Loading...
HomeMy WebLinkAboutMBC Minutes 10/23/2001s`5 �i , r� �E �t L, b-1 L. E f TOWN OF MANSFIELD Municipal Building Committee Meeting Minutes of October 23, 2001 Members Present: Richard Feeley, Chairman, David Young, Clerk, Kenneth Gay, James Liddick, William Moore, and Eleanor McCarter Attendees: Walter Parker, School Building and Grounds Manager Michael Ahern, Special Projects Manager — Town of Mansfield Michael Callahan and Paul Ciaramitaro Meeting commenced at 7:30 PM. MANSFIE LD TRACK AND FIELDS PROJECT General Update: Report given by Mike Ahern. • Project Schedule - Track and Field Project is on schedule at this time. • Up -to -date budget summary for the Track and Fields Project was not provided. • Inspection Report - Quest Sports Surfacing performed final inspection of subsurface material installed by Owner per contract. Copy of written approval was provided to MBC for file. • Track Topcoat — Due to sporadic cool temperatures (under 40 degrees), Contractor recommended installation of red topcoat of track pavement be postponed until Spring, 2002. MBC concurred with this recommendation. • Field Turf Installation — Per Mr. Ahern, installation of turf surface is approximately one third complete. Timeframe estimated to complete Track and Field work is three weeks. • Games Lines/Numbers — Once turf installation is complete, Contractor will cut in permanent game lines and numbers for football and soccer. • Field Lighting - Electrical lines for field lighting are scheduled to be installed on Wednesday October 24, 2001. Mike Ahern noted that due to lighting materials sitting on track at this time, extra security would be on duty until 1:00 A.M. this evening. • Security — A local resident raised concern earlier that day about security needed on site to prevent vandalism to the field surface. A specific security plan is not in place at this time. Rich Feeley suggested the Town could install a cable camera security system tied into the Police station. A similar system is currently used at the Mansfield train station. East Street Field: Field update was not provided. MHS LOCKER ROOM RENOVATION PROJECT Budget - Walter Parker submitted up to date budget summary. Architectural Affidavit — MEP Affidavits are on file. WFDG needs to provide Final Architectural Affidavit for the Locker Room, Unit Ventilator— Walter Parker asked about the possibility of including cost a new unit ventilator need for Boy's Locker Room within school project budget. Issue pending. MANSFIELD HIGH SCHOOL Generator — Existing generator at the high school appears to be insufficient to handle additional electrical load from new additions. TCI submitted proposal with related scope of work to design new generator in the amount of $9,000.00. MBC opinion is that TCI did not provide a proper design in their original documents due to loads miscalculated by their firm. MBC Chairman had conversation with Moe Goyal (TCI) earlier that day. Mr. Goyal agreed to investigate issue further. Mr. Goyal indicated to Rich Feeley that if it was determined that TCI was at fault for miscalculating needs, their office would agree to design new generator at no additional cost. Response is expected in a few days. Exterior Lighting — Per code exterior lighting needs to be located in rear of building at doorway and ramp outside Little Hornet's nest in rear of building. This work was not required per contract. Per Walter Parker, School dept. installed exterior lighting earlier that day. School Projects Close -out — MBC generated a document earlier this week (dated 10- 22 -01) listing numerous JTC Close -out issues for the MHS and QMS Projects. This list was FAXED and mailed to Michael Callahan prior to tonight's meeting. JTC was advised in a cover letter that all outstanding items must be complete to close out school projects. MBC reviewed completion status of each closeout item with Michael Callahan and Paul Ciaramitaro. Status is as follows: MANSFIELD HIGH SCHOOL 1. Architeetw -crl Record Documents — Value $12,000. Michael Callahan advised MBC Architectural record documents were forwarded to WFDG for review. Status: MBC needs to verify approval status with Sue Michael Brown. 2. Architecttn•al EaistingBrtilding- $5,000. JTC clai ins work is complete. Status: MBC to ask WFDG to verify status. 3. PlmnbhW1F6•e Protection: Chlorination of Pipe - Value $2,000. JTC had no further update regarding this issue. Status: JTC needs to verify actual date work was performed as previously requested by MBC. Michael Callahan offered to redo chlorination of pipes if necessary. Rich Feeley noted this work could only be done when school is not in session. 4. Phanbitig /Fire Protection: Record Drmph — Value $5,000. Per Michael Callahan, final approval was received from Fire Department. Status: WFDG needs to forward copy to MBC. 5. Sprinkler heads installed at Boiler Room. Ceiling file needs to be replaced Status: Michael Callahan agreed to furnish new ceiling tiles at no additional cost. 6. Fire Inspection — Status: Complete. JTC provided copy of final approval to MBC. 7. Final Release Wiens —Status: JTC needs to provide release from McLaughlin Mechanical and Montle Plumbing. 8. HV -1 has no filter tt•ay and uo filtei s — Value $750.00. Status: Work is complete. 9. Credit dire to 'I'oinn for additional loans needed to complete lcrndsccl I?g QMS & MHS. Loam supplied by Lewicki & Sons Excavating - $2,891.00. (Back charge for this amount is reflected in pending JTC Change Order #26) Status: Michael Callahan agreed to back - charge amount of $2,891.00 but refused to sign Change Order #26 at this time. 10. Credit Change Order #26 for incwnplete Punch List work valued at $30.937. Change Order is not yet signed by JTC. Status: No action taken. MBC is holding punch list value of $27,500.00 pending WFDG verification of punch list work complete. 11. Credit due to Town for Seismic Clip work not required. Status: Amount of credit value due to Town remains in dispute. MBC determined original credit value to be ($46,000.00) based Upon Structural Engineer's letter. MBC previously offered to reduce value to accept $23,250.00. This amount is reflected in JTC Change Order #24 not signed yet by JTC. Michael Callahan disputes value of credit proposed noting value of work is worth only $10,000.00. When questioned by David Young, Michael Callahan was unable to substantiate how the $10K cost value was calculated . David Young recommended the previous settlement offer of ($23,250.) be withdrawn and suggested MBC pursue the original credit value ($46,000.) due to Town for work not performed. 12. Yellowing Floor at Girls Locker Room — Status: Eastern Flooring agreed to correct the yellowed epoxy floor finish under warranty. Problem with drain clean out in this area needs to be addressed prior to correcting floor finish. 13. Drain problem at Girls Locker Room — Incorrect drain clean out was covered over when contractor installed new epoxy floor. End shower drain is plugged at this location. Status: JTC needs to cut floor to expose drain clean out and cap drain properly. This work needs to occur prior to yellowed floor issue in locker room is corrected. Paul Ciaramitaro agreed to work with Walter Parker to coordinate this work. 14. Electrical Issues (JRW) — Home Economics and Front Foyer are not on emergency generator. Issue remains open. JRW subcontractor needs to complete work. 15. Fir.vt Floor Door -hold at Stairwell #6. Magnetic door -hold on one side does not old door open properly. Door hold needs to be relocated to wall. Per Fire Dept. this work must be complete to obtain final fire inspection approval. Status: This work is complete. 16. S. AdditionI2 "`u Floor at elevator —Large area of floor is sunken. Outline of in- filled stairwell is visible. New floor tile is cracking. School contacting Structural Engineer to review. QUAL 1'ERS MIDDLE SCHOOL 1. Fire Alarm Inspection — JTC needs to provide confirmation of final approval by Fire Department to Building Inspector or schedule a complete final inspection at the middle school. Further discussion was raised re: Fire Dept. directive that horn/strobe devices must be synchronized to meet ADA requirements. Status: MBC to send a letter to Bob Wedge (TCI) asking him to evaluate status of strobe lighting. Contractor needs direction from TCI as to what if anything needs to be modified to meet ADA requirements. 2. Final Release of Liens — Status: JTC needs to provide. 3. Inoperable Windows — Claim is currently outstanding to correct windows installed in conflict with walls and /or partitions. Town Legal Counsel, Susan Jacobs forwarded letter to MBC (dated October 24, 2001) advising no further payment be made to JTC from this contract until issue is resolved. Status: MBC needs to determine value of fix based on proposals from WFDG and /or Gale Associates to remove and /or replace to obtain operable window units per contract. 4. Unit Ventilators— Status: Work is incomplete. Ken Gay noted that based on the balancing report provided by McLaughlin Mechanical (dated 8- 30 -01) units are not working according to design. Johnson Controls was scheduled to replace freezestat to #13. Per Walter Parker Johnson Controls was on site October 17, 2001 and believes freezestat was replaced. Walter Parker and Ken Gay raised concern that units could have freezing problems again if fresh air temperature is brought in at 60 degrees. MBC reiterated that no payment would be authorized for this work until verification is received that all units are operational and work properly. Future Architectural Fees - The Architectural contract between the Town of Mansfield and Wallace Floyd Design Group expired on September 21, 2001. David Burson indicated to IVIBC Chairman that additional charges would be billed for future work relating to the Mansfield School Projects that are provided beyond this date. Rich Feeley advised Michael Callahan that due to JTC's significant delay regarding completion of contract work and submission of final close out documentation (as stated in a letter to JTC from the MBC dated 10- 19 -01) JTC would be expected to pay for any future costs incurred. WFDG Contract — Most recent Wallace Floyd invoice indicates ten percent of Extended Base Contract is incomplete (Value of $5,000. remains). NBC needs to determine final scope of work and discuss further with Wallace Floyd. Suggestions made included the following. • Final Architectural Affidavits /Locker Rooms — (Walter Parker to request from Dick Carney) • Review As -Built Drawings and O &M Manuals. (If not complete, WFDG would review upon resubmission.) • Review final payment for Qualters Middle School -WFDG to review and approve value of work provided. • Review (2) payment requisitions for Mansfield High School • One site visit JTC /Application for Payment #26 — Review /Approval MBC agreed to consider approval recommendation of JTC Application for Payment #26 provided Michael Callahan agreed to sign and include JTC /Change Order #26. MBC suggested the Requisition be revised to reflect the following: Punch List reduced by $17,500.00 $12,000.00 Architectural Record Documents $ 5,000.00 Architectural Existing Building $ 500.00 Outstanding Electrical Work QRW) $17,500.00 Sub Total ($46,000) Credit for Seismic work no longer required. $199,416.44 Total Payment to JTC Status: JTC refused to sign Change Order 926, therefore no action was taken on Application for Payment #26 as presented which included unapproved signed change orders on it. INVOICES Wallace Floyd Design Group — QMS MOTION to recommend payment to WFDG in the amount of $1,276.33 to]- services performed based on Time and Materials. $1,140.00 of this cost related to problems with unit ventilator. MBC to hold this value as deduct to JTC Contract. DYIJL: Passes 5 -0. Wallace Floyd Design Group — MHS Extended Base Contract No Action Taken. WFDG needs to provide back tip for reimbursable services in the amount of $723.30 for Personnel Services provided by David Burson and Sue Michael Brown. Webber Electric — MHS MOTION to recommend payment to Webber Electric in the amount of $3,032.00 for electrical services necessary to add exterior lighting at MHS and QMS to generator. DL /JL: Passes 5 -0. Meeting adjourned at 10:30 PM. Respectfully submitted, Eleanor McCarter, Secretary David Young, Clerk Date ll- zo