HomeMy WebLinkAboutPlanning Brd Min_7101996PLANNING BOARD MINUTES f
July 10, 1996
PRESENT: Chairman French, Acting Clerk Dolan P:; "'" I,
PLANNERS: Benda, Flynn, McShane, Penney
Shaun P. Burke, Director of Planning and Development j
1. Meeting called to order at 7:30 P.M.
Motion: To appoint Planner Dolan Acting Clerk .
(McShane - Bonda) All in favor. PASSES
2. Correspondence
1. Minutes June 19, 1996
Motion: To approve the minutes as written
(Dolan- McShane) Four in favor. Bonda Abstained.. PASSES
2. Minutes June 26,1996
Motion: To approve the minutes as written
(Bonda- McShane) All in favor. PASSES
3. ZBA applications
East Street - Mansfield Oil - variance from sideyard setback and to amend the
previous variance requiring landscaping along the frontage
Motion: To send the ZBA a positive recommendation on the sideyard setback
and suggest plantings be required along the frontage except in the area
of the concrete driveway access, as shown on the plan listed as Exhibit
C, provided visibility is not impaired.
(McShane - Flynn) All in favor. PASSES
Old Elm Street - Lavallee - variance from sideyard setback
Motion: To send the ZBA a negative recommendation because the application
substantially derogates from the intent of the zoning by -law, and out of
concern for the neighbors, who assume they have the sideyard setback
protection. (Flynn- Bonda) Three in favor. French and McShane
opposed. PASSES
Park Avenue - Dixon - finding for the addition of a deck and porch, which will
not cause any additional non - conformity.
Motion: To send the ZBA a positive recommendation because the addition will
not cause any additional non - conformity.
(Flynn- Bonda) All in favor. PASSES
4. Letter from Attorney Mangiaratti RE: Eastleigh Estates agreement
5. Letter from Jennifer Crotty, Administrative Secretary, RE: resignation
6. Letter from Shaun Burke RE: Acceptance of Resignation
3. Public Hearing - Sturbridge Estates Sewer Modification
The clerk read the public hearing notice and a memorandum from the Town
Engineer. Ralph Maloon, RIM Engineering, explained the proposal to extend
sewer from Mill Street and East Street easterly along East Street to Cooper
Road and through Sturbridge Estates to the Tara Estates property line. They will
provide service to each house via an easement rather than cut the street.
Mr. Maloon said the town had been concerned the pipe would be big enough to be
extended in the future. He presented a report on the pipe size and a map showing
what could be connected in the future, including Tara Estates, Alchemist Court,
Northridge Estates, and Eastleigh Estates, or 127 lots. He said it was possible a
portion of Tara Estates I, Eastfield, and Massapoag, plus the town -owned land
could be connected, for a total of 278 lots. Mr. Maloon explained there would be
capacity for any existing lots that could be sewered.
Mr. Maloon reminded the board that Mr. Zola had previously requested one
sideline of the road be moved out, but presented an alternate proposal to increase
the radius and maintain the 50 foot road by sliding the road over and creating a
slight bend.
Public Comment
Mark Levine, One Cooper Road, said his view of a nearby business is blocked by
a line of trees and asked if there would be any way to replace that buffer.
Chairman French explained the easement has to be kept open and free of trees.
Mr. Folkman said he would like to meet with the homeowner to get a better idea
of the situation, though he is willing to work something out.
Robert Alexander Bean, 974 East Street, asked if he would have access to the
sewer. Mr. Maloon explained he would, as the developer would be installing it
to the property line, which would be approximately 42 feet from the side of Mr.
Bean's house. Mr. Bean asked why the line couldn't be brought to the front of the
house, making less expensive for him to tie in. Mr. Folkman said they would put
the tie -in wherever he wanted it, but he should consider where his pipes come out
of the house and whether it would be more expensive to rearrange his piping to
come out the front, or to connect from the side.
Mr. Levine asked where the sewer would be hooked up. Mr. Maloon said it
would go directly from the sewer to the house, after the existing septic systems or
cesspools are pumped out, crushed, and filled. Mr. Folkman explained they
would not have to tie into the new sewer immediately, but that would be required
upon conveyance or failure of the septic system.
Paul Frisoli, 20 Shannon Lane, asked how many buildable lots are along the sewer
line, saying he currently has a drainage problem and was concerned more
impervious surface would increase the problem. Mr. Folkman said there are
currently five unbuilt lots in Sturbridge, and explained all the drainage from
Sturbridge goes into that subdivision's drainage area. If the sewer is not
approved, he said three of the unbuilt lots could be built, one was a possibility,
and the last probably could not be, so even without the sewer, three or four of the
unbuilt lots would be built.
Mr. Burke said he thought when the subdivision was permitted, the design
engineer took all the lots into account when doing the drainage calculations, so
tra in g s stem wasldesigned properly Mr.
nd was concerned that paving new areas
drainage Y
would make his problem worse.
Planner Penney arrived at this point
Charles Atchison' Coop
t er Road, asked
i1Taraa, Sturbridge
Mr. Fokm n said that cou dbe done
would be Conn
as early as this fall, but definitely within the next two years. date. Atchison asked
n s at a
if residents a would be
will e to
laterals t to
each house t the time of instal ation.aMr.id
they co the cul -de -sac island; Mr.
Atchison said he and his neighbors had been keeping up
Folkman said he would take a look at that area.
Sean Brumble, 25 Cooper Road, asked about construction impact on Cooper Road
Extension. Mr. Folkman said the roads would be connected with the sewer
stopping at the Sturbridge property line, and at the time of sewer installation, the
binder course for the road connection would be placed.
Board Comment
Planner McShane asked about the cost to connect. Mr. Maloon said that varies,
° depending on the difficulty, b the
would average co L,5ct d Mr Maloon said all the
McShane asked how many houses
houses on Cooper Road, 13 services, would be connected. 13 an ld be connected.
Sturbridge has 29 lots, five of which are unbuilt, but only
Stu ridge a said some houses on East Street and some on the easement route
would be connected.
Planner McShane said if the calculations are done based on Title V, there will be
capacity for 260 homes, but if they are done based on the consultant's design,
there will be capacity for 728 homes. Mr. Maloon said it doesn't have to be that
McShane said his primary
sized for that many. Planner
t the pipe is s
concern is that when sewer is built, there will be additional development, and
many, bu
asked how many of the hobased on the flow calculations built.
from Fthe�an
already es that can connect are
said the numbers are hypothetical percent of the houses that can tie
consultant's report and Title V. He estimated 90
in are already built or permitted, a would if
y be getting one lot that currently Ong
won'tda perk. He won't perk. He said he didn't know about unbdabhat part of town has failing
le lots in other but said the sewer is sized so that if in 10 -15 years,
septic systems, the sewer is already there and sized properly.
Mr. Zola said Stearns Avenue already has sewer, so this won't benefit anything
north of that, leaving the area to the right of Stearns and the existing homes,
so not many can be added. Mr. Maloon added the town -owned land would also
be able to connect.
Mr. Burke said Tara I has one unbuildable lot, Alchemist, Tara II, Northridge, and
Massapoag have none, Eastleigh Estates has four unbuildable lots because of
wetland issues.
Mr. Folkman said they are trying to make their one or two unbuildable lots
buildable, but said this is an area of critical environmental concern in the
watershed, and the town would be getting the sewer put in by someone else. In
10 -20 years, the town could add 200 -250 homes and the capacity will already be
there. Planner McShane asked about current capacity and how much this would
use up. Mr. Folkman said he did not know. Mr. Burke said the capacity
fluctuates depending on the season, there is less during the summer and fall.
Planner McShane asked what would happen to the unbuildable lot if the sewer is
not approved. Mr. Folkman said they would retain it and eventually the town
would extend the sewer.
Mr. Burke said this is an area of critical environmental concern within the Zone II
area, so for environmental reasons, it makes sense to sewer the area. He explained
capacity in the existing town -owned line isn't the issue, since that was sized big
enough when the East Mansfield sewer was done. He said if the developer does
this, the town won't have to do it when the systems eventually fail. With this, the
developer gets one lot, but the town gets good long -range planning. He said the
easement is privately held, so if the town had to do the sewer, it would have to
take the easement by eminent domain.
Mr. Burke said the second issue is the street, saying with Mr. Maloon's proposal,
it starts and ends at the same points it did before, so there has been no big change,
keeping in mind the abutters' concerns about the buffering and the island. He said
if the street is accepted as a public way, the town would also accept the easement.
A resident asked if the town had any plans to bring water to the area. Mr. Burke
said he had heard no discussion of that.
Mr. Levine asked about a timetable for the sewer installation. Mr. Burke said he
thought the board could ask for a construction schedule as a condition of approval,
but it would have to be completed within the two year time frame. Mr. Levine
asked how close to the easement he would be able to build. Mr. Burke explained
it would be the same as now, as long as nothing permanent is placed on the
easement. Mr. Levine asked what the sewer would add to the water bills. Planner
Penney estimated they would double.
( Planner Penney said it had been a Sewer Commissioner policy not to allow
easements across private property, and asked if there would be any way to bring
the sewer in through East Street. Mr. Folkman explained the sewer line comes in
from the back of the Mansfield Meadows apartments, and Mr. Maloon said
coming from East Street would require a lift station.
Planner Penney asked if the eight inch main would handle the 260 homes. Mr.
Maloon said it could potentially handle 700 homes.
Planner McShane asked about the cost of the project. Mr. Zola said there would
be 1,800 to 2,000 feet of sewer line at a cost of about $60,000 to $80,000.
Planner Flynn asked what could be done about the buffering. Mr. Burke
suggested staking the center line of the easement to determine where the pipe will
have to go, then plant around it. He said enough of the easement would have to
be cleared so the equipment can get through for repairs.
Mr. Folkman said he is willing to work with the residents. Mr. Zola said he
thought the residents were more concerned with a visual buffer than with the
noise from the business. Mr. Maloon said he would stake the center line.
Motion: To continue the public hearing to July 17, 1996 at 8:45 P.M.
(Dolan- Flynn) All in favor. PASSES
4. Discussion of Stearns Hill Estates Sewer Modification
Ralph Maloon, RIM Engineering, explained his proposal to modify the plan as
approved because the sewer line was approved at depths of up to 34 feet. He
suggested putting five houses on grinder pumps, with each lot having its own
force main.
Mr. Folkman told the board they had not yet gone to the Sewer Commissioners
with this proposal because the Town Engineer, Lee Azinheira, suggested they
discuss it with the Planning Board first. Mr. Folkman said Mr. Azinheira told him
if the Planning Board was satisfied and the technical issues were worked out, he
would recommend the Sewer Commissioners approval the proposal. Mr.
Folkman said this proposal would allow for easier maintenance than the approved
sewer, which was very deep.
Planner Penney suggested running the force mains in the roadway rather than on
private property. Mr. Maloon said that was no problem. Mr. Zola agreed.
Chairman French noted Clerk Sullivan had wanted individual force mains to a
grinder pump. Mr. Burke said the town would own the force mains unless it
granted the homeowners easements. He added the line is in the middle of the road
at Jameson Court.
( The clerk read a memorandum from the Town Engineer and a letter from Mr.
Maloon. the deep cuts and
Mr. Burke said he agreed with Mr. Azinheira that eliminating
five grinder pumps would be in the town's best interest. deep, , b t the
adding stem gravity and to go
reminded the board that time toldlh m to make thenvhole system deep, butt e
Town Engineer at
as deep as necessary. try to avoid
Planner Penney said this is a good compromise, but asked they
running the lines throug h P rivate property'
orts the concept, and then
Mr. Burke told the board it should decide if it sup
public hearing. Planner Dolan said he liked
Meth the
whether it requires a p
Motion: To support the concept of the modification rasa strip.
relocation of the force main to within the g
(D location of Five in favor. McShane abstained. PASSES
require a public hearing,
Planner Dolan said he and not adding iteorrnisept,vould e as a field
since it is eliminating public hearing and deal with the change
to the board for
Motion: Not to require a p plans be brought
modification. To request the modified
a formal vote- r ie abstained. s
(Flynn- Dolan) Five in favn o erCommi Commissioners for approval'
Mr. Folkman said they would beg o g t the
and a letter from the Planning Board would help.
Planner Penney left at this point.
5. Around the Table
et something in writing from Mr. Kreutzg r
another Master Plan meeting with him. He said he expects
Mr. Burke said he would like tog reed. The board
before scheduling
something within the next few w weeks.
SchootCommittee before that. Mr-
discussed scheduling a meeting for August 13 or 15 with the School
Burke will try to schedule a meeting
Committee.
Copeland Drive. Mr. Burke said that
the Board of Selectmen to sell used cars.
Planner McShane asked about the car lot on oP
site has a Class 11 license issued by ad next to the building, but is the
Planner McShane asked en up about the and is oc a
ated pad West Street. din Burke
explained that has
( only one he knows of in town,
Mr. Burke told the board it would have to do public hearing for the articles it
wants on the Special Town Meeting warrant. The board requested copies of the
draft articles for a discussion on July 17 and a tentative public hearing on August
14. The board discussed other possible articles, including day care and Zone II.
Acting Clerk Dolan asked about the glass at Massapoag Estates. Mr. Burke said
the detention area had been cleaned up and hydroseeded. Acting Clerk asked
about progress on Weaver Lane. Mr. Burke told him Mr. Folkman has been
working on that with the Town Engineer.
Planner Flynn requested Mr. Burke draft articles for discussion to separate day
care businesses, and for a lot size increase in the Zone II. Mr. Burke suggested
doubling the current requirement of 60,000 square feet.
6. Adjournment
Motion: To adjourn at 10:35 P.M. (Dolan- McShane) All in favor. PASSES
Date of next meeting: July 17, 1996 at 7:30 P.M.
Signature of Clerk Date of Approval