TOWN OF MANSFIELD
Municipal Building Committee
Workshop Meeting Minutes of October 2, 2001
Members Present: Richard Feeley, Chairman, David Young, Clerk, James Liddick,
Kenneth Gay, William Moore and Eleanor McCarter, Secretary
Attendees: Mike Ahern, Special Projects Manager — Town of Mansfield
Line Lynch, School Business Manager
Walter Parker, School Buildings and Grounds Manager
Meeting Commenced at 5 :00 PM.
ALAS TRACK AND FIELDS PROJECT
General Update report was provided by Mike Ahern.
• Subsurface material is installed.
• Installation of curb around inside of track is complete.
• Contractor is scheduled to install base coat pavement of track on Thursday or Friday
this week. Mike Ahern noted installation of the top red track coating would depend
on temperatures. Contractor indicated installation should be delayed if temperature is
below 40 degrees.
• Infield grading needs to be done.
• Installation of new turf is schedule for next week
• Rubberized pellets for track have been delivered.
Quest Change Order #1 - Includes sewing in permanent game lines /numbers (football and
soccer) and school logo and changing track topcoat color from black to red. Mike Ahern
was asked to provide a copy of approved Change Order to MBC for the project file.
Bond Conditions _ Mike Ahern reported that Quest Sports had provided a $10,000 cash
deposit to the Town to show good faith that their bond would be provided by Tuesday,
October 25, 2001 as promised. This was with the understanding that if the bond was
received by Tuesday, the deposit would be refunded. The bond was provided on Friday of
that week. In an effort to obtain a cooperative working relationship with Quest, the
School Dept. and Mr. Ahern agreed to return the deposit. Quest Sports, in return for the
grace period, agreed to donate (1) "Toby" sweeper valued at $3,600.00 and six park
benches valued at $1,200.00 each. MBC agreed with the actions taken.
Lighting delay — Current delay in delivery of field lighting. Lighting was scheduled for
delivery last Sunday. Mike Ahern advised that lie sent a letter to the contractor stating
they would be responsible for cost of crane needed to set lights, if an additional cost for a
crane is incurred due to delay.
Press Box — Superintendent announced that construction of a Press Box would be
donated by Easton Savings Bank and would be located on top of block electrical shed
near the field. Additional steel material needed would be made available by an unnamed
personal donation.
Bleachers — School Department currently investigating possibility of obtaining used
bleachers from Foxboro Stadium for high school field.
East Street — Irrigation system is needed. Mike Ahern commented that additional funds
would be required by Town Meeting vote if the Town chooses to install sprinkler system.
Baseball Field Fencing - Per Town Superintendent and Athletic Director, fencing would
be installed for backstop and dugouts only. Opinion by School Dept., Athletic Director
was that installation of outfield fencing would restrict usage for other sports. Mike Ahern
commented that DPW could move backstop from Plymouth St. to East Street for cost
savings.
MANSFIELD HIGH SCHOOL
Landscaping — MBC previously requested Walter Parker pursue ordering (2) trees to be
installed in rear parking lot island as a safety precaution. Purchase Order was received
for Prew Landscaping in the amount of $900.00 to install two shade trees at this location.
Walter Parker confirmed that price includes a warranty. Waiting for invoice.
Generator — Existing generator at MHS is insufficient to hold new electrical load. Walter
Parker presented quotes to purchase new unit. (Southworth price to supply 20OKW
diesel unit was $35,775. FM Generator quote for 175KW unit was $32.500.) New
generator may need to be located outside due to new building codes. If purchase amount
exceeds $25K, it would need to be handled by public bid process. MBC asked Walter
Parker to request a proposal from TCI to design generator and associated work.
Fire Protection — JTC still working to correct various issues. Retest of Fire Protection
system at MHS is scheduled for October 9, 2001
Stairwell at West Addition — Issue re: sunken floor noted in West Addition where old
stairway was in- filled. WFDG was asked to send structural engineer to investigate.
MBC advised Walter Parker to send written notice to JTC advising of problem. Any
defective workmanship would be included in warranty.
Flooring,/Girl's Locker Room — Previous problem reported of yellowing floor.
Manufacturer visited site to evaluate. Problem appears to be with resin. Issue pending.
Drainage Problem/Girls Room Shower — Walter Parker reported drain not working
properly in new shower. MBC asked Walter Parker to issue written notice to JTC.
Occupancy Permit Issues —
Fire Protection — Need final approval.
MHS LOCKER ROOM PROJECT
Unit Ventilator — School Department agreed to purchase new unit ventilator ($3,900) to
be located in new storage room. This room was previously used as a weight room.
School Dept. /School Committee Budget Priorities – MBC and School Superintendent
discussed future financial appropriations to be made from the Pepsi donation account
budget ($120,000). Superintendent offered that if MBC could cover cost of a new
generator unit with in the school project budget, the School Dept. could absorb cost to
motorize bleachers ($20,000) and delete future purchase of aerobic equipment ($20,000.).
Mr. Moretti noted that due to anticipated increased need for boy's locker room facilities
next year, the existing aerobics room would be converted to a boy's locker room.
Proposed MBC Budget Expenses:
$25,000 In -house locker room modifications /Walter Parker
$38,000 Architectural Fees /Wallace Floyd Design Group
$17,385 Purchase of (61) football lockers /G.J. Sales Corporation
$ 2,000 Structural Design
$82,385 Sub -Total
Plus Generator
Proposed School Dept. Expenses
Aerobic equipment (On Hold) $ 20,000
Cost to motorize bleachers $ 20,000
Purchase of UV for locker room 3,90
Total $126,285
Auditorium Rigging - Superintendent noted that necessary replacement of auditorium
stage rigging (not contract work) would be handled by School Dept.
QUALTER MIDDLE SCHOOL
Occupancy Permit Issues –
• Fire Protection – JTC needs to obtain Final Approval.
Room 105A – Sprinkler too close to wall. Walter Parker noted sprinkler head was
moved. School Dept. covered this cost.
• Ceiling tile missing in some rooms – Replacement of tiles required for final approval.
• Handicap station is Home Economics – Not required per contract. Walter Parker to
handle.
Parking Lot Stripping,– Cars continue to park directly in front of rear gym doors. "No
Parking" stripping is needed. Walter Parker agreed to coordinate this work.
Meeting Adjourned at 9:30 PM.
Respectfully submitted,
Eleanor McCarter, Secretary
David Young, Clerk