 17D, 22, 22A, 22B, 22C, 22D, 22E,
37A and 41C of Section 5 of Chapter 59 of the Mass. General Laws be hereby accepted; that
Chapter 59 Section N of the General Laws be hereby accepted by the Town, including both that
Board Of Selectmen's Meeting April 16, 2014
Page 9 of 15
125 hour limitation and designation of representatives be also accepted from the final paragraph of
said Section N and that the sum of $3,750 be hereby raised and appropriated from the Fiscal Year
2015 Tax Levy and other General Revenues from the Town , to add to the FYI Allowance for
Abatements and Exemptions (Overlay) account to provide funding for the "Veterans Tax
Work -Off Program" as allowed by Mass. General laws Chapter 59 Section N (Moran/Kozlowski)
PASSES 5:0
Article 15: Authorization of Revolving Funds for Fiscal Year 2015
Motion: To move that the listed Revolving Funds be authorized for Fiscal Year 201 in accordance
with Mass. General Laws Chapter 44 Section 53E % and under the following specification as set
forth and that each such Revolving Fund shall be credited with the balance remaining in such
Revolving Fund at the end of FY2014 (Moran/Kozlowski) PASSES 5:0
Article 16: Employee Other Post - Employment Benefits (OPEB) Liability Trust
Motion: To move that the sum of $400,000 be appropriated to the Employee Other
Post - Employment Benefits (OPEB) Liability Trust Fund and to meet this appropriation, $400,000
be raised and appropriated from the FY15 tax levy and other general revenues of the Town
(Moran/Kozlowski) PASSES 5:0
Article 17: Transfer from Free Cash to the Town's Capital Stabilization Fund
Motion: To move the sum of $50,515 be transferred from Free Cash in the treasury of the Town to
the Town's Capital Stabilization Fund (Moran/Kozlowski) PASSES 5:0
Article 18: Transfer from Free Cash to the Town's Stabilization Fund
Motion: To move the sum of $250,000 be transferred from Free Cash in the treasury of the Town
to the Town's Stabilization Fund (Moran/Kozlowski) PASSES 5:0
Article 19: Design, Construction, Equipping and Furnishing New Department of Public
Works Garage Facility
Motion: To move the sum of $13,600,000 be appropriated to be spent by the town Manager to pay
costs of designing, constructing, originally equipping, and furnishing a new Department of Public
Works garage facility, including the payment of all costs incidental and related thereto; and that to
meet this appropriation, the Treasurer, with the approval of the Selectmen, be hereby authorized to
borrow $13,600,000 under and pursuant to Mass. General Laws Chapter 44 Section 7 (3), or
pursuant to any other enabling authority, and to issue bonds or notes of the Town therefor;
provided, however, that his vote shall not take effect until the Town votes to exempt from the
limitations on total property taxes imposed by Chapter 59 Section 21C of the Mass. General Laws
( "Proposition 2 % ") all amounts required to pay the principal of an interest on the borrowing
authorized by this vote. Mr. Moran noted this will need to pass by 2/3 vote. (Moran/Kozlowski)
Discussion:
Mr. Kozlowski noted that the hope with this project was to bring it in line with retiring debt so that
there would be no impact to the residents. Mr. Ross reminded that it was "minimal impact" and
not "no impact ". Chairman Aptowitz asked what the impact would be to an average home to
which Mr. Stanbrook explained if the Article were to pass this year, using the FY 14 tax rate (which
is the only number available) and the median residential home value in Mansfield is $339,300
there would be an impact of $120.47 and the average home is $362,625 and there would be an
increase of $128.75. Chairman Aptowitz noted that would be considered debt exclusion.
Board Of Selectmen's Meeting April 16, 2014
Page 10 of 15
Mr. Kozlowski and Chairman Aptowitz asked how much the Town would have to borrow to be an
offset to the debt coming off the books to which Mr. Stanbrook noted the tax levy would go up no
matter if the Article passed or not thus no number would be a net zero. Chairman Aptowitz asked
how much can the Town borrow that won't have any debt exclusion impact. Mr. Stanbrook noted
that $700,000 is coining off for FYI in principle and interest and Mr. Ross noted it would finance
about $7 million. He explained the rule of thumb is to take the PMI and multiply by 10 and that is
about how much to borrow.
Chairman Aptowitz noted'the current facility is a wreck and the Town needs to do something but
in his mind he believed it was going to be expense neutral or pretty close to that but $130 added on
to taxes as it is isn't necessarily neutral.
Mr. Kozlowski rephrased and asked how much highway garage the Town can get with no impact.
Mr. Moran stated probably just cosmetically assisting the current facility. Mr. Ross did not believe
the Town could get anything useful with that amount. Chairman Aptowitz asked if that was
studied in Capital Improvement.
Mr. Feeley noted this was studied extensively and felt the Board was taking part in an incomplete
discussion. Ile explained that the nature of the facility that is being built is also going to generate
substantial operational savings during its life and noted it is north of $8 million (with efficiency,
heating and equipment being inside, manpower and overtime). FIe felt that the Capital
Improvement study emphasized the maximization of those benefits and questioned if a lesser
facility would have the same results. He stated that as the Town would need a debt exclusion to
purchase the facility the Town would see the benefit on the operational side during the facility's
life. Mr. Kozlowski felt the operational savings could easily get swallowed up in other operational
costs in the next five to ten years. Chairman Aptowitz felt it would be up to the residents to make
the call and would need a 2/3 vote at Town Meeting and then would need to vote on at a Special
Election.
Mr. Annino was not comfortable voting on a $13 million project with no backup let alone
discussing it. Mr. Ross and Mr. Moran noted there was a presentation to the Board to which Mr.
Annino reminded it was a schematic design presentation where there was discussion of design
build. Mr. Annino is not convinced the Town needs a $13 million DPW garage.
Mr. Dentino would like to see the plans as it is a lot of money.
The Chairman felt the Capital Improvement Committee did a great job but the Board is the
gatekeeper and felt more discussion was needed before voting on this Article. Mr. Moran felt that
beyond Capital Improvement the Board has had enough information on this for a while as well as
figures presented to the Board and was surprised that members are acting shocked at this figure.
Mr. Armin stated he was shocked at the figure at the initial presentation. Chairman Aptowitz
noted he was expecting a minor at most impact to the tax payer. He is questioning the debt
exclusion. Mr. Annino stated the Town is looking at tax increases every year and this would be
another one on top of those so in his mind it would need to be justified.
Mr. Ross noted the other part to this is if you look at some of the other buildings that have been
done (on the cheap) and now are not working. He noted the Plymouth Street Fire Station and some
others. He felt this proposal was done correctly and that the costs are very comparable to other
communities who have done the same thing. He noted the Town could build a $7 million facility
Board Of Selectmen's Meeting April 16, 2014
Page 1 I of 15
with equipment outside and not gain a great deal in terms of efficiency of operations. Mr. Ross
said putting substantial money into the current facility would not be worth it to which Mr. Annino
agreed. Mr. Annino also stated there are a hundred different ways to look at how to budget
something and sometimes you need to be inventive and constructing something that is
economically viable.
Chairman Aptowitz moved the discussion to the possibility of one large building housing DPW as
well as Public Safety. Mr. Feeley noted there has not been a proposal with that in mind in a
location that could accommodate a facility of that nature. Mr. Ross felt that if this was about the
location then that is a different discussion and stated he is convinced there is not enough room at
the existing DPW site for a facility of that nature. Chairman Aptowitz stated the Fruit Street
location just came about and that the Board did not vote to put it there.
Chairman Aptowitz stated Mr. Moran is 100% correct that the Board had the number and the
expenses but it was the detail of the financing that the Board did not discuss. Mr. Stanbrook noted
that the fall off fi•om last year to this year was $657,727 and reminded that all debt exclusions will
be gone by FY20. Mr. Moran if there was any ramification to letting all the debt fall off to which
Mr. Stanbrook stated the tax rate would be lower.
Mr. Annino stated the Town cannot make Mansfield unaffordable to potential residents and
businesses.
The Article was tabled for further discussion at next week's Board meeting.
o n
a s
The Board would like the Finance Committee to review Articles 20 (TOD). 21.22 and Articles 28
and 29. Mr. Schooveld and the Finance Committee will provide feedback at next week's Board
Mr. Ross reported that the budget is balanced. He explained that the number for Charter Schools
was slightly reduced than originally budgeted so adjustments were made. The School Department
was informed of that change. The Chairman would like to see a final press release distributed. Mr.
Ross noted that the School Committee has supported the Municipal budget and recommended that
the Board do the same for them as it is important and really is an integrated budget.
Chairman Aptowitz asked that the Article be placed on the Town Website so that residents can
digest the information and be able to associate with the appropriate Article number and attend
Town Meetina well informed.
None.
A. Approval of Warrants
Town Vendor Warrant No. 14042T $360,857.91
Motion: To approve Town Vendor Warrant No. 14042T $360,857.91
(Kozlowski/Moran) PASSES 5:0
Electric Department Vendor Warrant No. 14042E $510,505.40
Motion: To approve Electric Department Warrant No. 14042E $510,505.40
(Kozlowski /Moran) PASSES 5:0
Board Of Selectmen's Meeting April 16, 2014
Page 12 of 15
School Department Vendor Warrant No. 14042S $441,736.40
Motion: To approve the School Department Vendor Warrant No. 140425 $441,736.40
(Kozlowski /Dentino) PASSES 5:0
Town Payroll Town Medicaid Payroll Warrant No. 14042PT $290,881.16
Motion: To approve "Town Payroll Town Medicaid Payroll Warrant No. 14042PT
$290,881.16 (Kozlowski /Amiino) PASSES 4:1 Dentino NAY
Town Deductions Vendor Payroll Warrant No. 14042TV $89,909.32
Motion: To approve Town Deductions Vendor Payroll Warrant No. 14042TV
$89,909.32 (Kozlowski /Annino) PASSES 5:0
B. License and Permit Approval
• Consideration of Water Installer's License For W. Walsh Company
Motion: To approve 2014 Water Installer's License for W. Walsh Company
(Kozlowski/Moran) PASSES 5:0
• Consideration of Hackney License for Veterans Taxi for Paul Thibeault
Motion: To approve Hackney Driver's License for Paul Thibeault with Veterans Taxi to
expire March 31, 2015 (Kozlowski /Annino) PASSES 5:0
• Consideration of Commercial Parking Facility Application For Xfinity Center Located At
885 South Main Street
Motion: To approve a commercial parking facility license for the Xfinity Center to expire
April 30, 2015 (Kozlowski /Annino) PASSES 5:0
• Consideration of Common Victuallers License for Capriotti's Sandwich Shop Located At
321A School Street
Motion: To approve common victuallers license for Capriotti's Sandwich Shop subject to
final walk through from Board of Health and Building Department issuing a certificate of
occupancy (Kozlowski /Annino) PASSES 5:0
C. Events
• Consideration of Event Application For The Jamie Fund 5K Road Race & Walk
Motion: To approve the Jamie fund 5K Road Race and Walk subject to Public Safety,
Board of Health and Building Department restrictions (Kozlowski /Moran) PASSES 5:0
Motion: To approve the banner as presented for the Jamie Fund Road Race and Walk
(Annino/Moran) PASSES 5:0
• Consideration of Event Application For The 2nd Annual Run From The Cops
Motion: To approve the 2nd Annual Run From The Cops (Kozlowski /Annino) PASSES
5:0
D. Correspondence
• Letter From Richard Bros. Electric Regarding Customer Service Of The Building
Department Staff
• Letter From MassDOT In Regards To Winter Rapid Recovery Program
• Police Chief Sellon's Monthly Report
Mr. Ross has signed and returned contracts to the State in regards for the projects paid for by the
roughly $311,000 received from the State for winter recovery repairs to the streets. Mr. Ross
noted that contractors have been scheduled and the work should be completed by the end of the
fiscal year.
Mr. Ross brought the Indemnification Agreement for the Xfinity Center for the Board to sign. It
was approved at the previous week's meeting but Mr. Montgomery had left prior to signing.
Board Of Selectmen's Meeting April 16, 2014
Page 13 of 15
Mr. Ross reported on miscellaneous Highway Updates: contractor performing tree trimming on
various roads where trees are too low, Lorusso Corp. making road repairs so that chip sealing can
be completed this spring (hoping to begin April 21St), Sealcoating, Inc. began cracksealing last
Monday (April 14th) and town -wide street and sidewalk sweeping is in the process.
The office will be closed on Monday, April 22 ad due to the Patriots Day holiday.
Mr. Ross asked if Monday, April 281h would work for an Electric Board meeting. Mr. Dentino
reported it would.
Mr. Ross reported the motions are mostly complete and Mr. DeRensis is working on the remaining
Articles and motions.
Mr. Ross noted the Town is in discussions with the Clemmey's regarding the public safety detail
payments for the private commercial lots. A report will be issued from Town Counsel with review
of the commercial t)arkina facility's license renewal.
Mr. Dentino called into question how much Free Cash the Town needed to spend and noted that
when all tallied the (actual) Free Cash for FYI Budget was $2,608,517. He noted that $217,500
was transferred to Stabilization and felt that amount not to be efficient compared to what is being
spent by Free Cash.
In regards to the Parking Enterprise Account, Mr. Dentino remembered that the last reported
revenues for that account was $345,000 - $360,000 and asked if the Town is getting $350,000
(plus or minus) in revenues and appropriating $617,000 in FYI 5, how long will the Parking
Enterprise Account remain positive because the Town is not only taking revenue but retained
earnings. Mr. Ross noted revenues are estimated to be $556,000 for Parking Enterprise and the
expenditures are estimated to be $555,806 (numbers may vary). Mr. Ross felt the revenue stream
to be fairly solid and noted that in previous years the lots were not always filled up when the Town
was charging $4. Mr. Dentino stated the Town will still exhaust just about everything it makes in
appropriations. Mr. Ross felt there was still a sufficient balance.
Mr. Moran commented on the how smoothly the budget process has been this year. He was
appreciative of the efforts of the Finance Committee, School, John Stanbrook and Mr. Ross in
taking into account the Strategic Plan and allowing the Town to move forward.
Chairman Aptowitz noted that the Board has gone through a lot of battles over the years
concerning the budget and it is nice to see management sit down to achieve a cohesive budget that
is best for both the Town and the Schools. He appreciated the cooperation of both Brenda Hodges
and Ed Vozzella and the work done by Mr. Ross and Mr. Stanbrook.
Chairman Aptowitz sent his best to Larry Crossman.
None.
Board Of Selectmen's Meeting April 16, 2014
Page 14 of 15
Motion: To adjourn the BOS meeting at 10:39pm
J, �,, PV
1
Signature of C erk
/Tracey Whalen
Board Of Selectmen's Meeting April 16, 2014
Page 15 of 15
Annino) PASSES 5:0
Date of Approval