HomeMy WebLinkAboutConservation Minutes 3/10/1986MANSFIELD rOf NDDAY, MARCHS10,A1986 COMMISSION M
gg��-' : G ONE
Si
Members Present: Chairman Sweet, Commissioners O'Neill, Graham, Mandell
and Barr*
Prior to the meeting being called to order, a Mr. Jim Roberts of Pine Needle
Lane introduced himself and asked if there would be any objections to his
removal of some dead trees behind his property. He said most of them were
from the hurricane and he would be willing to sign a release before any
work was done. There were no objections.
The meeting was called to order at 7:33 p.m.
Edward J. Broderick - Camelot Estates
Mr. Broderick appeared before the Commission to report on the progress of
the drainage system at his Camelot Estates project. He advised that they
have constructed the system from the brook in the back to the retention
area and that he expects the work to be completed for that particular phase
in about one month. The Commission members agreed to view the site on
Saturday morning, March 22, at 8:00 a.m.
Turner Brothers Construction - SE211 -158
Erick Road Project
Robert Turner of Turner Brothers Construction and Malcolm Post of Post Properties
appeared before the Commission regarding the Cease and Desist Order they were
served in connection with their Erick Road - Bristol Arms Project.
Mr. Turner explained that with the transfer of authority from Karl Droun to
Scott Leite, the plan that was originally filed with the Board of Health was
lost. They re -filed and the leach fields nos. 1, 2 and 3 were approved.
When Mr. Leite came to the site to inspect the field that was installed, he
noticed a wet area and notified Chairman Sweet.
Mr. Turner stated that they proposed to move the field 80 feet back from the
edge of the wetland and install a siltation fence along the perimeter of the
property. Commissioner O'Neill questioned why the wetlands were never shown
on the original plans. Commissioner Barr maintained that one of the buildings
was sitting on the site of a pond or a sink hole.
Chairman Sweet advised Mr. Turner that by law it would be necessary to hold a
public hearing on the matter. It was agreed that in the interests of saving
time, the Commission would hold a special meeting the following Thursday to
hear this matter.
*Commissioner Barr arrived at 7:47 p.m.
MANSFIELD CONSERVATION COMMISSION MINUTES
MONDAY, MARCH 10, 1986 PAGE TWO
MOTION: To hold a meeting of the Commission on
Thursday, March 20, 1986 in order to
hear this matter.
(Barr - Graham; all in favor) VOTED
Wetland Protection Act Hearing - SE211 -156
Assembly of God
1007 West Street
A Wetland Protection Act Hearing was held on a Notice of Intent dated
February 18, 1986. The project involves construction of an assembly
building with a 550 seating capacity including the development of a
drainage system, driveway and on -site sewage disposal facility. See
attached summary.
Wetland Protection Act Hearing - SE211 -154
Steve Benoit - Williams Street
A continuation of a Wetland Protection Act Hearing was held on a Notice
of Intent dated February 5, 1986. Mr. Benoit appeared and submitted the
new plan previously requested by the Commission. See attached summary.
Mr. Endriunas
Reclaiming of Whiteville Pond
Mr. Endriunas appeared before the Commission regarding reclamation of
Whiteville Pond. He is the excavating business and has been approached
by some of the abutters about cleaning the pond and making it more usable
to the residents. He stated there were about 19 abutters. Chairman Sweet
advised him that it would have to be treated as a wetland matter with
drawings showing present conditions and future conditions including any
impact either upstream or downstream. Mr. Endriunas stated he would be
taking gravel out of the pond which would probably involve a change in the
depth of the pond from about 3 feet to 15 feet.
Foxfield Corp. - SE211 -155
Mr. Michael Trowbridge of RIM Engineering appeared before the Commission with
new plans addressing the issues listed in the Commission's Orders of Condition
dated February 25, 1986. Mr. Trowbridge stated that they had moved the
leaching trench back as a result of a meeting with the Planning Board and had
put in a non - leaching pipe in one section. In response to a question raised
by Commissioner Mahoney regarding the distance of the leach field from the
edge of the wetlands, Mr. Trowbridge stated that Sanford Ecological Services
MANSFIELD CONSERVATION COMMISSION
MONDAY, MARCH 10, 1986
MINUTES
PAGE THREE
checked the distances and felt the flags were where they should be. An
abutter was present and stated that the Soil Conservation Service recommended
that there should be a perforated pipe to handle ground water and a solid
pipe to handle surface water. Mr. Trowbridge stated he had already been
before the Planning Board and was told the town engineer did not feel this
was a good idea.
The Commission will write a letter stating that work may commence on the
project.
New Business
140TION That the minutes of January 27 and
February 10, 1986 be approved as
written.
(O'Neill - Graham; Mandell abstained) VOTED
Correspondence
1. Payroll voucher for Marilyn Holman for $195 from February 4, 1986 to
March 3, 1986.
MOTION To pay.
(O'Neill - Graham;.all,in favor). VOTED
2. Bill from Bristol Office Supply in the amount of $36.76 for office
supplies.
MOTION To pay.
(Graham - O'Neill; all in favor) VOTED
Orders of Condition - SE211 -152
M. R. Keefe - 252 -258 West Street
1. This is a new Order of Conditions and will supersede those written
on January 27, 1986 and recorded with the Bristol County Registry
of Deeds on January 30, 1986 at Book 2908, page 139.
2. Work shall proceed according to the revised plan dated February 26,
1986, said plan showing compensating wetland.
3. Hay bales shall be placed along the edge of the existing brook during
construction, excavation and until the seeded areas have been firmly
established.
4. All disturbed areas shall be appropriately loamed and seeded.
MANSFIELD CONSERVATION COMMISSION MINUTES
MONDAY, MARCH 10, 1986 PAGE FOUR
** Meeting with the Board of Selectmen on March 19
Discussion on this matter was postponed as Mr. Trowbridge asked if he
could have a few minutes of the Commission's time on a couple of matters.
Franklin Street - Regarding street drainage on Franklin Street, Mr. Trowbridge
advised that the town will be taking over and did the Commission have any
objection to the use of 24 -inch corrugated pipe instead of RCP. The Commission
members stated that they had no objection.
Condyne on Oakland Street - Regarding on -site drainage at this project, Mr.
Trowbridge advised that they originally planned on using 12 -inch PVC with
sewer Ys, but found that it was extremely expensive. He asked if the Com-
mission had any problem with their using perforated pipe. The Commission
members agreed.
MOTION To agree to the use of 24 -inch corrugated pipe
instead of RCP on Franklin Street and to the use
of perforated pipe instead of 12 -inch PVC with
sewer Ys at the Condyne - Oakland Street project.
(O'Neill - Barr; all in favor)
VOTED
In connection with the Foxfield project, Mr. Trowbridge asked when they might
commence work there- it was agreed to send a letter stating that the additional
information requested had been provided to the Commission and that work could
proceed. A copy of the letter will be sent to the DEQE and a copy will be filed
at the Registry.
** Meeting with the Board of Selectmen on March 19
Members of the Commission are to meet with the Board of Selectmen on March 19
at 8:00 p.m. at which time they will be making a presentation regarding the
need for a conservation agent. It was suggested that the Commission be ready
to supply figures on salary, mileage and any necessary office equipment.
Little League /Soccer
Commissioner Ouellette was approached about the Little League giving some of
its land to the Soccer League. It seems the Little League is in need of
money to build their concession stand. They would like to enter into an
agreement with the Soccer League whereby they would give them some room on
the conservation land in return for some help with the concession stand.
Chairman Sweet noted that there is a contract between the town and the Little
League that is quite involved and explicit. He feels that they just cannot
arbitrarily give the Soccer League some of the land without coming in an
making a presentation. In reviewing the file, he also noted that the
MANSFIELD CONSERVATION COMMISSION
MONDAY, MARCH 10, 1986
MINUTES
PAGE FIVE
contract was written in 1979 and was to run for only six years. To his
knowledge, it has not been renegotiated.
MOTION To adjourn at 11:26 p.m.
(Mandell - Graham; all in favor) VOTED
The next meeting of the Conservation Commission will be held on March 20, 1986.
Approved by:-
Date to Town Clerk: E- YG
/msh
Applicant: Assembly of God
File Number: SE211 -156
Location of Project: 1007 West Street
Purpose of Project: Construction of 550 seat assembly building
including development of a drainage system,
driveway and on -site sewage disposal facility
bordering wetland.
In attendance: James M. Dunn, Dunn Engineering Co.,
Pastor Hans Theerman
Abutters: Richard and Theodore Wuschke
Warren A. Jansen
The Wetland Protection Act Hearing on the Notice of Intent dated February 18,
1986 for the Assembly of God opened at 8:02 p.m. Mr. James M. Dunn of Dunn
Engineering made the presentation on behalf of the Assembly of God.
The project involves the construction of a 550 seat assembly building including
the development of a drainage system, driveway and an on -site sewage disposal
facility bordering lands subject to flooding. The first area in question is
an area subject to flooding which is adjacent to the proposed location of the
assembly building. There is also a second area running next to West Street
subject to flooding.
The first area in question adjacent to the proposed location of the assembly
building contains a water body of approximately 1542 square feet which is ap-
proximately 18 inches deep. It is proposed to move this area to a detention
basin located in the lower portion of the property bordering the second area
subject to flooding. It is proposed to construct a drainage system from
the proposed building to the detention area below. There is a stone culvert
below West Street which would be used. A gas /oil separator would be installed
to handle any spill that would occur in the parking lot or on the surface of
the roadway.
The retention /detention area will allow for the retention of the water presently
being held on the northerly side of the proposed building. The outlets in
the retention area have been designed to be one foot above the base of the
basin itself to allow for the retention of this water. The area will also
allow for the detention of water from a 10 or 100 year storm. The water which
runs raturally down the roadway will be picked up in a series of catch basins
and paved scuppers located along the edge of the asphalt. A pipe will be
installed below the driveway with a riprap area. A concrete outlet structure
will also be installed which will consist of a concrete wall with a 24 -inch
pipe 16 feet long which will allow the flow to be controlled from the basin.
The area of the outlet structure will be double hay baled before any work is
started.
Hearing Summary Continued . . .
Applicant: Assembly of God
SE211 -156
Mr. Dunn stated they would need to keep the peak flows below what they are
now. He stated that the peak flows were presently 19.7 cubic feet per
second under a 10 -year storm and 35.4 cubic feet per second under a 100 -
year storm. After construction, he estimated the peak flows to be reduced
to 15.0 cubic feet per second under a 10 -year storm and 28.2 cubic feet per
second under a 100 -year storm.
When questioned by Commissioner O'Neill, Mr. Dunn stated that the new detention/
retention area would be 8,000 square feet.
Commissioner Graham questioned whether there were any vegetated wetlands prior
to removal of all of the trees. She noted that when the site was walked, it
seemed to be very wet. Mr. Dunn stated that one of the problems they have
encountered is the impervious nature of the soils below the surface. He
stated that he could not identify any vegetated wetlands on the site.
Mr. Dunn stated that a 6 -inch berm would be installed from the paved area at
the upper portion of the project along the southeast side of the road down to
West Street to help protect the abutters. The abutters present were concerned
with the removal of the trees and what effect this would have on them. Speci-
fically, Mr. Jansen questioned that the measures being taken would protect his
property. Mr. Dunn and Pastor Theerman stated they would not be opposed to
putting up a swale or,.a.berm along the upper portion to protect Mr. Jansen's
property. Chairman Sweet asked whether the construction of such a berm would
affect the flow calculations. Mr. Dunn stated that the 12 -inch pipe could
handle the flows.
Chairman Sweet advised those present that the Commission would be writing
the Orders of Condition at either the March 20 meeting or the meeting
following. He also advised that the Orders could be appealed to the DEQE
within 10 days by any abutter or any ten residents. The hearing closed at
9:04 p.m. All fees have been paid.
Applicant: Steve Benoit
File Number: SE211 -154
Location of Project: Williams Street
Purpose of Project: Construction within land bordering
vegetated wetland and within 100 foot
buffer zone.
In attendance: Steve Benoit
Abutter: Jay Goldman
This was a continuation of a hearing previously held on February 24, 1986.
The hearing opened at 9:05 p.m. Mr. Benoit represented himself. The
hearing was continued pending the receipt of a new plan delineating the
following items: (i) driveway; (ii) culvert; (iii) wetland; (iv) distance
of septic system from wetland; and (v) contour line onto Mr. Goldman's
property.
The Commission members reviewed the revised plans noting the items pre-
viously requested. Runoff from the common driveway will be going back
into the wetland. No fill will be required. The main concern would be
siltation during construction.
Abutter Jay Goldman was present. His original concerns were whether
there was going to be any fill or a swale that might cause him problems.
It was decided there were no further concerns to be addressed and the
hearing was closed at 9:17 p.m. The Orders of Condition will be written
at either the next meeting of the Commission on March 20, or at the meeting
following. All fees have been paid.