HomeMy WebLinkAboutConservation Minutes 6/26/1989MANSFIELD CONSERVATION COMMISSION MINUTES NOV 0����
MONDAY, JUNE 26, 1989 -- PA6E 1
Members Present: Chairman Ouellette, Commissioners Cauldwell, O'Neill, Owens, i
Rhoads
The meeting was called to order at 7:30 p.m.
LOT 16, NELSON WAY - Discussion with Steve Benoit re compliance with Order of
Conditions SE211 -302
Mr. Benoit explained that the footprint has not moved, but the lot line
between lot 15 and lot 16 has changed, as shown on the plan submitted for
purposes of replication. Comm. Rhoads asked why Steve chose the area so far
back for replication. Dick suggestel it, according to Mr. Benoit. Chairman
Ouellette has observed that the hay bale line is in place. Commissioners
indicated to Mr. Benoit the need for the following:
- -a planting scheme, etc. for the replicated area.
- -more in -depth information than what is currently written on the plan
-- inspection thre=_-hholds, or some method of surety relative to the
replication (to be discussed with Dick when he returns from vacation)
-- progress in the replication area (Without replication having been done on
lot 17, the commission indicated to Mr. Benoit that no certificate of
compliance will be issued for lot 16.
-- letter stating when certain levels of completion will be reached:
excavation, loaming and planting, meeting the 50% vegetation criteria,
etc.
i
Once these details have been completed, the commission feels that Mr. Benoit
will have met the intent of the Order of Conditions.
MOTION: That wort: be allowed to proceed, based on the receipt of the Board
of Health plan, a verified footprint, and the receipt on 6 -27 -89
of a letter containing the requested information.
(Rhoads - Cauldwell; all in favor) VOTED
REQUEST FOR DETERMINATION OF APPLICABILITY -
Florence Poholek - -28 Angelina Lane -- Excavation, installation of in- ground
Pool within 100 feet of wetlands
A pump and dry well will be present because of the high water mark. This
lot (13) is included in Order of Conditions under file SE211 -134, which is
currently undergoing a review, with a possible change in the replication. If
the order is amended as proposed at the 6 -19 -89 meeting, the pool would be
within the buffer zone by six feet. Mrs. Poholek was advised to pump nothing
toward the wetlands; she stated that the well will be kept out of the buffer
zone as much as possible. The dry well will be constructed first, so water
during construction can be pumped into it.
NOTION: To issue a negative determination #3.
(Owens - O'Neill; all in favor) VOTED
MANSFIELD CONSERVATION COMMISSION MINUTES
MONDAY, JUNE 26, 1989 -- PAGE 2
WETLANDS PROTECTION ACT HEARING - SE211 -308
Folkman u Zola Builders- -185 Mill Street -- Construction within 100 feet of
wetlands
There will be no filling in the 100 -year flood plain; extensive wort: will
take place within the buffer zone. Comm. Rhoads explained the need to install
dry wells for roof leaders, which will be included in the orders. Abutters have
not been notified; the applicant requested a continuation to attend to this.
Keith Properties will retain ownership of the house being built, as a model
home. The site wall; will take place on 7 -1 -89 at 7:30 a.m. The hearing will be
continued to 7 -10 -89 at 7:30 p.m.
WETLANDS PROTECTION ACT HEARING
Jerrold C. Wood - -223 Franklin St. -- Construction of 2 -car garage
Mr. Wood explained that a brook runs along his property line. Comm. Rhoads
is not concerned about the flood plain impact for a project of this size. Site
will be walked 7 -1 -89 after the Mill St. site. Foundation hole may have to be
Pumped. Abutters will be notified before the next hearing.
MOTION: To continue to site walk and to 7 -10 -8? at 9:00 p.m.
(Rhoads - O'Neill; all in favor) VOTED
WETLANDS PROTECTION ACT HEARING CONTINUATION - SE211 -304
Dana Colby - -26 Cavan Crossing
NOTION: To continue to 7 -10 -89 at 9:15 p.m. in the absence of the
applicant and revised plans.
(Rhoads - O'Neill; all in favor) VOTED
CERTIFICATES OF COMPLIANCE:
SE211- 218-- Texeira, Wessel /Thompson St,
NOTION: To issue a Certificate.
(Owens - O'Neill; all in favor, Cauldwell abstaining) VOTED
SE211- 250-- Brookdale, Matthew Estates, lot 15, b Jacob Drive. Chairman
Ouellette observed the site on 6- 26-89. She informed the applicant that the
originally disturbed area should be loamed and seeded, or stabilized with a
wildflower mix. The applicant indicated that would not be a problem.
MOTION: To issue the Certificate, to be held by Chairman Ouellette and
released at an appropriate time,
(O'Neill - Rhoads; all in favor, Cauldwell abstaining) VOTED
SE211- 284 -- Release requested for lot 15, and the bond for lot 1 ?, of fling
Arthur Way.
NOTION: To postpone decision until Commissioners have looked at the site.
(O'Neill - Rhoads; all in favor) VOTED
MANSFIELD CONSERVATION COMMISSION MINUTES
MONDAY, JUNE 26, 1989 -- PAGE 3
SE211- 298 - -Nr. Benoit state that 11 Nelson Nay will be ready for inspection
on 6- 29 -89, and he is requesting a Certificate of Compliance.
ORDER OF CONDITIONS - SE211 -306
Inspections should be conducted annually for an initial two -year period,
subject to review.
MOTION: To issue the order with the above change.
(O'Neill - Owens; all in favor) VOTED
Hearing Continuation on Request for Amended Order of Conditions, SE211 -134 -
Mansfield Manor Estates, Fruit Street
New plan submitted. Removal of material from the proposed site of
replication may be a Problem, because those granting the right of way may not
want truck traffic. The bottom of the flood storage area would appear to be a
"wet basin" which will vegetate; water will probably run in the brook 1Q -11
months per year. This parcel is owned by the applicant. The commission had
requested a letter stating that this Parcel was included in the original filing.
The easement issue may be best handled by Planning Board, since this proposal is
Part of the subdivision drainage and will have to be reviewed by them as a
change in the plans. A walking easement over lot 18 (specifying no heavy
equipment) might be sufficient for the Conservation Commission's purposes; the
applicant was requested to supply such a document. The project will probably
have to go before both the Planning Board and the Board of Selectmen. Comm,
Rhoads has reviewed the calculations and found them adequate.
NOTION: The hearing was closed on 6- 26 -89.
(Rhoads - O'Neill; all in favor)
SHELL OIL PIPELINE
VOTED
Comm. O'Neill requested further information regarding the wort: being done
on the pipeline. Chairman Ouellette suggested that Did, could report to the
commission upon his return from vacation.
PHONE COMPANY
Chairman Ouellette will check with the town engineer about installation of
Phone conduit lines along Otis Street next to Sweet's Pond; Comm. Rhoads
suggested that they should do a buffer zone filing RDA.
Pumping of telephone company manhole near the DPW - Comm. Cauldwell
indicated that the pumped water goes right into the river. He will refer this
question to Dick Lewis upon his return.
FULTON'S POND
Chairman Ouellette, Dick Lewis, John Rhind, Bob Swanson, and Nick Carpeno
have walked the site. The broken plastic pipe in the area was originally from
the construction of the new dam and doesn't do anything. There is also a relief
valve, which has a control structure in the pond itself.
MANSFIELD CONSERVATION COMMISSION MINUTES
MONDAY, JUNE 'Lb, 1989 -- PAGE 4
CLERICAL BUDGET:
NOTION: To raise PF's salary to $8.00/hr. effective 7 -1 -89.
{Owens - Rhoads; all in favor) VOTED
MOTION: To send letter to TN's attention stating support and reasons for
such change.
(CauldwelI - O'Neill; all in favor) VOTED
The meeting adjourned at 10 :40.
Approved by: mar,_dQ `, � Q - � Date to town clerk:
/Pf 6 nn nn