HomeMy WebLinkAboutMBC Minutes 8/22/2006i
a ti
DECEIVED
Town of Mansfield
06 SEP 15 Ali 10: 15 Municipal Building Committee
Meeting Minutes of August 22, 2006
i iAN"; -'IE -D
Members KhfibACHUSETTWilliam Moore, Chairman, James Liddick, Clerk, Alan Clapp,
Kenneth Gay, and Eleanor McCarter, Secretary
Attendees: Kurt Gaffney, Assoc. MBC Member/Water Operations Manager
Lee Azinheira, DPW Director
Robert Chapell, Woodard & Curran
Meeting commenced at 7:30 P.M.
WATER TREATMENT FACILITY PROJECT
Status Update - MBC members met with Bob Chapell to confirm the status of outstanding
warranty items at the new water treatment facility located at 500B East Street. (Warranty lists
dated June 29, 2006, revised July 20, 2006 and revised August 3, 2006). Hart Engineering was
notified to address these issues within the one -year warranty period. Jim Ramos of Hart
Engineering declined an invitation to attend this evening due to a prior commitment. A status
update was received from Hart Engineering via electronic mail prior to this meeting.
Outstanding Warranty Items:
1. Air Scour/Wash Blower trips dining backwash (warranty list 6- 29 -06)
Hart Engineering (Response Aug. 8, 2006): Fall River Electric confirmed to Jim Ramos
that the combination starter's thermal overload was set too low as shipped from the
factory, as they did not take into account motor's service factor. This was adjusted
accordingly.
DPW/Water Dent: System backwashes are performed on a weekly basis. There are no
recurring problems at this time.
Status: Closed item.
2. IR rinse valves failed to open during "Auto" regeneration (warranty list 6- 29 -06)
• Hart Engineering: (Response Aug. 15, 2006) Valve failure is determined via limit switch
feed back. Limit switch's can come out of adjustment due to flow /mechanical causes.
Limit switch adjustment is standard maintenance. Switches were tested and verified
during start up.
• DPW /Water Dent.: Water Treatment Foreman indicates that this issue is still a problem
that needs to be resolved by Hart Engineering and /or Roberts Filter.
• Woodard & Curran: Bob Chapell disagrees with Hart's statement that the limit switches
for the IR rinse valves came out of adjustment due to flow /mechanical causes for these
reasons;
• The IR rinse valves have not been used since startup in August of 2005, and
questions how the valves could come out of adjustment when not being used.
• During a test of the intermittent regeneration program in May 2006, Woodard &
Curran observed that all of the IR rinse valves failed to open under "Auto"
operation mode. In order to confirm that the problem was not a "sticky" valve, at
that time, each of the IR rinse valves were manually exercised. When exercised
manually all of the valves moved to their correct position without any alarms.
W &C then completed a follow -up test of the IR rinse valves in "Auto" operation,
which resulted in the same failure of the valves.
• Status: Open item. Roberts Filter needs to address this issue.
3. Provide tttah* to owner suntntarizing steps and valves that should be opened or closed
during "Auto "regeneration (warranty list 6- 29 -06)
• Hart Engineering: Jim Ramos requested Roberts Filter to provide a matrix per contract.
• DPW /Water Dept.: Water Treatment Foreman indicates that the valves have never
opened during "Auto" regeneration.
• Status: Open item. Still waiting to receive matrix from Roberts Filter. Hart needs to
forward the matrix to Woodard & Curran upon arrival.
4. Filter Cotatrol Pattel program shotld riot allows perntartgaitate to enter the filter until after
receiving pertttissfve front Main Conh -ol Panel that vatdt valves are moved to con ect position
(warrano, list 6- 29 -06).
• MBC Discussion: MBC asked Woodard & Curran to confirm whether this is a change
order item.
• Hart En ing eering (Response Aug. 15, 2006): Per Roberts Filter, Roberts has no control
of the vault valves. The subcontractor indicates that programming modifications can be
made to incorporate this request, but would require Hart to provide a written request and
Purchase Order to accomplish this task.
• DPW /Water Dept. Comment: Water Treatment Foreman indicates that this issue is still a
problem that needs to be resolved.
• Woodard & Curran: Bob Chapell is aware that the Filter Control Panel (FCP) does not
have direct control of the vault valves. W &C does not require the FCP to control the
valves.
• W &C's wants Roberts Filter confirm that the FCP waits for the permissive from
the Main Control Panel (MCP) before proceeding with the IR sequence. This step
is necessary to ensure that permanganate waste is directed to the equalization
tank.
• Bob Chapell reiterated that W &C is not requesting that the FCP be modified to
control the vault valves.
• Status: Open item. Roberts Filter needs to address this issue.
S. Provide repairs1modications to NaOCIMetering Pump No. 1(warranty list 6- 29 -06)
• MBC Discussion: The center chlorine metering pump has been leaking at fitting and tube
below counter.
• Hart En ineering (Response Aug. 15, 2006): Hart Engineering hired LMI to furnish and
install fittings and has since returned to correct any leaks found.
• DPW /Water Dept.: A representative from Northeast Pump was on site 8 -14 -06 and
replaced a fitting on the center NaOCI metering pump with the same style as two other
chlorine pumps on either side. A spare fitting was also provided for future use at that
time. Hart believes item is resolved to everyone's satisfaction.
• Woodard & Curran: Bob Chapell noted that the manufacturer had changed the design of
the fittings during the course of the project, and had since reverted back to the original
design which they found performs more efficiently.
• Status: Closed item.
6 Repair KOH leak at the KOH motorized valve (fvarranty list 6- 29 -06)
• MBC Discussion: MBC reported to Hart that the recent repair by Hart on 8 -7 -06 did not
fix the ongoing KOH leak issue. Chemical leaks have been an ongoing issue since
substantial completion of the facility. Jim Ramos was notified that Hart is responsible to
fix all leaks until its no longer an issue, even if this time extends beyond the one -year
warranty period. KOH material continues to leak as of this date.
• Hart Response: Hart's personnel was on site 8/7/06 to correct any visible leaks. MBC
reported a continued leaking situation near the motorized valve to Jim Ramos on 8/9/06.
Hart ordered new "O" rings and will return to the site to correct accordingly.
• DPW/Water Dent.: Water Treatment Foreman indicates that this problem still needs to
be resolved.
• Woodard & Curran: Bob Chapell concurred that a small leak remains at the threaded
fitting near motorized valve.
• Status: Open item. Hart Engineering to return and install "O" rings. Repair work needs
to be coordinated with Water Treatment Foreman, Kevin O'Donnell.
7. Repair leak near the flange on the KOH transfer pump (warranty list 6- 29 -06)
• MBC Discussion: Chemical leaks have been an ongoing issue since the project was
substantially complete. Hart is responsible to fix all leaks until its no longer an issue,
even if this time extends beyond the one -year warranty period.
• Hart Engineering: Hart has ordered new "O" rings and will return to correct accordingly.
• Status: Open item. Hart Engineering to return and install "O" rings. MBC Secretary
will notify Jim Ramos to coordinate leak repair work with Water Treatment Foreman,
Kevin O'Donnell.
8. Investigate and repair Filter flow meters (warranty list 6- 29 -06)
• Hart Engineering: Flow indication forward and backwash are correct and set up by the
manufacturer. Step 7 is a transition step therefore flow indication will be effected. A
programming modification can be made by Roberts Filter to ignore the indication during
this step if desired. Roberts Filter would request a written change order for this work if
the modification is requested.
• DPW /Water Dept.: Flow meters indicate a fluctuating flow rate and /or zero during
backwash (Step 7). Water Treatment Foreman, Kevin O'Donnell indicates that this
problem needs to be resolved.
• Woodard & Curran: Bob Chapell explained that Step 7 is designated by Robert Filter as
a "Pre -low flow backwash" with an adjustable preset for the step duration currently set at
5 minutes.
o The statement by Roberts Filter of this being a "transition" step where operators
are to ignore the flow readings for the duration of the step is confusing. W &C
questioned the point of the low flow rate for 5 minutes, if the staff cannot verify
that flow rate. Also, the valves typically take 10 to 30 seconds to move to their
required position.
• Bob Chapell questions whether Roberts Filter response is stating that no function
other than valve positioning is happening during Step 7 for 5 minutes? If so,
W &C wants confirmation.
• Woodard & Curran does not need the Filter Control Panel modified to ignore this
indication.
• Status: Open item: Roberts Filter needs to respond to Woodard & Curran regarding this
issue.
Note: Bob Cltapell referenced having recent conversation with Harlan Bartlett of Roberts
Filter about issues at the Water Treatment Facility. Mr. Bartlett assured Woodard &
Curran that Roberts would return to resolve outstanding issues with the treatment system.
9. Landscaper to rentol,e and replace (4) fbur dead shrubs (warranty list 6- 29 -06)
• Status: Pending. See Item No. 13 below.
10. Repair /replace Weil McLain Boiler controller (warranty list 6- 29 -06)
• MBC Discussion: Ken Gay suggested that DPW request the HVAC contractor
(InControi) to verify repair /replacement when they perform seasonal changeover from
cooling to heat this fall.
• Hart Engineering: Mark Cordery (NEP) informed Jim Ramos that this work was
completed earlier in the year. Hart requested, but has not received written confirmation
from his subcontractor.
• Woodard & Curran: Bob Chapell is unable to verify.
• Status: Closed item. Town will request InControi to confirm change.
IL Sensor for boiler water supply temp relocated to supply header )Varranty list 6- 29 -06)
• Hart Response: Mark Cordery (NEP) informed Jim Ramos that this work was completed
earlier this year. Hart requested, but has not received written confirmation from his
subcontractor. Hart believes work is done and recommends owner field verify.
• Woodard & Curran Response: Bob Chapell stated that as of this date the sensor remains
in the wrong location.
• Status: Open item. New England Pipe needs to respond.
12. Correct space gap in exhaust louver in northwest corner of Vehicle Storage Roont (warranty
6- 29 -06)
• Hart Engineerintr (8- 15 -06): Mark Cordery (NEP) informed Jim Ramos that this work
was complete. Hart personnel was on site 817106 and adjusted the damper to close
further.
• MBC Discussion: MBC previously notified Hart that the louver installed needs to close
tight with no air gaps, in order to avoid drafts complaints.
• Hart Engineering (8- 22 -06): NEP and Hart adjusted this damper several times and believe
it is fine. Jim Ramos responded that the damper in question is an intake.damper, which
simply has aluminum blades that close against each other. There is no gasket for a
completely weather -tight seal therefore a slight gap should be expected when in the
closed position.
• DPW /Water Dept. Comment: Water Operations Manager Kurt Gaffney reported that
prior adjustments to repair the damper are unsatisfactory.
• Louver panel is still bent.
• Space gaps between the louvers on the upper tier of the damper approximately f -
inch wide must be corrected.
• Kurt Gaffney noted that the louvers on a second damper installed in the opposite
side of the same garage do close tight.
• Woodard & Curran: Both dampers should close tight to prevent heat loss.
• Status: Open item. Hart and/or Phoenix Sheet Metal need to address this item.
13. Revised; Remove `ALL" dead shiwbs and replace ivith new plantings. (Revised warranty
list 7- 20 -06)
• MBC Discussion: Owner requests all dead shrubs be removed and new plantings be
installed during planting season Sept. 2006. 1 -year warranty is expected for all new
plantings.
• Hart Engineering: MON Landscaping is scheduled to replace shrubs. Subcontractor
visited the site and agreed it would be best to wait to replace "ALL" dead shrubs during
fall planting season.
• Status: Pending completion of Item 9 and Item13:
14. Adjust belt for indoor fan in air handling unit (Revised warranty list 7- 20 -06)
• Hart Response: NEP was contacted and did not response. Belt was adjusted accordingly.
• Status: Closed item.
15. Replace filters in air handling unit with proper size (revised warranty list 7- 20 -06)
• Hart Engineering: Correct size filters are installed. Owner needs to replace filters on
occasion as part of routine maintenance.
• Status: Closed item.
16. Lights on hwnsfer pump boxes do not illuminate in i7in and close positions
• Hart Response: Hart verified power is active lights on pump panel.
• DPW/Water Dent.: Water Division to replace bulbs as necessary.
• Status: Closed item.
17. Adjust door weather stripping to close center- gap between doors in wafer treatment area
(warranty list 7- 20 -06)
• Hart Response: Adjustments to weather stripping is as of 7 -7 -06.
• DPW /Water Dept, Comment: Work appears to be satisfactory.
• Status: Closed item.
18. Investigate trouble signal and reset Fire Alarm System (wan•anty list 8 -3 -06)
• Hart Response: Alarm system was checked completely and reset by Fall River Electric
on August 7, 2006.
. I
• DPW/Water Dept Comment: Fire Dept. was unable to reset system. The problem may
have been associated with fire hydrant testing that was going on outside of the building.
• Status: Closed item.
19. Continued problem reported with leaking at motorized valve (8 -3 -06)
• Hart Response: New O -rings should be delivered this week. Hart will return to change
accordingly.
• Status: Open item. Hart needs to address ongoing leak issues.
Related Discussion:
UtMwid brnoice/Door Systems, Inc. — The Water Division received an invoice in the amount of
$345.00 for overhead door repairs that were completed within the warranty period. The invoice
was fouwarded to Hart (letter dated July 25, 2006) and is not yet paid. The Water Division
received a 2nd notice regarding payment this tiveek. The Water Department hill reseed invoice to
Hart L'ngineering for payment.
Vehicle Wash Station — Lee Azinheira advised the MBC that he was unhappy with the
performance of the drainage system in the new vehicle wash station.
• The Highway Division is experiencing problems with the drain clogging.
• The Water Division issued a written request to Woodard & Curran on behalf of the
Department of Public Works to investigate this matter (letter dated August 3, 2006).
• Based on preliminary investigation to date, it appears that the drain piping was not
installed in accordance with the plans.
• Inspection services were provided by a sub - consultant of Woodard & Curran on a part-
time basis for this project.
• The MBC /Water Division has no record of changes made "In the Field" regarding this
issue.
• Woodard & Curran will work with the Department of Public Works and is requesting that
Hart Engineering provide revised As -Built Drawings for the project.
Future Project Proposal — Kurt Gaffney announced that the Mansfield Water Division is now
working on preliminary design plans to construct a new water treatment facility to support the
Albertini Wells in Mansfield. A request for funds will be submitted for a vote at the Annual
Town Meeting in Spring 2007. The Water Dept. also plans to seek approval for a State
Revolving Fund Loan for this project. MBC may be asked to become involved with this project
after funding is approved.
Meeting adjourned at 9:15 P.M.
Respectfully submitted,
Eleanor McCarter, Secretary
�' Jp
Wines Liddick, Clerk
Date
q, /2 -0Co