Meeting Minutes of January 23, 2001
ers ?_ Richard Feeley, Chairman, Kenneth Gay and James Liddick
Eleanor McCarter, Secretary
William Moore — Excused Absence
David Young — Excused Absence
Attendees: Steve Chmura, Keyes Associates
Robert Mangiaratti, Volterra, Goldberg, Mangiaratti, and Jacobs
Meeting Commenced at 7:45 PM.
QUALTERS MIDDLE SCHOOL
Project Coordinator Files — Walter Parker informed the Committee that Project Coordinator files
were removed from the JTC Office by his staff as requested. Files are now in his possession.
Additional documentation, drawings, plans etc. still need to be removed.
JTC /Change Order #21
COP #314 Ref. Additional material cost due to change in size of Lintels. Original cost
proposal of $14K (plus mark up) to upgrade size of lintels was never submitted by
JTC. Additional work is not included per contract. Mr. Larkin advised the MBC
on November 28, 2000, that he would accept cost of only materials as payment.
Michael Callahan had conversation with Ken Larkin earlier this week proposing a
reduced amount of $5,400. Per Steve Chmura, Mr. Larkin did not agree to accept
the amount proposed and requested added cost of labor be included.
Status: No Action Taken. Steve Chmura to forward letter to Larkin Iron
reiterating Ken Larkin's conversation with the MBC (11- 28 -00), whereby he
proposed to accept payment for only the cost of material ($8790.50) without
any mark up to JTC.
Electrical — Per Steve Chmura, electrical contract work is incomplete.
Keyes Associates Manpower — Bob Vogel advised the MBC on 1 -9 -01 that he would continue to
be the "Point Person" representing Keyes Associates for the QMS Project. Mr. Vogel did not
attend tonight's MBC Meeting as expected. Mr. Vogel was asked to provide various updates to
the MBC at tonight's meeting including financial analysis of Keyes' payments to subcontractors
as well as other project - related issues. This information was not provided.
Operating and Maintenance Manuals — Walter Parker commented that O & M documentation,
provided by JTC to date, is incomplete. Steve Chmura asked Walter Parker to review Project
Coordinator files for O &M Manuals believed to be missing. Jim Liddick suggested that if it
becomes necessary, Walter Parker could contact the appropriate Manufacturer Rep. directly to
obtain any necessary materials not provided.
Status of O &M's ry 1- 23 -01:
Mechanical: O &M Manuals — School Dept. Received.
As Built Drawings (including controls) — School Dept. Received.
• Balancing Reports - Reports are Incomplete (as of 1- 23 -01).
Electrical: O &M Manuals — School Dept. Received.
As Built Drawings — Not Received.
Plumbing: O &M Manuals — School Dept. Received.
As Built Drawings - Not Received.
Fire Protection: O &M Manuals - School Dept. Received.
As Built Drawings — School Dept. Received.
Architectural: O &M Manuals - Not Received.
As Built Drawings — JTC has in possession, but has not turned
over to School Dept.
Project Close -Out — JTC previously indicated to the MBC that outstanding contract work at
QMS would be completed within two weeks. MBC expressed disgust with the lack of effort put
forth by JTC to complete contract work as promised. JTC provided no explanation to the
Committee for work not performed. Decision was made to deny Application for Payment #24
and direct Keyes Associates to generate a deduct Change Order in the amount of $165,606.00
(with specific amounts identified for each trade effected) to close out the QMS Project.
Egress Plan —Steve Chmura reported that a "Stamped" Egress Plan was hand delivered by Keyes
to Nick Riccio, Building Inspector.
Handrail on one side at Cafeteria — Walter Parker agreed to coordinate installation of handrail
required for final occupancy permit.
Affidavits:
Architectural Affidavit - Keyes Associates has provided.
Mechanical Affidavit — TCI has not provided due to Keyes non - payment issues.
Electrical Affidavit - TCI has not provided due to Keyes non - payment issues.
Plumbing Affidavit - TCI has not provided due to Keyes non - payment issues.
Structural Affidavit - Sarkis Zeronian has not provided due to Keyes non - payment issues.
Affidavits from sub - consultants are owned per contract and are required by Building Inspector
prior to Final Occupancy Permit. Rich Feeley to contact TCI and Zeronian Assoc. to follow up.
Unit Ventilators — Walter Parker advised the MBC that his school staff plumber (Dan Avery) is
scheduled next week to replace inoperable hot water valve on the unit ventilator located in the
Cafeteria. Johnson Controls has provided material. Montle Plumbing is responsible for
installation per contract, but has refused to perform installation to date.
Acid Waste Neutralizing Tank — Issue re: neutralization tank located in Science Rm. 130 was
improperly installed by Montle Plumbing. MBC and School Dept. expressed dissatisfaction in
Montle Plumbing's lack of response to correct the hazardous situation in a timely fashion.
Classroom had to be closed and programming suspended for one week due to severe odors from
sink. Plumbing is now corrected.
KEYES ASSOCIATES
Manpower — Steve Chmura reported that Keyes Associates is now operating with a skeleton
crew. Permanent staff is reduced to about eight to ten employees. Senior Partners remaining in
the main office in Waltham include Walter Keyes and Dave Casali.
Keyes' Non - Payment to Sub - consultants — Per Steve Chmura, the financial gain from the sale of
Keyes' Connecticut Office last Fall was to be used to offset outstanding fees owed to Keyes' sub -
consultants, i.e. TCI, Wallace Floyd, etc.
Bankruptcy Status — Pending. Keyes Associates is investigating buy -out options with Gale
Associates. Mr. Mangiaratti agreed with an MBC decision to suspend payments to Keyes
Associates.
Contract: Town of Mansfield/Keyes Associates - MBC met with Attorney Robert Mangiaratti to
discuss Town's legal recourse and action to break the existing contract with Keyes Associates
relating to the Mansfield School Projects. Keyes' scope of work included architectural services
at Robinson Elementary and Qualters Middle School. Keyes hired Wallace Floyd Design Group
as a sub - consultant to handle construction administration for Mansfield High School
Summary:
Mr. Mangiaratti to provide MBC response to the following:
• Whether or not the Town of Mansfield can make direct payments to Wallace Floyd for
contract work not previously billed to the Town.
• How to terminate existing contract with Keyes Associates due to non - performance.
• Hiring a Successor — Mr. Mangiaratti to determine how to hire successor to Keyes following
State Public Bid Law Requirements.
• School Building Assistance Bureau — Bob Mangiaratti to meet with current Administrator at
SBAB to review situation and confirm reimbursement status. Question was raised whether
Town can use another Architect for the Track/Field Project. Mr. Mangiaratti to verify.
• Ability to recover payments to Keyes appropriated for Sub - consultants (i.e. WFDG, TCI,
etc.), but not received by Sub - consultants.
MBC to provide the following information to Town Counsel:
• Timeline of Keyes non - performance and related documentation.
• Amount of remaining funds owed to Keyes.
• Amount of remaining funds owed to Contractor (Approximately $12,000 for QMS and
$2,500 for MHS).
• Copies of JTC Locker room change orders.
• Copies of Keyes Invoices (QMS and MHS)
• Contact List, including Keyes staff, Keyes' Sub - consultants, SBAB Rep., Contractor, etc.
Window Conflict - MBC opened discussion about pursuing claim against Keyes Associates
Errors and Omissions insurance. Bob Mangiaratti to consult his associate, Sue Jacobs, who
handles bankruptcy issues as to the appropriate timing to file claim. Bob Mangiaratti suggested
MBC generate a letter including all valid claims against Keyes, i.e. window conflict issue.
MANSFIELD HIGH SCHOOL
Track/Field Project — Walter Parker advised the MBC that School Business Manager is working
with SBAB to obtain "written" approval to hire an Architect (other than Keyes Associates) to
oversee MHS Track/Fields Project.
Bleachers — MBC received cost proposal from WFDG to motorize new gym bleachers as
requested by School Dept. Cost to add full power to bleachers, is $24,770.00, cost for portable
power tractor and tug frames is $7,400.00 and portable operator and tug frames is $3,300.00. All
cost estimates are delivered and installed. Due to high cost to install power to bleachers, the
proposal was not approved by MBC. Walter Parker plans to pursue funding with School
Superintendent.
OTHER
Jordan Jackson Elementary
Roof Litigation — MBC Chairman deposition rescheduled to February 2, 2001. Meeting
scheduled with Mansfield Board of Selectman on January 31, 2001 is postponed due to conflict
with Max Volerra's schedule.
INVOICE
Webber Electric Service Inc. — QMS
MOTION to recommend payment to Webber Electric Service in the amount of $714.25.
JL/KG: Passes 3 -0.
CSS Architects — FDMW Facilities
MOTION to recommend payment to CSS Architects (Invoice No. 972 -06) for services
related to Master Plan Concept Design in the amount of $2,750.00. (Paid to date amount is
$22,254.65. Total contract not to exceed $25,000.00.) JLlKG: Passes 3 -0.
Meeting adjourned at 10:30 PM.