JORDAN JACKSON ELEMENTARY SCHOOL - ROOF REPAIR PROJECT
Progress Update —The MBC received copies of (3) Field Reports prepared by Gale Assoc. dated
week ending July 7, July 14, and July 21, 2002. MBC Members observed minimal progress
made on roof during the months of June and July. Walter Parker, School Building & Grounds
Manager noted earlier that day, that the Contractor seemed to be working slow, however they
appear to be doing a thorough job at this time. MBC and School Dept. expressed concern that
the Contractor may not finish repairs by the start of school in September 2002. MBC to request
Gale Associates obtain an updated Project Schedule from the Contractor.
QUALTERS MIDDLE SCHOOL
Unit Ventilators — Ongoing issue regarding ventilator units located at administration that have
not worked properly since installation. Walter Parker forwarded a proposal from G &P Service
Contractors, Inc. for MBC review /approval. The proposal in the amount of $2,550.00 was to
furnish and install high and low pressure regulators for (4) Tempstar ceiling mounted condensing
units ( #13, #14, #15 & #16). Dick Carney, TCI recommended this fix to permanently correct the r
current problem of unit freeze -ups. AMC accepted the proposal and advised School Dept. to
proceed with work. MBC to back - charge JTC for that amount.
Handicap Station/Home Economics - School Dept. is still waiting for delivery of (1) all -in -one
handicap kitchen station. Installation of this item is required to meet ADA code requirements
and to obtain a Final Occupancy Permit. Walter Parker to coordinate installation.
Window Liti ation
• .Cost Estimate/Gale Assoc. - Town entered into an agreement with Gale Associates to
prepare a cost estimate to correct 272 inoperable windows at QMS. (7/30/02) MBC received
(2) copies of a final report prepared by Gale Associates (dated July 29, 2002). The report
includes a summary of Gale's investigation efforts and five different cost options to correct
the windows.
• Depositions — Sue Jacobs held depositions of former Keyes Associate employees, Ron
Ashton, on
t Bob Vogel and Dan Freeman earlier that day. Based upon the Architects responses,
Sue Jacobs was confident she had enough information to prove tort liability. Town Counsel
plans to name J.T. Callahan & Sons to this claim before the statute runs out.
{
( MANSFIELD HIGH SCHOOL
Project Close -out - Michael Callahan contacted the MBC Office to request status of final
payment to JTC. MBC Office advised Mr. Callahan earlier that day of a previous request from
the Committee that JTC submit revised Application for Payment #27 along with (3) signed
change orders (as stated in a letter previously sent to JTC dated May 30, 2002). ', Members
agreed that no further payment would be made to JTC until paperwork is submitted in proper
order.
Direct Payment Claim/General Mechanical- No change. Town is still holding $51,772.12 in
escrow for this demand.
GENERATOR REPLACEMENT PROJECT (MHS)
(7/30/02) Spoke with Gerry Caron, Freedom Electric regarding status of remaining work.
• Wiring - Electrician completed wiring on Friday, July 26, 2002.
• Bollard - Contractor secured (1) remaining front bollard in place. Ken Gay reported as of
that date, Contractor had not filled the last bollard with concrete. MBC to follow up.
• Start up Test - Genset was start tested Monday, July 29, 2002. Walter Parker and Electrical
Inspector were among those present during testing. Per Walter Parker and Gerry Caron,
everything tested fine.
• Punch List - Per conversation with Walter Parker (7/30/02), one (1) inside light fixture base
is cracked which the Contractor was made aware of There are no other items outstanding.
(7130/02) Gerry Caron asked the MBC Office to forward a written punch list of all
r outstanding issues and Freedom would address them prior to submitting final requisition.
l • Close -out Documents - Received call from Walter Parker asking about final close out
documents from Contractor. (7/30/02) Called Freedom Electric. Gerry Caron advised that
close -out documents would be mailed to the MBC Office later this week and would include
test reports, original submittals, and fire alarm information. Freedom expects to obtain the
Generator O &M Manual from "Superior" next week. Mr. Caron noted that optional service
contract information would also be provided the manufacturer.
• men Requisition for Pa 3
Payment 7/ 0/02 PY
MBC received a FAXED co of Freedom Electrical
(
Application for Payment No.3 and No. 4 for MBC review /approval.
• Grading —Ken Gay suggested grading options near the generator be explored to prevent
erosion at the base of the generator.
MOTION to recommend payment to Freedom Electrical Co. for Application for Payment
No. 3 in the amount of $48,299.90 and Application for Payment No. 4 in the amount of
$1,967.10. Chairman to verify and sign original copies upon receipt. Both requisitions were for
work related to installation of a new generator unit at Mansfield High School.
KG/WM: Passes 3 -0.
WATER TREATMENT PLANT FACILITY PROJECT
Advertisinn - The bid proposal due date was incorrect in the advertisement that appeared in the
Sun Chronicle. The WC Office sent a revised notice to Sun Chronicle earlier that week
changing the deadline date to submit proposals as August 16, 2002. Ad will appear in the
Central Register and again Sun Chronicle Wednesday, July 31, 2002.
RFQ Response - To date three firms have requested RFQ packets. Kurt Gaffney asked the NBC
Office to forward a packet to Woodard & Curran.
Project Schedule:
• Site Walk - through -August 8, 2002.
• Deadline to submit Engineering Design Proposals - August 16, 2002 at 10:00 AM.
• RFQ Evaluation and Short List -August 27, 2002 (Full Committee to review at Tuesday
evening MBC Meeting.)
FISHER- RICHARDSON HOUSE PROJECT
Construction Bid Documents — Architect delivered (15) copies of contract documents to MBC
Tuesday afternoon. Distribution list for copies include; the MBC, James Bright Architect, Tom
Paske- Preservationist, Timelines, Inc., MASS -HC, MANSF -HC, Mansfield Town Clerk. The
remaining copies of plans and specs would be available for bidders with a $25 refundable check
deposit and optional $25 mailing fee.
Construction Sign Ken Gay noted that Mansfield Bank should be recognized for their donation
to the project. Rich Feeley suggested their name be added to the construction sign. Secretary to
notify Architect.
Advertising - The "Invitation to Bid" was scheduled to appear in the Central Register and The
Sun Chronicle, Wednesday, July 31, 2002.
Project Schedule:
Site Walk- through - August 7, 2002.
Sub -Bid Opening (Roofing) - August 14, 2002 at Noon.
General Bid Opening - August 20, 2002 at Noon.
Archaeology - Contract st ill needs to be signed. Town Manager and Timelines President t were
both on vacation until August 5, 2002,
INVOICES
Allegra Print & Imaging Jordan Jackson Elementary/Roof Repair Project
MOTION to recommend payment to Allegra Print & Imaging in the amount of $71.40 for
(4) copies of roof plans. KG/WM: Passes 3 -0.
Meeting adjourned at 8:30 PM.
Respectfully submitted,
I
Eleanor McCarter, Administrative Secretary