HomeMy WebLinkAboutBOS MINUTES 2-17-1982BOARD OF SELECTMEN
AGENDA
February 17, 1982
1. 7:00 P.M. Meeting Opened for Correspondence Review
2. 7:30 P.M. Meeting Called To Order
Peter DeTrolio, Jr. - Leash Laws
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
Clerk's Folder
Warrants
Correspondence
8:00 P.M. Bill Callahan - Camp Dresser & McKee
8:30 P.M. Arthur Stockus - Whitman & Howard
Minutes of February 10, 1982
Town Manager's Report
Board Reports
Budget Review - Public Works
Adjournment
BOARD OF SELECTMEN
MINUTES OF MEETING
FEBRUARY 17, 1982
PRESENT: Chairman May, Selectmen Colella, Mahana, Levine, McNair,
Town Manager, W. Chadwick Maurer, Jr.
7:30 P.M. Meeting called to order. Peter DeTrolio, Jr. came before
the Board to discuss the local leash law. His complaint is that it is
not being enforced. His son's dog was attacked and injured by a neighbor-
hood dog in his yard. The DeTrolio's pet was on a run and the other was
running loose.. He would like to see the'Dog Officer pick up the loose
dogs. Selectman Levine would like a policy on dogs to be restrained or
held. Mr. DeTrolio suggested charging higher fines on the dogs that are
picked up. Town Manager will check with Town Counsel on the fines. The
Board suggested Mr. DeTrolio go forward and register a complaint against
the neighbor's dog.
Clerk's Folder
License for American Legion needed to be signed by Board members. Pre-i
viously voted. Also V.F.W. license to be signed. It was asked if VFW
was serving yet. This will be checked. Building Inspector Cook has
issued a temporary occupancy permit to the VFW. It was also asked how
long it would be before a permanent occupancy permit would be issued
from Bert. These items will be checked.
Warrants
* #52 - $443,673.40, Town and School Expenses. Selectman McNair questioned
voucher #3664 to MMWEC for $99,630.98 fuel expense. After a short dis-
cussion it was voted to approve the warrant, excluding voucher #3664 from
the $443,673.40. Mahana/Colella VOTED: 4 -0. Levine abstained.
Correspondence
Sewer connection permit from Paul Boyden, 64 Highland Avenue. Mr. Boyden
noted that there will be a two family home on the vacant lot.
* MOTION: To grant the sewer permit for 64 Highland Avenue. McNair/
Mahana VOTED: 5 -0.
Notice from Zoning Bd. of Appeals for hearing on March 3.
Letter from EPA re: grant increase amendment and contract #2 for Board's
approval. Will be discussed later with CDM.
Letter from Planning Bd. to SRPEDD re: requesting additional hours to
work on master plan.
( Notice from Head Start re: coffee hour at Brockton Hospital on 3/3/82.
Notice from Dept. of Public Utilities re: hearing for comments on
the recovery for advertising expenses by DPU. 3/4/82 10:00 A.M.
Selectman Levine mentioned that they should not have consumers pay for
their advertising.
BOARD OF SELECTMEN
MINUTES OF MEETING
FEBRUARY 17, 1982
PAGE 2
MOTION: To send a letter to the DPU advising them that they cannot
support the DPU's request to have advertising fees paid by
consumers. Levine /McNair VOTED: 5 -0.
8:00 P.M. Camp, Dresser & McKee. Charles Loveridge, Fernando Requena
and Bill Mackey were present from Camp Dresser to discuss the grant
increase details that were brought up at last week's meeting. The Board
had some questions on the additional design work. Mr. Mackey tried to
explain that the design changes were outside the scope of contract.
EPA approved the amendment for contract #2. The original contract in
1978 for design fees was $1,025,000 lump sum. EPA suggested $950,000
cost plus fixed fee contract. In a letter from Bill Callahan for the
application for the design contract, they agreed to change payment from
lump sum to fixed cost. CDM had Charlie Loveridge deliver the letter
from EPA so that the Board could approve contract 2 and put it out to
bid. Selectman Mahana requested that all letters be addressed to the
Board. He then asked for an explanation on the additional�!work due to
high groundwater. Mr. Mackey explained that they had taken 8 borings
at the site and that before the scope of work, they did not know where
they would put the building. The geo- technical engineers then did
additional borings and found the groundwater to be 6 -8' higher. He
noted that the soil is very thick, like clay at the site. This was when
the additional design work had to be done and it was not included in the
scope of work. They also had to do design work to add retention basins.
Discussion followed on the high groundwater and why CDM did not include
this work in the original scope of work for the design contract. Mr.
Mackey also mentioned that the geo- technical engineers indicated after
their borings that an underdrain system would be needed. There was some
discussion on charging back costs to the other towns when they connect
to the interceptor. Selectman Levine asked about the direct costs and
what was included in the overhead costs. Mr. Mackey went through these
items with the Board. The contingency for cost overrun was also discussed
and it was noted that this is provided in the contract for up to 5%.
After much discussion, it was decided to approve the grant increase and
approve contract 2.
* MOTION: To accept grant amendment #3 and to approve Contract #2.
Levine / Mahana VOTED: 5 -0.
CDM mentioned that they will be having monthly progress reports on the
plant and noted that Board members can go down to the site whenever they
like. Selectman Mahana would like to meet with EPA and State on some of
the charges. Selectman McNair also asked about the operating cost of the
facility. Mr. Loveridge had some figures available for the Board.
BOARD OF SELECTMEN
MINUTES OF MEETING
FEBRUARY 17, 1982
PAGE 3
Whitman & Howard - 9:00 P.M. Present from Whitman & Howard were Paul
Bucknam, Arthur Stockus and Bob Morrision, Water Supervisor. The dis-
cussion centered around the water division budget and status of water
department projects. Town Manager mentioned that when they went over
the budget last week, he had made an error in his calculations on the
budget. 1/6 of the billing was based on the new rate and 5/6 of the
billings was at the old rate. There was some discussion on the pro-
jected revenue for FY 1983 and power costs to operate. Capital improve-
ments for the water department were discussed. They can now go ahead
with these without raising the rates. Selectman Mahana advised Whitman
& Howard to send all correspondence addressed to the Board. They
talked about the water rate study and the projections included in the
study. The fire protection charge could also be put in the budget.
Selectman Mahana requested a revised schedule and long term budget
impacts. Paul Bucknam will come back in to the Board with more in-
formation along with an operating manual. He would also like a list
of all contracts that the Town & Whitman & Howard are involved with.
There was discussion on the capacity of the wells, status of Prescott
wells, Mill Street project, pumping capacity, etc. Town Manager noted
that the original rate structure was good for 10 years assuming all
recommendations were followed. The fire protection charge came up
again.. Selectman Mahana would like anew breakdown: what is outstanding
and in what direction should they be going. He would also like to
know about future sites for a possible reservoir, surface storage.
In conclusion, the water rate tables will have to be updated by
Whitman & Howard for the budget.
Return to Correspondence
Letter from Jaycees thanking Town for letting them use Spaulding School
for Haunted House. Board suggested sending a letter to Bob Cardin to
see if Jaycees would like to volunteer to pick up newspapers and bottles
for recycling program on a periodic basis.
Letter from Ron L'Herault of North Attleboro re: commuter rail parking
lots. Does not want to be charged a fee to park.
Notice from Dept. of Revenue re: bonds for Treasurer /Collector and
Town Clerk for 1982. Treasurer /Collector's bond is the same as last
year, and Town Clerk's went from $5,000 to $7,000 for this year.
Letter from MMWEC re: informational meetings 2/23 and 2/25 on Stonybrook.
Card of thanks from family of Mary Couture.
Meeting notice of Sturdy Advisory Committee 2/22/82.
BOARD OF SELECTMEN
MINUTES OF MEETING
FEBRUARY 17, 1982
PAGE 4
Sewer connection permit from Bonwood Corporation for his portion of
Fairfield property. Housing Authority will still have to apply.
* MOTION: To send sewer connection permit for Bonwood Corp. to
the State for approval. Levine /Colella VOTED: 5 -0.
Notice from Planning Director re: downtown circulation. Board would
like to have discussion on it before taking a vote. On hold until
next week.
Monthly police report. It was asked if convictions could be added to
the report.
Red Sox home game schedule.
Information from MMA re: 22.
Flyer from Universal Badge & Label Co. on campaign buttons.
( * Minutes of February 10, 1982. Approved. Levine /McNair VOTED: 5 -0.
Town Manager's Report
Town Manager noted that Foxboro will be sending down traffic counters in
the spring for School Street study. They also talked about traffic -
counters on 106 because Plainville and Foxboro are discussing widening
106 from Rt. 140 to 152 in Plainville.
Street lights have been looked at and there are currently 3 list to be
collated. The total of lights on all 3 lists is 152. Selectmen Levine
and Colella will be collating the lists. Would like the Town Manager
check into using paint for islands and curbs.
Board Reports
Selectman Colella reported that Arthur Terenzi was contemplating contacting
his lawyer about his driveway.
Selectman Levine asked if a letter had been sent to Foxboro re: perambulating
boundaries which had been done. She also asked about the vendor parking
at the train station. There was a vote by the Board recently to prohibit
vending trucks from parking at the train station. The only problem now is
to establish the metes and bounds of the town owned property. Town Manager
will check on parking regulations for vendors. It was also asked if the
rusty signs might be reconstructed. Selectman Levine also asked if any-
( thing had been done yet on Fruit Street. Town Manager will take care of
this item.
Selectmen Mahana, McNair and May had no reports.
BOARD OF SELECTMEN
MINUTES OF MEETING
FEBRUARY 17, 1982
PAGE 5
Budget Review - Public Works. It was decided to put the budget review
for public works on next's week agenda.
* There being no further business, the meeting adjourned at 11:05 P.M.
Mahana /Levine VOTED: 5 -0.