1. Meeting called to order at 7:30 P.M.
2. Public Hearing - Special Permit Vicino Buick
The applicant plans to expand his existing facility by
approximately 2,000 square feet.
Department Head Comments
Officer Lance Lawson said the site posed no traffic issues.
The Engineering Department was concerned about the site having
no drainage and about sidewalk improvements.
Mr. Burke was concerned about handicapped parking, lighting,
drainage, traffic flow, parking calculations and the dumpster.
Board Comments
Planner Trombetta asked what the current showroom would be
used for. Mr. Vicino told him mostly office space, and the
addition would be for a new showroom, two handicapped
bathrooms and some storage.
Planner Flynn said she was concerned about the size of the
addition. Architect Gene Racek showed the board a picture of
a two -story addition with a flat roof. Planner Flynn asked if
there would be a traffic flow problem and suggested customers
be encouraged to use the Pratt Street curb cut rather than
Route 106. She also requested the dumpster be completely
screened and the lights be shaded.
Clerk Sullivan asked if the applicant planned to change the
existing curb cuts or signage. Engineer Rick Merriken
answered they would not change any curb cuts and 'would add a
sign to the addition. Mr. Merriken added the roof now has
downspouts for drainage, and the addition would have the same.
Builder Tom Murray said they would be repairing the pavement
in the area, but did not know exactly what would be done.
Chairman McClanahan asked if test pits had been done and was
told they had not. Mr. Murrary said they had discussed that
at the site plan meeting and was told the Engineering
Department would consider allowing a tie -in to town water.
Mr. Merriken suggested they do test holes and have Mr. Burke
witness them. He added there were sandy areas on site and
�. drainage could be relocated if necessary.
Planner French asked if the site would conform to zoning with
the addition and was told it would. He asked what was located
across Chauncy Street. Mr. Vicino explained his body shop and
employee parking were across the street.
Mr. Burke encouraged the applicant to use entrance and exit
signs to help traffic flow, require employees to park across
the street, and discourage on- street parking on Pratt Street.
Motion: To close the public hearing.
(French - Sullivan) All in favor. PASSES.
Motion: To approve the site plan /special permit with the
conditions that the dumpster is fenced, percolation
tests are done prior to the addition to find the best
location for galleys, an alternate galley plan is
developed, a table is provided showing sufficient
parking, the sidewalk is repaired after any
construction, an entrance sign be placed on Chauncy
Street, and the lights are shaded.
(Sullivan- French)
Planner Trombetta - In favor. The plan and conditions are
acceptable.
Planner Flynn -
In favor. The plan adheres to zoning.
Planner Bonda -
Abstaining from vote because of late arrival.
Clerk Sullivan
- In favor. The plan meets zoning requirements
providing the conditions are met. The
Vicinos have always run a good business.
Chairman McClanahan
- In favor. The plan meets zoning
requirements. The building's facelift
will be an asset to the neighborhood.
Planner French
- In favor. The plan and provisions are
satisfactory. PASSES
3. Discussion with Karl Clemmey RE: Woodlot Estates
Ken McKenzie, Dunn - McKenzie Engineering, showed the board a
revised plan showing the potential for Woodlot connecting with
Woodland Park, another subdivision in the preliminary stage.
The plan showed two cul -de -sacs, one wetland crossing, and
more regularly shaped lots. He said the roads lined up well
with minor shifting, but there is a parcel in the middle of
the two subdivisions owned by a third party. Mr. McKenzie
said he could push the cul -de -sacs up to the property line in
anticipation of connecting the two later. The board was in
agreement this was a better plan.
4. Workshop - Subdivision Rules and Regulations
Sight Distance - Planner French had requested applicants
demonstrate how they arrived at their sight distance figure.
Mr. Burke suggested requiring no more than a certain grade
change within the sight distance triangle. Planner French
said the board could make the requirement tough, then waive it
if the circumstances warranted.
The board discussed the ASHTO requirements. There was some
concern about them being outdated, but the question was raised
whether it would be defensible if that were a reason for
denial. Planner French suggested adding more backup
information to support the board's use of a minimum of 300
feet.
Motion: To include sight distance as a revision to the
Subdivision Regulations, adding additional support to
the ASHTO figures.
(Sullivan- Flynn) Five in favor. One opposed.
PASSES.
Roadway Width - The board discussed location of street lights
and street trees. Planner Flynn felt a lighting plan should
come from the Planning Board, not the Electric Department.
Chairman McClanahan said a 20 foot paved width was tight and
suggested 22 feet. Consensus on the board was for a wider
grass strip with either a narrower paved width or a wider
right -of -way.
Motion: To require a 22 foot paved width with a 50 foot right -
of -way and one sidewalk on minor roads.
(French - Flynn) Four in favor. One opposed. One
abstention. PASSES.
Correspondence
1. Minutes of October 19, 1994
Motion: To approve the minutes as written
(French- Sullivan) All in favor. PASSES.
Motion: To approve the Executive Session minutes of
October 19, 1994 as written. (Flynn - Bonda) All in
favor. PASSES.
2. Letter from Dennis Baker, Shamrock Homes RE:
Request for final release Donovan Lane
Motion: To release the final 10% as the road meets all
Planning Board requirements. (Flynn - Sullivan)
All in favor. PASSES.
3. Letter from Ed Marcheselli, Walmark Corp RE:
Request for final release Longwood and Jefferson
Motion: To release the final 10% as the road meets all
Planning Board requirements. (Sullivan- French)
Five in favor. One abstention. PASSES.
4. Letter from Paul Folkman, Folkman & Zola
Builders, Inc. RE: Request for release of all but $2,500
Rosewood Court Motion: To release all remaining funds
except $2,500 as the road meets all Planning Board
requirements. (Sullivan - Bonda) All in favor.
PASSES.
5. Memo from Dan Clifford, Subdivision Inspector
RE: Partial release of bond Maple Hill Estates.
Motion: To approve the release
(Flynn - Bonda) Five in favor. One abstention.
PASSES
6. Memo from Dan Clifford RE: Partial release of
bond Carlton Estates
Motion: To approve the release
(Flynn - Bonda) All in favor. PASSES
7. Memo from Dan Clifford RE: Partial release of bond A
Massapoag Estates
Motion: To approve the release
(French - Trombetta) Five in favor. One abstention.
PASSES
8. Memo from Dan Clifford RE: Partial release of
bond B Massapoag Estates
Motion: To approve the release
( Trombetta- French) Five in favor. One abstention.
PASSES
Memo from Dan Clifford RE: Partial release of
bond D Massapoag Estates
Motion: To approve the release
(McClanahan - Flynn) Five in favor. One
abstention. PASSES
10. ZBA application for variance - American Legion
11
intent
12.
13
- Fruit Street
Motion: For a positive recommendation for a single family
lot.
(French- Flynn) All in favor. PASSES.
ZBA application for variance - David Martin
Motion: For a negative recommendation because the
application substantially derogates from the
of the zoning by -law in lot frontage and width
requirements. (Sullivan - French) All in favor.
PASSES.
ZBA application for variance - Judith Simmons
Motion: For a negative recommendation because the
application substantially derogates from the
intent of the zoning by -law in frontage
requirement. (Sullivan - Flynn) All in favor.
PASSES.
Letter from Attorney Robert Mangiaratti RE:
Hope Street Mansfield Realty Trust vs. Town of Mansfield.
Mr. Burke explained Attorney Mangiaratti brought the
amended agreement to Mr. Baker and Mr. Mahoney, who agreed
as long as their earlier filing fee was credited to this
submission. They will dismiss the suit and come in under
the zoning in effect when they filed the latest plan, in
April 1994.
Motion: To write Attorney Mangiaratti a letter confirming
the board's discussion and agreeing to the above
settlement and conditions. (Flynn - Bonda) All in
favor. PASSES.
Around the Table
Motion: To send the Board of Selectmen a letter with a copy to
the Town Manager informing them of the position the
Planning Board was put in when Town Meeting adjourned
before taking up the street acceptances.
(Flynn - Bonda) All in favor. PASSES.
Planner Sullivan said the detention basin at Cedar Ridge had
come out very nicely.
7. Public Comment
Regarding lot grading, Bill Madan suggested that some towns
require the top of the foundation to be one foot above the
crown of the road.
8. Adjournment
Motion: To adjourn at 11:15 P.M.
(Sullivan- French) All in favor. PASSES.
Date of next meeting: November 16, 1994 at 7:30 P.M.