HomeMy WebLinkAboutMBC Minutes 8/13/2002i TOWN OF MANSFIELD
uMunicipal Building Committee
! _ i Meeting Minutes of August 13, 2002
Members Present: kichad Feeley, Chairman, David Young, Clerk, Kenneth Gay, James
Liddick, William Moore (8:05PM) and Eleanor McCarter, Secretary
Meeting Commenced at 7:30 PM.
MANSFIELD HIGH SCHOOL
Project Close -out MBC received a letter from John T. Callahan (dated 8/7/02) summarizing
JTC's position on various closeout issues. Committee members reviewed and verified accuracy
of the documentation submitted by JTC (Application for Payment No. 26 and Change Orders
Number 24 and No. 26).
JTC /Change Order Number 24 — Review /Approval
MOTION to approve Change Order Number 24 re: Credit deduct in the amount of
($15,000.00) for seismic clips no longer required. DY /JL: Passes 5 -0.
JTC /Change Order Number 26 - Review /Approval
MOTION to approve Change Order Number 26 re: Credit deduct for outstanding Punch
List work ($36,911.00) and New Door 131E for the amount of $2,437.00. Total Credit
amount due to Town is ($34,474.00). JUDY: Passes 5 -0.
JTC /Change Order Number 27 - Review /Approval
MOTION to approve Change Order Number 27 re: Credit deduct in the amount of
($2,822.93.) for costs incurred by the Town of Mansfield for Architectural Services
provided by Wallace Floyd Design Group beyond their contract end date. Extended
architectural services were required due to J.T. Callahan's delay in submitting close -out
documents for review and incomplete general contract work. DY /JL: Passes 5 -0.
JTC /Application for Payment #26 - Review /Approval
MOTION to recommend payment to J.T. Callahan for a reduced amount of $151,231.85.
DY /JL: Passes 5 -0.
Project Closeout Issues — MBC discussed final outstanding issues and monies remaining in
contract:
• Direct Payment Claim General Mechanical/$37,262.12 must remain in an escrow until
this claim is withdrawn by the sub - contractor.
• Electrical - $15K currently being withheld due to JRW contract work incomplete.
• HVAC - $10K currently being withheld due to General Mechanical contract work
incomplete.
MBC Chairman to call the Contractor to discuss JRW's plan of action to complete work.
JORDAN JACKSON ROOF
Site Meetings - Weekly site meetings were planned to monitor progress of roof repairs.
Next Site Meeting to be held this Thursday, August 15, 2002. The Contractor was advised by
Gale Associates earlier that week that there was no assurance the School Dept. would allow
Atlas Roofing to work while school is in session. Superintendent of Schools, Principal and other
staff members plan to attend this meeting to review /comment on Atlas', plan of action. (i.e. safety
plan, sequence of work, expected completion dates etc.)
Site Inspection — Gale Associates inspected roof surface preparation earlier that day, prior to
application of paint primer.
Ventilation In response to a previous issue raised by the School Dept. regarding ventilation
during painting, a Gale's Field Report (dated 8/13/02) noted Ed Stewart had observed interior
conditions during spray application of paint primer and that no paint odor appeared to be present.
In addition, the school maintenance staff did not report any interior odor of paint when asked by
Gale.
ROBINSON ELEMENTARY SCHOOL
Project Close -out Town Accountant was gathering audit information that week and asked
MBC to verify final status of the school renovation project. Based on a previous suggestion by
David Young MBC issued a letter to the file identifying the project was closed. Due to an
unpaid energy credit due from J.T. Callahan & Sons to the Town of Mansfield, a final
Application for Payment to J.T. Callahan was never processed. (Amount owed to J.T. Callahan
equals zero.)
QUALTERS MIDDLE SCHOOL
Window Claim — Gale Associates submitted a Window Investigation Report (dated July 29,
2002) in response to a previous request by MBC to determine a cost to correct 272 inoperable
windows installed during recent renovations. Committee members expressed concern that the
report states many of Gale's "opinions" on issues relating to improper window installation.
MBC will ask Town Counsel to review wording. Members unanimously agreed that Option #5
referencing credit to Town for materials was unacceptable and should be deleted.
Ramp Lighting — David Young opened discussion regarding insufficient lighting at front ramp
entrance creating a possible safety issue. MBC discussed sending a letter to School Dept.
recommending School Dept. obtain a cost estimate to install or possibly ask Gale to design
additional lighting.
Handicap Station/Home Economics — Installation of one handicap unit was required to meet
ADA Code requirements. Per Bldg & Grounds Office, the unit was delivered last week. School
Dept. needs to install.
JORDAN JACKSON ELEMENTARY
Contract Agreement/Gale Associates — Concern was raised by Ed Stewart earlier this week, that
Construction Administration was not included as part of original contract Settlement Agreement.
Based upon conversation at the Pre - Construction Meeting, Gale Associates had agreed to handle
construction administration until a project schedule was generated. 'MBC has not received a
project schedule to date.
Request for Funds — MBC received letter from the School Superintendent requesting information
on funds remaining from school projects. Rich Feeley to update the MBC's school budget
summary.
FISHER- RICHARDSON HOUSE RESTORATION PROJECT
Sub -bid Opening — Scheduled to occur Wednesday, August 14, 2002 at noon. Architect and
MBC Secretary to oversee bid opening.
Construction Sign — Proposal to reduce the size of the project construction sign needs to be
approved by MASS -HC.
INVOICES
Eleanor McCarter — Fisher- Richardson House Project
MOTION to recommend payment reimbursement to Eleanor McCarter in the amount of
$65.40 for mailing fees incurred to send plans & specifications during the bid process for
the Fisher Richardson Project. DY /JL: Passes 5 -0.
James Bright Architect — Fisher - Richardson House Project
MOTION to recommend payment of Invoice No. 3 to James Bright Architect in the
( amount of $2,664.07 for Professional Services rendered for the Fisher Richardson Project.
Amount includes $704.07 printing costs. WM/DY: Passes 5 -0.
W.B. Mason — MBC Office Supplies
MOTION to recommend payment to W.B. Mason in the amount of $130.65 for
miscellaneous MBC office supplies. WM/KG: Passes 5 -0.
Gale Associates — Qualters Middle School Window Claim
MOTION to recommend payment of Invoice No. 0207070 to Gale Associates in the amount
of $2,664.07 for Professional Services rendered June 1 to June 30, 2002. Fee is related to
preparation of a Window Investigation Report needed for ongoing litigation.
WM/DY: Passes 5 -0.
Gale Associates — Jordan Jackson School — Roof Repair
MOTION to recommend payment of Invoice No. 0207056 to Gale Associates in the amount
of $1,500.00 for Professional Services rendered June 1 to June 30, 2002. DY /JL: Passes 5 -0.
The Sun Chronicle — Fisher- Richardson House Project
MOTION to recommend payment of Invoice No. T000825106SC to The Sun Chronicle
newspaper, in the amount of $297.00. 'Expense incurred was for advertising the
"Invitation to Bid for the Fisher- Richardson House Project. KG /JL: Passes 5 -0.
_
The Sun Chronicle — Water Treatment Plant and Wells Project
MOTION to recommend payment of Invoice No. T000820541 SC to The Sun Chronicle
newspaper, in the amount of $101.64. Expense incurred was for advertising the "RFQ for
Engineering Design Services for the Water Treatment Plant and Wells Project.
JL/KG: Passes 5 -0.
The Sun Chronicle —Water Treatment Plant and Wells Project
MOTION to recommend payment of Invoice No. T000825354 SC to The Sun Chronicle
newspaper, in the amount of $106.92. Expense incurred was for advertising the "RFQ for
Engineering Design Services for the Water Treatment Plant and Wells Project.
JL(KG: Passes 5 -0.
Meeting adjourned at 10:30 PM.