HomeMy WebLinkAboutMBC Minutes 8/7/2001TOWN OF MANSFIELD
Municipal Building Committee
Workshop Minutes of August 7, 2001
b-, { .
Y�
L1Y J^�
Members Present: Richard Feeley, Chairman, David Young, Clerk, Kenneth(g
Eleanor McCarter, Secretary
James Liddick and William Moore - Excused Absence
Attendees: Lincoln Lynch, School Business Manager
Walter Parker, Building and Grounds Manager
Michael Ahern, Special Projects Manager
Meeting commenced at 7:30 PM.
TRACK AND FIELDS PROJECT
GC Contract — Quest Sports Surfacing was previously determined to be the low bidder for the
MHS Track and Synthetic Field with a bid amount of $499,802.00. Scope of work for high
school track (i.e. grading and overseeing asphalt) is included in the GC bid as an alternate. MBC
questioned Mike Ahern re: status of the signed contract. Mike Ahern responded that a contract
with Quest has not been signed yet. Mr. Ahern stated he would give a copy of the contract to
Town Legal Counsel (Bob Mangiaratti) on Wednesday, August 08, 2001 for final review.
Budget - Line Lynch advised that an up -to -date budget summary would be provided at the next
MBC Meeting. David Young requested the School Department modify budget summary format
to show a more accurate accounting of available funds under contracted services. School Dept.
agreed to adjust the budget to show any monies already committed for contracted services (i.e.
Contractor, Architect, trucking services etc.) under dollars encumbered column.
Project Schedule - Mike Ahern highlighted upcoming work to be performed by Town of
Mansfield:
August 9, 2001 Reclaim track surface.
August 11, 2001 Grading to be performed by Saturday, August 11a.
August 13, 2001 Begin installation of concrete curb around synthetic field area.
August 14, 2001 School Dept. to submit updated financial report to MBC.
August 20, 2001 Bid opening for field lighting.
September 1, 2001 Final grading for track to be completed by Sept. V.
Track Finish — Mike Ahern stated that the specifications for track surface call for a spray- on red
color finish. Based on Mr. Ahern's discussion with the contractor, a more permanent red surface
material is available for an additional $16K. Mr. Ahern and Line Lynch advised that the School
Department plans to pursue a change order to the Quest contract (after it is signed) to install red
color asphalt. If approved, the change order would increase the cost of the total contract to just
under $520,000.00. This amount was presented at Town Meeting (October 17, 2000) in a
preliminary budget put forth by the School Department
Li htin -Mike Ahern reported that the foundations for field lighting were installed by DPW.
l Per Mr. Ahern, installation was inspected and accepted by Charles Hurley of Scoreboard
Enterprises. Bid opening for lights is scheduled for August 20, 2001. David Young questioned
whether a maintenance agreement is included in light bid. Mike Ahern responded that
maintenance was not included. Line Lynch noted the School Dept. is pursuing possible donation
in the future from Northeast Savings Bank to offset cost for lighting or possible press box.
Scoreboard - Mike Ahern reported that the foundation for the scoreboard was installed by DPW.
Per Mr. Ahern, installation was inspected and accepted by Scoreboard Enterprises. Charles
Hurley, President of Scoreboard Enterprises in Mansfield is donating installation services. Line
Lynch noted that the cost to purchase the new scoreboard would be donated by Pepsi. School
Dept. changed type of scoreboard to be installed from a standard lit scoreboard to an LED
digitally -lit scoreboard.
Field Subsurface - Mike Ahern stated that the stone base was installed by DPW and that two
more layers are needed. Per Mr. Ahern, a representative from Quest Sports Surfaces visited site
and inspected installation. Per Mr. Ahern, verbal approval of work was given by Quest. MBC
later advised School Dept. to obtain written confirmation of inspected work approved by Quest.
MBC suggest the letter of approval be in hand prior to DPW installing additional top layers to
protect warranty issues.
Drainage - Mike Ahern advised that the drainage ditch at the rear of school is complete. Per
Mike Ahern, DPW also reconnected a drainage pipe at rear parking lot (previously disconnected
by DPW in error) to the new field drainage system.
Electrical Building —Mike Ahern advised MBC of plans to construct a small building to house
electrical work and requested MBC input regarding color selection of materials. MBC suggested
using red or tan brick to compliment color of school buildings nearby.
EASTSTREET
Drainage - Drainage ditch at East Street is complete.
Loam Pile - DPW has begun screening loam to be used for East Street fields. Per Mike Ahern,
quality of soil is good.
Project Schedule - Mike Ahern advised MBC that no further work was planned for East Street at
this time. School Dept. needs to determine best timeframe to reclaim existing field. Per School
Department, completion of MRS Track and Field remains first priority, East Street fields second.
LOCKER ROOM RENOVATION PROJECT - MHS
Architectural Affidavit — Walter Parker reported that the stamped affidavit for Locker Room
Renovations at MHS has been provided by WFDG. MBC to give original to Building Inspector
on Wednesday (8- 8 -01).
Architect Fees — Walter Parker reported having conversation about additional fees with Sue
Michael Brown earlier that week. Per Mr. Parker, Sue Michael Brown agreed that WFDG and
TCI fees related to the in -house locker room work could be appropriated under the "Locker
Room Construction Phase" of their current contract. MBC to discuss further with WFDG.
HVAC - TCI to review.
Plumbing - Walter Parker advised that the in -house plumber disconnected gang shower.
Discussion opened re: handicap toilet in locker room that needs to be moved to opposite wall due
to code requirement. Issue pending.
Sprinkler —TCI to review.
Existing Weight Room — If the school continued to use area as a weight room, a heating unit
could be re- installed, but would require installation of new ceiling unit ventilator for an
estimated cost of $15K -$18K. Decision was made to change existing weight room to a storage
room at this time. TCI needs to review further.
Flooring - Rubber flooring material is planned to be installed in girl's locker room, aerobic room
and team room. Flooring is expected in two weeks.
Marble shower panels - Marble panels were previously removed by JTC as part of Contract. In-
house staff has not completed re- installation.
Exhaust Fan #19 - Exhaust Fan #19 has been re -wired by in -house electrician as previously
requested.
Lockers - Per Walter Parker, gym lockers in locker rooms are installed.
MANSFIELD HIGH SCHOOL
JTC Unpaid Invoices - Walter Parker presented unpaid bills from Lewicki and Sons for 84 yards
of additional loam requested by J.T. Callahan for high school renovation work. MBC to ask
WFDG to deduct the amount of unpaid bills ($1,239.00) from Contract and include in Change
Order #26.
Fire Alarm Panel — Walter Parker reported additional troubles with fire alarm panel this past
Friday and having trouble getting JRW to respond. Siemens claimed previously to Mr. Parker
that they did not own repairs due to troubles occurring beyond warranty period. School Dept.
incurred recent cost to replace motherboard panel contingent on JRW addressing future problems
should it be necessary. MBC advised Mr. Parker to forward written notice to JTC advising of
previous understanding that JRW would own repairs for continued problems after motherboard
was replaced with copies to JRW, Wallace Floyd and MBC.
Landscaping — MBC previously asked Walter Parker to obtain quotes to provide (2) trees to be
located on island in rear parking lot. Only one quote was received. MBC agreed to move
forward with proposal submitted by Prew Landscaping in the amount of $800.00 to provide and
install two Armstrong maple trees prior to opening of school. David Young asked Walter Parker
to ensure trees are watered sufficiently.
Occupancy Permit Issues - Walter Parker reviewed electrical items noted in Building Inspector's
report that need to be addressed. Mr. Parker advised that the school in -house electrician would
handle as much as possible.
QUALTERS MIDDLE SCHOOL
Unit Ventilators — School continues to experience problems with air conditioning. Rich Feeley
reported having conversation with Michael Callahan earlier this week. Dick Carney is now
claiming that ongoing problems with air conditioning at Administration are due to the unit
ventilator being oversized. Rich Feeley advised JTC that unit is not operating properly by
August 14, 2001, Town will take a deduct amount for the value of this work.
Floor Finish at Gym —Wafter Parker stated that the gym floor at QMS was recently refinished by
school in -house staff. Mr. Parker reported having a great success using a new floor product,
McGee Wood Flooring Treatment.
Meeting adjourned at 9:30 PM.
Respectfully submitted,
Eleanor McCarter, Secretary
David Young!Clerk �-
Date