MANSFIELD HIGH SCHOOL
Infill Stairway #6 — Previous issue raised regarding structural integrity of Stairway #6 infill
located at the South Addition. Walter Parker reported that JTC was on site recently and did some
welding in this area to provide additional support. Structural Engineer needs to review and
verify repair is acceptable or issue detail to correct as needed. To date Bruce Davey (Davey
Associates) has refused to review this issue until his firm receives confirmation of additional
compensation to be paid for their service. MBC members agreed to send a letter to Davey
Associates authorizing payment of up to $500.00 for engineering services necessary. Per Walter
Parker, extra floor tile is in stock. Contractor is scheduled to repair cracked floor tiles during
December school vacation.
Drain issue at Girl's Locker Room — Inadequate As -Built Drawings contributed to problems in
locating the drain cleanout in this area. Walter Parker coordinated exposing drain clean out to
find New England Flooring had poured excess floor material in shower drain which caused a
blockage. Blocked drain problem is resolved. New England floor agreed to be responsible for
cost to replace floor top coat. MBC agreed that JTC should cover cost of time incurred by
School Building and Grounds Manager to resolve this issue.
Electrical Issues — Walter Parker noted concern regarding several electrical issues that remain
incomplete by the subcontractor (JRW). Rich Feeley referred to list provided by Building
Inspector that noted only a limited amount of work remained. This list was issued to JTC as part
of the Final Inspection Report. As of July 31, 2001, Punch List value for electrical was $750.00.
MBC advised Walter Parker to forward letter to JTC directing work be completed by Friday,
December 7, 2001.
Doors/Hardware Girls Locker Room — Walter Parker reported having problems with door locks.
MBC advised School Dept. hire someone to fix locks vs. waiting for contractor.
Door 13 111 — Walter Parker reported the right side door in Girl's team locker room is missing.
JTC needs to provide. Door 131E also located in Girl's Team Locker Room, was not provided.
This is included in Change Order #26 in the amount.of $2,437.00 not yet approved. MBC asked
Walter Parker to notify JTC to install this week.
COP #24 /Seismic Credit — Value of credit due to the Town remains in dispute.
( Pump Station — Walter Parker reported outstanding issue regarding poor ventilation in pump
station that needs to be corrected. Walter Parker to coordinate necessary work to correct issue.
Generator — School Dept. continues to rent temporary unit. MBC is working with School Dept.
to replace existing generator from School Project Account. TCI provided bid documents earlier
this week for MBC review. Scope of work includes purchase of one new Generator, wiring,
transfer switch and new panel. Discussion was as follows:
Coordination - David Young noted several items show no coordination between trades
within the contract documents. TCI should note coordination required in contract
documents.
Fuel - MBC questioned TCI's choice to use diesel fuel. Existing genset is gas. MBC
recommends use of natural gas, not diesel,
Location — David Young noted that the new generator location recommended by TCI
near auditorium entrance is directly under an outside air vent (vent location was not
shown on original drawings). MBC recommends new generator be located near loading
dock where temporary genset is now located. Existing generator located inside
building is to remain in place at this time
• Alternates — MBC recommends that existing Alternate 1 be only option.
• Transfer Switch - Needs new transfer switch. 1 SOM
• Exterior Site Work —MBC states exterior site work needs to be shown, including
underground oil tank.
• Enclosure - Drywall enclosure needs to be done ivith proper fire rating. Four bollards
should be shown.
• Filed Sub- Bidders —Question was raised as to why six Filed Sub - bidders are listed on
documents. MBC suggested documents are boiler plate and six "Filed" sub- bidders
would not be needed. Electrical trade is listed to be General Contractor.
• Bid Documents — TCI to include Copies of Plans and Specifications available for pick
up at MBC Office at no cost or sent to requestor by mail for a fee of $25.00.
• Proposed Bid Schedule
Documents to be made available by December 18, 2001
Pre -Bid Walk through to be held Thursday, December 27, 2001
Filed Sub Bids due either Tuesday, January, 15th or 22, 2002
MBC to make 12 copies of bid documents.
• MBC needs to check with Town Counsel regarding wording about waiving fees for
various permits. MBC to summarize comments and forward letter to TCI this week.
LOCKER ROOM PROJECT
Final Affidavit — Walter Parker needs final affidavit from WFDG and TCI to obtain Final
Occupancy.
Unit Ventilator — Walter Parker advised MBC a new unit ventilator was installed in the Locker
Room Storage Room. School Dept. had previously advised MBC that a UV was needed due to
insufficient heat in this space. Cost of unit ventilator was $3,900.00. MBC agreed to cover cost
under School Project account.
Weight Room —Walter Parker advised MBC that the current Storage Room in the Locker Room
may be used as weight room in the future. MBC noted this would be a separate project from
Locker room renovations and a separate building permit would be needed to convert storage
room to weight room.
WFDG/Remaining Scope of Work - At this time, MBC agreed Wallace Floyd would not need to
attend any future MBC meetings regarding the school projects. The following scope of work
needs to be completed by WFDG:
High School.
1. Architectural Record Drawings — WFDG has in possession. Documents need to be
reviewed, approved and returned to Owner.
2. O &M Manuals — JTC needs to revise and resubmit to WFDG for approval.
3. Delay Claim Schedule — WFDG received schedule from JTC on November 30, 2001.
Jim Liddick suggested MBC get copy of this schedule and review it prior to WFDG
sending any response to the General Contractor.
4. WFDG and TCI need to provide Final Affidavit for Locker room area.
5. Punch List — Unless JTC hires WFDG to re- inspect additional work completed, the value
of the punch list will remain the same as submitted in Revised Change Order Proposal
#26 in the amount of ($36,911.00).
Quniters Middle School.
1. COP #322 — WFDG needs to process Change Order #322 for Fire Protection in Cafeteria
performed on T &M.
2. Final Requisition — Based on advice from Town's Legal Counsel (Sue Jacobs), no further
payment should be made to JTC until the pending litigation regarding the window
conflict at QMS is resolved. WFDG needs to review final requisition only so MBC
would have accurate records for future payment. Requisition should not be signed by
Architect at this time.
QUALTERS MIDDLE SCHOOL
Window Conflict — MBC previously sent RFP's to Gale Associate and Wallace Floyd to provide
a cost estimate to remove and replace newly installed windows in conflict with walls and /or
partitions. Gale Associates has expressed interest. Wallace Floyd has not responded to date.
David Young asked if Mr. Stewart agreed to be an expert witness for the Town. This question
was not asked in original request for cost proposal. David Young suggested Ed Stewart (Gale
Assoc.) contact Sue Jacobs to determine scope of work needed.
Unit Ventilators #13, #14 #15 #16 — Town continues to hold money for this work until units are
tested Spring, 2002 and accepted by the Town.
Handicap Station at Home Economics — No change. MBC asked Walter Parker to hire someone
to do this work. This needs to be complete to obtain Final Occupancy.
MHS TRACK AND FIELD
Project Budget - Walter Parker reported that the School Business Manager would provide an up-
to -date budget summary to MBC next week.
Track - David Young noted track is uneven on opposite right side. Contractor may have run out
of asphalt at that point or possibly truck traffic delivering temporary bleachers. Mr. Young
suggested Walter Parker review issue.
Synthetic Field - Approximately 100 lbs. of additional rubber pellets remain on site and will be
added to the synthetic field in Spring, 2002. Initial installation of rubber needs compacting
before it would be able to accommodate remaining pellets.
LITIGATION
Debrino Caulking — Copy of all related correspondence was forwarded to Bob Mangiaratti. Per
directive from Town Manager and Town Counsel, MBC Office contacted Town Treasurer and
requested an escrow account be established until this claim is settled.
Erin Kelly Claim — Legal response has been filed by Town's Legal Counsel.
Meeting adjourned at 10:15 PM.