TOWN OF MANSFIELD
Municipal Building Committee U r [((' j
Meeting Minutes of September 18, 2001
Members Present: Richard Feeley, Chairman, David Young, Clerk, ki neth'bit"y'dih "
Liddick, William Moore and Eleanor McCarter
Attendees: Walter Parker, School Buildings and Grounds Manager
Lincoln Linch, School Business Manager
Michael Ahern, Special Projects Manager
Meeting Commenced at 7:30 PM.
MHS/LOCKER ROOM MODIFICATIONS
Fire Protection — Walter Parker reported the Local Fire Inspector (Lt. Towne), had reviewed and
approved fire protection plans with respect to the changes made in the Locker Room area. This
was based on the original drawings provided by Wallace Floyd Design Group.
Budget — MBC received an up -to -date budget summary of Locker Room modifications
performed in- house. Expenditures total about $22,000.00. Mr. Parker advised that $3,000
remains in the budget and that this amount would be used to offset costs of a new unit ventilator
in the storage room (previously used as weight room).
MANSFIELD HIGH SCHOOL
Fire Alarm System — Walter Parker noted that JRW had been working to make necessary repairs
to the Fire Alarm System. Per Mr. Parker, the alarm system appears to be working properly at
this time.
Electrical As -Built Drawings —Contractor located As -Built Drawings and will send to WFDG
for review /approval. WFDG needs to forward drawings to TCI for review.
Plumbing As -Built Drawings — MBC received three copies of approved Plumbing As -Built
Drawings earlier that day. Two of the three copies were given to Walter Parker at this meeting.
MBC Office retained one copy of the drawings.
Epoxy Floor at Girls's Locker Room — Discussion opened regarding yellowed condition of
newly installed epoxy floor. MBC asked Walter Parker to send letter to JTC requesting the
manufacturer send a representative to the site to investigate further. This is a warranty issue.
Elevator Tool — Walter Parker confirmed that JTC had provided a necessary maintenance tool to
School Department (valued at $5,000.00) as per contract.
Fire Protection/Boiler Room — Discussion re: previous direction given by local Fire Department
that installation of sprinkler heads in mechanical room, storage and one other room located in or
near boiler room would not be required due to type of usage. Upon further review Fire
Department requires sprinklers be installed per contract drawings. WFDG was advised by JTC
that Yankee Sprinkler had scheduled this work to occur last Friday (9- 7 -01). Walter Parker
commented that as of this date, sprinkler work was incomplete. Completion of this work is
necessary to obtain a Final Occupancy Permit.
Exterior Lighting — Walter Parker reported several bulbs are missing from exterior light fixtures.
Mr. Parker believes subcontractor (JRW) did not complete work per contract.
Emergency Generator — School Dept. reported that the existing generator located at MHS is
insufficient to carry added electrical loads. It was noted that replacement of the existing
generator was not included in JTC's current contract. Walter Parker noted that the addition of
emergency lighting throughout the school had contributed to the overload.
• Temporary Generator - School Dept. is renting a temporary generator at this time. Cost of
rental is $2,700.00 per month.
• TCI Reconnuuendation - Based on the existing load, TCI is recommending installation of a
200 KVA generator. MBC questioned whether such a large unit was necessary. A much
smaller (60 KVA) generator was recently purchased for QMS.
• Cost —Per TCI, cost is estimated at $100,000.00 depending on option package, manufacturer
warranty, etc. Rich Feeley noted that an engineering design would be needed for a new
generator. The School Dept. should anticipate an additional cost for design fee. Existing
generator is located within the building. If the generator was replaced, per code, the new
generator would need to be located outside the building. This would also add to total cost.
• Availability — Jim Liddick suggested that locating a new generator could be difficult due to
emergency response actions to the National Disaster on Sept. 11, 2001. Government agencies
could require all generator units be shipped to New York. School needs to pursue ordering a
new unit as soon as possible.
• Funding — MBC to investigate status of possible funds available from JTC contract. Due to
critical need, School Dept. will investigate possible use of funds from Town's free cash
account.
Gym Bleachers — Walter Parker reported students using gym earlier this week attempted to close
gym bleachers without staff assistance. As a result, gym bleachers were jammed and severely out
of line. In order to prevent permanent damage to bleachers, Walter Parker advised School
Superintendent of the issue and requested funds to motorize bleachers. Per Mr. Parker, Mr.
Moretti gave verbal approval to motorize newly installed bleachers. Walter Parker to get quotes.
Line Lynch to follow up with School Superintendent about funding cost from Pepsi Account.
MHS TRACK/FIELDS UPDATE
Project Schedule —Mike Ahern gave MBC a project schedule provided by Quest Sports
Surfacing. Mike Ahern advised that the project schedule is approximately two weeks behind.
Construction Update — Building constructed to house electrical work is complete.
Quest Contract/Bond Issue — Mike Ahern advised that the Town has signed the contract with
Quest Sports Surfacing for the MHS Track and Field Project. School Dept. is waiting for a copy
of the bond. Quest has received the "A" Bond rating previously required by the School Dept.
Mike Ahern to provide a copy of the contract and bond to MBC Office.
Budget — Per Line Lynch, the MHS Track & Field Project is currently within budget. Mr. Lynch
advised that an up -to -date budget would be provided to WC next week. Mr. Lynch noted
approximately $175K remains in budget.
East Street Field - Mike Ahern presented a plan of the East Street field generated by Rizzo
Associates showing maximized usage for this site. Discussion was as follows:
• Baseball Field - MBC commented the School Department's original intention was to relocate
the baseball field removed from MHS during its renovation project. Chairman confirmed that
the baseball field was properly oriented on the plan shown.
• Irrigation - Mr. Ahern noted that irrigation needs to be installed. DPW plans to utilize
existing well at East Street.
• Fencing— Rich Feeley suggested fencing be installed for varsity baseball field.
• Waiving Track - David Young suggested School Dept./DPW install a warning track around
varsity baseball field as a safety precaution.
• Parking Access — Mike Ahern noted that parking would be available across the street at the
high school. Based on plan layout, MBC expressed concern over lack of parking provided in
proximity to field. Suggestion was made to install a footbridge from Jordan school side to
the field. This would create additional parking and access to East Street fields from Jordan
Jackson Elementary School. David Young suggested picnic tables could be placed in this
area as well.
Rizzo Contract —MBC previously requested a copy of the Rizzo Contract for review. Mike
Ahern and Line Lynch did not have copy available for this meeting.
Status: Line Lynch to forward copy to MBC Office. (Contract and amendments)
RizzoChanee Order — Review /Approval
• Change Order #1— Mike Ahern advised the MBC he had given previous approval of
Rizzo /Change Order #1 for an existing condition survey of the East Street Field.
Status: Rich Feeley requested Mike Ahern/Linc Lynch provide a copy to the AMC
Office for the file.
• Change Order #2 — Mike Ahern reviewed Rizzo /Change Order #2 with the MBC and
requested approval. Scope of Work included the following:
Work relating to bid process for an added cost of $3,900.00.
Task #1 - Additional survey and layout.
Task #2 Design Development of East Street Field $2,600.00.
Status: MBC did not approve Change Order #2. Committee members agreed Rizzo
would be entitled to payment for a portion of work presented, but questioned that
work relating to bid process may be owned in contract. Mike Ahern to review
wording in contract agreement.
QUALTERS MIDDLE SCHOOL
Final Occupancy Permit Issues —
• Emergency Lighting in Girls Locker Room — Walter Parker reported that work is complete.
• Strobe lighting - Issue raised re: strobe emergency lighting out of sequence in long corridors.
This needs to be corrected per code. Walter Parker questioned status of previously approved
fire inspection slip.
• Handicap Station in Home Economics — School Department to provide one handicap
accessible station in Home Economics room. This work was not required per contract.
Unit Ventilators — To date issues with inoperable unit ventilators at Administration, Nurse and
Guidance Offices are unresolved. TCI recommends all Johnson Controls freezestats be replaced,
preferably with another manufacturer. These freezestats were installed by Johnson Controls as a
subcontractor to McLaughlin Mechanical. Member Ken Gay continues to monitor any progress
made on this issue.
OTHER
Jordan Jackson Elementary School
Roof Litigation — MBC received a written update from Attorney Max Volterra (dated 9- 10 -01).
To date a Settlement Agreement has not been signed due to a dispute regarding warranty. Town
Manager was made aware ofMBC concerns earlier that day, that installation of roof coating
needs to be performed during summer months. Bill Moore expressed frustration that the
agreement as discussed at the Mediation Meeting (held in Boston June 26, 2001) was not
finalized. Mr. Moore to forward letter to Town Manager.
INVOICES
MATS Inc. — MHS Locker Room Project
MOTION to recommend payment to MATS, Inc. in the amount of $7,602.90 for floor
covering in the Locker Room area. DY /JL Passes 5 -0.
W.B. Mason —MBC Office Supplies
MOTION to recommend payment to W. B. Mason in the amount of $48.48 for
miscellaneous office supplies. DY/WM Passes 5 -0.
Daly Drywall, Inc. — MHS Locker Room Project
MOTION to recommend payment to Daly Drywall, Inc. in the amount of $4,400.00 for
purchase of materials to construct full height wall for Team Rm. #1 and #2.
JUDY Passes 5 -0.
Bruce Bissett Floorine — MHS Locker Room Project
MOTION to recommend payment to Bruce Bissett Flooring in the amount of $1,875.00 to
prep floor and install 1875 Sq. Ft. of tile in Boy's and Girl's Locker Room.
DY/WM Passes 5 -0.
G.J Sales Company – MHS Locker Room Project
MBC received Purchase Order #019297 in the amount of $17,100.00 to furnish and install 60
deluxe collegiate lockers. No action taken. Waiting for invoice.
Hill & Barlow – Jordan Jackson Elementary
No action taken. Attorney has not provided copy of draft Summary Agreement.
Gale Associates – Jordan Jackson Elementary
Invoice No. 0104347 - $2,137.95, Invoice No. 0107329 - $1,784.50, and Invoice No. 0108268 -
$520.00 were submitted with incorrect or without proper back up. No action taken. MBC
Secretary to contact Ed Stewart to follow up.
Wallace Floeses Design Group – Qualters Middle School
MOTION to recommend payment of QMS Invoice #2 to Wallace Floyd Design Group in
the amount of $1,334.23. This invoice includes engineering services provided by TCI in the
amount of $850.00. DYlWM Passes 5 -0.
Wallace Floyd Design Group – Mansfield High School
MOTION to recommend payment of NMS Invoice #4 to Wallace Floyd Design Group in
the amount of $4,875.75 for services provided through June 30, 2001. DY/WM Passes 5 -0.
Wallace Floyd Design Group – Mansfield High School
MOTION to recommend payment of MHS Invoice #5 to Wallace Floyd Design Group in
the amount of $2,250.00 for services provided through July 31, 2001.
JUDY Passes 5 -0.
Wallace Floyd Design Group – Mansfield High School
MOTION to recommend payment of MHS Invoice #6 to Wallace Floyd Design Group in
the amount of $5,086.00 for services provided through August 31, 2001. JUDY Passes 5 -0.
Meeting adjourned at 10:30 PM.