HomeMy WebLinkAboutMBC Minutes 11/6/2001TOWN OF MANSFIELD
Municipal Building Committee
Meeting Minutes of November 6, 2001
Members Present: Richard Feeley, Chairman, David Young, Clerk, Kenneth Gay, James
Liddick (8:00 PM), William Moore, and Eleanor McCarter, Secretary
Meeting commenced at 7:45 PM.
QUALTERS MIDDLE SCHOOL
Window Conflict — Town has initiated a legal claim for cost to correct 272 windows in conflict
with walls and /or partitions. MBC was asked by Town Counsel (Sue Jacobs) to establish cost
value to correct windows. MBC will issue letters to Wallace Floyd and Gale Associates inviting
both firms to submit cost proposals, to assist the Town of Mansfield in resolving window conflict
issues at Qualters Middle School. Firms may visit site to evaluate conditions and make copies of
relevant MBC documents needed to prepare a proposal.
Remaining Scope of Work:
Contractor /J. T. Callahan &Sons:
1. Fire Protection — JTC needs to provide copy of final approval signed by Fire Department
to Building Inspector in order to receive Final Certificate of Occupancy.
2. Submit final payment requisition and Release of Liens.
ArchitectlWallace Floyd Design Group:
1. MBC may need Architect (WFDG) to prepare and review final Requisition for Payment.
2. Process Change Order #322 —Fire protection in cafeteria done on Time and Materials
basis.
School Dept ✓6Yalter Parker, Building & Grounds Manager:
1. Handicap station is needed at Home Economics. School Department to install.
2. Sheet rock ceiling is missing in Boy's Locker room. Ceiling needs to be installed.
3. Strobe lighting appears to be out of sequence. MBC to forward letter to Bob Wedge
(TCI) to review and advise.
MANSFIELD HIGH SCHOOL
Fire Protection —Paul Ciaramitaro gave MBC a copy of an e-mail (dated 10- 23 -01) sent to the
local Building Inspector from Lt. Towne at a prior MBC meeting. The e -mail noted the Fire
Department had completed their final inspection of the high school and was satisfied with
building conditions. Lt. Towne stated he was unable to locate the building permit for MHS to
sign off for approval.
Generator — Rich Feeley spoke with Moe Goyle at Thompson Consulting on October 30, 2001 to
discuss waiving fee proposed ($9,000) to provide design for new generator. MBC suggested that
if electrical loads were calculated properly, TCI would have been required to provide a generator
design under their contract. Mr. Goyle agreed to investigate issue further. Mr. Goyle stated, that
if TCI miscalculated load in original documents, they will provide new generator design at no
additional cost to the Town. TCI is proceeding with design work and had indicated to Rich
Feeley that a working design would be ready this week. Rich Feeley to follow up.
Architectural Contract/WFDG — Existing contract between the Town of Mansfield and Wallace
Floyd ended September 21, 201. David Burson agreed to continue contract for professional
services relating to the Mansfield School Projects (QMS /MHS) billed on time and material basis.
Remaining Scope of Work - MHS
Architect/WFDG: A�MC to issue letter to WFDG advising of remaining Scope of Architectural
Services needed to close out the high school project. Scope includes the following:
1. Review and approve Operation & Maintenance Manuals as submitted by Contractor.
2. Review and approve Architectural Record Drawings as submitted by Contractor.
3. Review and approve Electrical Drawings. (MBC to send letter to confirm WFDG
forwarded drawings to TCI for review.)
4. Prepare final requisition for payment for MHS.
5. Provide inspection and final Architectural Affidavit for locker room.
6. Prepare final requisition for QMS.
School Dept. /Walter Parker:
1. Coordination issue at Girl's Locker Room;
• Yellowed Floor in Girls Locker Room —Subcontractor agreed to repair under
warranty.
• Drain Problem —Contractor needs to cut floor to expose drain clean out prior to
corrected floor installation.
2. New Generator (MIIS)
3. Electrical issue re: home economics and front foyer needs to be on emergency generator.
4. Request final inspection for Architectural affidavit of Locker Rooms.
JTC Outstandinglssues:
1. Fire Protection — Approval is complete. JTC needs to provide to record drawings to
MBC.
2. WS Outstanding Change Orders:
C.O. #24 - Seismic clip credit.
C.O. #26 — Punch List and New door 131E.
3. QMS Outstanding Change Orders:
C.O. #322 — Fire Protection at Cafeteria performed on T &M.
Stairway #6 Infill — Concern raised previously re: possible structural issue related to infill of
Stairway 46 (2nd floor). Tile is cracked outlining previous stairway and floor is depressed in this
area. MBC Secretary has left several detailed messages as well as written requests to Structural
Engineer to review and evaluate. Davey Associates (former subcontractor of Keyes Associates)
refused to review the stairway issue without a new Contract Agreement. Engineer needs to
address safety concern ASAP. Determination needs to be made whether condition is a structural
problem. Discussion was that if the stairway problem was due to Contractor error JTC would be
back - charged for Engineer's services. If problem occurred due to lack of detail provided on
drawings done by Davey Associates, Towns will not pay additional cost for Engineer's services
necessary to correct issue. Rich Feeley to follow up with Bruce Davey.
Project Close out — Due to the number of discrepancies that were corrected by MBC in
previously submitted requisitions, David Young suggested the MBC verify math is accurate prior
to WFDG preparing final payment requisition for signature.
INVOICES
W.B. MASON —MBC Supplies
MOTION to recommend payment to W.B. Mason in the amount of $61.49 for
miscellaneous office supplies. DY /JL : Passes 5 -0.
Infinity Flooring LLC — MBC Locker Room Project
MOTION to recommend payment to Infinity Flooring LLC in the amount of $520.00 to
seam bind floor padding in Girl's Locker Room. DY /JL: Passes 5 -0.
Gale Associates — Jordan Jackson Elementary
MOTION to recommend payment to Gale Associates in the amount of $1,740.00 for
services relating to roof failure mediation settlement. DY /JL: Passes 5 -0.
MBC MINUTES — Review /Approval
MBC minutes of March 16, 1999
MBC minutes of November 9, 1999
MBC minutes of November 16, 1999
MBC minutes of November 23, 1999
MBC minutes of November 30, 1999
Meeting adjourned at 9:15 PM.
Respectfully submitted,
Eleanor McCarter, Secretary
David Young, Clerk
MOTION to approve. JL/KG: Passes 3 -0 -2.
D. Young and W. Moore absent.
MOTION to approve. DY /WM: Passes 4 -0 -1.
J. Liddick .
MOTION to approve. DY/WM: Passes 5 -0.
MOTION to approve DY/WM: Passes 5 -0.
MOTION to approve. DY/WM: Passes 5 -0.