HomeMy WebLinkAboutMBC Minutes 4/3/2001ter
TOWN OF MANSFIELD
7 i F, j r. [s Municipal Building Committee
Meeting Minutes of April 3, 2001
i;f,`;;
Membtsrsi•¢sept: Richard Feeley, Chairman, David Young, Clerk, James Liddick,
William Moore and Eleanor McCarter, Secretary
Ken Gay - Extended Excused Absence
Associate Members: Mike Ahern, Special Project Manager
Robert Button, MENU
Attendees: John Savasta, Mike Cronin, CSS Architects
Lincoln Lynch, School Business Manager
Walter Parker, School Business and Grounds Director
Sean Reardon, Rizzo Associates
Meeting commenced at 7:40 PM
MRS TRACK AND FIELDS PROJECT
Engineering Services - Line Lynch introduced Sean Reardon, Site /Civil Engineering Project
Manager representing Rizzo Associates, One Grant St. Framingham, MA 01701. Rizzo
Associates was selected by the School Department (March, 2001) to provide engineering
services relating to the MRS Track/Fields Project based on their proposal price and experience
with synthetic fields.
Bid Process - Line Lynch stated that the Track and Fields Project meets the criteria of a public
work project (over $100K) and would be bid under the guidelines of M.G.L. Chapter 30 — 39M.
Per Mr. Lynch, the School Dept. also plans to use the Designer Selection Process to obtain
Architectural services. Mr. Reardon stated that once bids are submitted, he would evaluate and
select the most qualified bidder. MBC Chairman pointed out that the Track/Fields Project is a
public bid project therefore Ioivest priced qualified bidder" must be selected.
Bid Documents - Rizzo Associates is currently developing Track and Fields plans and
specifications.
Bid Schedule - Mr. Reardon stated plans to advertise Request for Proposals in early May, 2001.
Mr. Reardon advised that two separate bid processes will be utilized (one for MHS Track and
one for Various Fields). Rizzo Associaties has been issued Notice to proceed from School Dept.
Budget/Construction Schedule — Chairman questioned Line Lynch re: status of a completed
Line -by -Line Budget and Construction Schedule for the Track/Fields Project, as previously
requested (during an MBC Meeting held February 20, 2001). Line Lynch stated that he was
working with Rizzo Associates to prepare this information. Rich Feeley asked that a copy be
forwarded to the MBC Office as soon as possible.
In House Services - Mike Ahern stated that he has arranged for DPW to perform a lot of the site
work necessary for the Track/Fields Project to provide some cost savings. MBC noted that
complete Certified Payroll Forms need to be kept on file for any construction services provided
( in -house as well as outside contractors. To reflect an accurate budget, the School Dept. should
incorporate cost of in -house labor used at the Track/Fields Project in the overall project budget.
Site Work - MBC advised Mr. Reardon to provide necessary site work information to Mike
Ahern and coordinate schedule of work to be performed in -house to avoid conflicts with work to
be performed by outside vendors.
Test Pits — Mike Ahern stated that approximately 10 -12 soil test pits were performed. Mr. Ahern
noted that the material found is glacial till and some gravel. Per Mike Ahern no peat was found
on site.
Synthetic Field In -fill - Mr. Reardon commented there are various types of in -fill available for
synthetic fields. Rizzo recommends using an all rubber in -fill. To protect the warranty all
vendors must supervise installation and approve in -fill. Mr. Reardon noted that the "Shot Put"
event could not be held on the artificial field surface without causing damage to the field. David
Young asked Mr. Reardon to confirm that the synthetic field surface is flame retardant.
MHS Track — School Department stated their intention to keep the track in its existing location.
Plan is to increase the number of track lanes from six to eight lanes and modify the pitch to lean
toward to inside of the track. Rizzo to incorporate alternates in bid documents for different
colored rubber track surfaces. Existing pavement will be reclaimed.
Fencing - Plans to include installation of 4 -foot chain link fence (black) around track area.
Scoreboard - Discussion was to include conduit for future installation of a scoreboard.
Due to unavailable funding, scoreboard was not included in current plan.
Goal posts —Due to unavailable funding, goal posts are not included in current plan. Line Lynch
to investigate alternative funding options.
Field Drainage — David Young questioned School Dept. plans to address drainage. Mr. Young
recommended under - drains be installed to take away rain. Discussion was that Conservation
Dept. would need to verify final drainage requirements.
Field Markings - Rizzo presented option to have field lines sewn into synthetic surface. School
logos can also be painted in the center if desired. At this time the School Dept. plans to have
white football game lines sewn into synthetic surface material with yellow soccer game lines to
be painted on later.
QUALTERS MIDDLE SCHOOL
Handrail installation at Cafeteria — Walter Parker reported that the second handrail at cafeteria
ramp required to meet ADA requirements is installed.
Operation and Maintenance Manuals - Elevator passed recent state inspection however, School
Dept. is still waiting for O &M Manuals from Thyssen Elevator.
MANSFIELD HIGH SCHOOL
Locker Room — Sue Michael Brown noted that a walkthrough was done of the locker room area
with TCI, Walter Parker and Sue Michael Brown. Per School Dept. request, existing girls room
is to be changed into team room areas with no walls.
JTC Manpower — Per Walter Parker, no workers were on site this week.
Drinking Fountains — Installation of new drinking fountains unacceptable. WFDG to issue
notice rejecting work.
Tile - Per Walter Parker, the contractor was on site to correct tile. Mr. Parker assisted with
details of work needing to be done.
FDMW FEASIBILITY STUDY
CSS Architects - John Savasta and Mike Cronin presented review of final study.
MBC Members discussed various items and changes to be incorporated in the final report;
• Need to add MBC Member "William Moore" to Project Team list.
• Project Cost -Add notation that cost of project is based upon ....(include date).
• Site Demolition — Report does not reference demo of existing DPW building.
• Generator — Generator was omitted from electrical needs.
• Drainage — Per John Savasta, plan incorporates a lot of drainage needs.
• Lighting - Lighting was omitted from electrical costs.
• Cupolas located on proposed fire station roof will be functional not fashionable. Cupolas
will house carbon monoxide evacuation system.
• Fuel Storage/Dispense — Discussion opened regarding access to fuel storage and dispensing
area as shown on plan. MBC raised concern about sufficient vehicle and parking clearance.
Mike Ahern to follow up with DPW Department users re: best location of fuel tanks. Fuel is
currently done in -house for approx. $100K -150K.
• Telecommunications Tower —David Young commented that a telecommunications tower
was not included in plan as discussed. Rt. 106 Site would require same size as existing tower
(150 FT.). Note to be incorporated in study that cost of project does not include
communications tower.
• Feasibility Study does include cost of computer networking.
• Hose Tower - Hose tower was included in space needs analysis and per Fire Chief should be
included in final study.
• Storm Water Storage conceptual area is shown on site. This will need to be sized
appropriately during design.
• Gas Pump location — Discussion was to locate gas pumps in a central area behind
Fire/MEMA building.
• DPW area needs to be secured by fencing.
• Rich Feeley express concern regarding the low amount carried as contingency. John Savasta
responded that cost figures are accurate at this time.
• Study to include disclaimer that if buildings are built separately versus whole project, cost
will be higher.
• Final Report Changes - MBC Members to review final Feasibility Study draft and submit
written changes to the MBC Office. MBC Secretary will send all final changes to be
included in the printed report to CSS.
Public Forum Presentation — Suggestion was made to have CSS present the final
Feasibility Study Report in a public forum sometime in the near future. MBC to ask Town
Manager for direction to proceed.
OTHER
Litigation Issues - Qualters Middle School
• Window Conflict— Issue is being followed up by bankruptcy attorney Sue Jacobs (Volterra,
Goldberg, Mangiaratti & Jacobs). Sue Jacobs contacted MBC Chairman earlier that day
advising of plans to pursue claim on behalf of the Town against all parties involved (i.e. JTC-
Contractor, Cheviot - Manufacturer and Keyes Associates - Architect).
• Suburban Middlesex Insulation —Mediation scheduled for Friday, April 7, 2001.
Meeting adjourned at 10:40 PM.
Respectfully submitted
Eleanor McCarter, Secretary
David Young, Clerk Date