HomeMy WebLinkAboutPlanning 03/27/2024l%
Pr_'CEIV ED Town of Mansfield
�= o
r 7 {f C!.. u (� C 6 Pak Row, [1lansfeld, YAL4 02048
asaos°� 2OZq Al"R ? i A 8: S5 Planning Board
• err—�r�
Meeting Held in Person in Meeting Room 3A/B and
Virtually Using Go ToWebinar Platform
Present: Joseph Cerretani, Chair; Sharon Friedman, Clerk; Ralph Penney; Michael Feck;
Beth Ashman -Collins; Mark Corsillo; and Sreelatha Allan, Associate
Sarah Raposa, Director of Planning & Development
Priscilla McGill, Administrative Secretary
Absent: Michael McClanahan and James Turnbull, Associate
Mr. Cerretani read the meeting's introductory remarks.
Present for the application presentation were:
Mike Ahern -Town of Mansfield Project Manager
Doug Annino- Municipal Building Committee Chairman
John Fasano- Architect, BH+A
Tony Donato- Engineer, Hancock Associates
Mr. Ahern explained that the team was before the Planning Board to get their thoughts and
suggestions on the proposal for 50 West Street and to partner with the Board for the final design
concepts and the site. I-Ie said that the site was formally the police station and has been vacant
since 2019 and presently serves as a communications structure for the Town's radio and fire
alarm infrastructure. The site is comprised of fill and some unsuitable soils in the rear of the
property which will need to be managed with DEP involvement.
Mr. Ahern and the team then reviewed the presentation as follows:
1. Existing Site
Aerial pictures showing connections to downtown, Bike Path, Town Hall, and Fulton's
Pond
Planning Board Meeting Minutes 3/27/24 Page 1 of 7
Site Rendering
• Existing building on site (old Police Station) is about 12,500 square feet and the
footprint of the new building is about 7,500 square feet
• Existing COA area is 6,000 square feet and the new building is proposed at 15,000
square feet
3. Site Plan
• .2-mile circuit trail path
• Pedestrian signal at West Sheet in front of the site to cross to Fulton's Pond
Connection
• Boat Dock, Shuffle Board Court, Bocce Court, Pickle Ball Court
• Electric Charging Stations (approximately 6)
• Parking Spaces- (Approx. 87 spaces)
Overall Grading and Site Drainage (no net increase)
• Pre vs Post Imperviousness Area
• Existing-- 57,948
• Post— 57,588
• Net decrease of 363 square feet
4. Overall wetlands onsite
• River Bank stabilization on the westerly side (this may be a separate permitting
process)
• Knot Weed invasive species removal from a couple of areas on the site (this is being
worked on with the Conservation Conunission as a test location along with DEP)
Mr. Donato explained the preliminary proposed renderings and briefly explained the water
retention and discharge systems. He spoke about the wetlands at the Rumford River, floodplain,
new plantings, pedestrian walk around the site, the site being ADA accessible, proposed
pickleball courts, additional amenities, covered outdoor seating, and the location of the building
and parking.
Mr. Fasano spoke about the exterior renderings, the mechanicals being placed in the attic, the
roof being sloped, and multiple exterior materials to visually minimize the scale of the building.
Bollards will be placed at the front entry for safety. Ms. Friedman suggested fencing in lieu of
bollards. When the project is ready there would be a Site Plan submission to the Planning Board.
Mr. Cerretani noted that this is part of the Master Plan priorities for multi -generational use.
Mr. Ahern said that it would be 25% more expensive to update the existing building as opposed
to the new proposed option. The design also includes a small kitchen and multi -purpose rooms.
He noted that they conducted an online survey of the Town seniors for their input on facility
activities.
Planning Board Meeting Minutes 3/27/24 Page 2 of 7
Ms. Allam asked if they would conduct a traffic study. Mr. Ahern said that it would be included
in the site plan criteria. They explained the onsite traffic flow and that the pedestrian crossing
should align with the existing crossing.
Ms. Aslnnan-Collins asked if there was consideration for adding a floor to accommodate senior
housing. Mr. Amnino answered that the site would most likely not support that.
Ms. Friedman suggested fewer parking spaces since there are additional parking options around
Town.
Mr. Ahern said that the next steps would be to prepare construction and bidding documents. The
Town is currently seeking grant funding for the project.
The JM Goldson team present for the meeting were: Laura Smead, Noah Harper, Flavin Villa
Ms. Smead began the Mansfield MSROD Expansion update presentation. She reviewed the
meeting agenda and project schedule noting the completion of the community engagement phase
and they are now working on the buildout and fiscal impact analysis for the April 10°i meeting.
Mr. Cerretani asked what would be considered for the fiscal impact analysis. Ms. Smead replied
that they would be looking at the assessed value, estimated number of residents, and estimated
footage of commercial and residential space. Then look at the projections based on the buildout
analysis results. They will also include the impact on the schools and Town services such as fire
and police.
Ms. Smead reviewed the in -person 2/28/24 forum results relating to the demographics of
participants, their interests, housing density, streetscapes, and outdoor dining. The participants
were generally in favor of presented zoning strategies.
Mr. Villa then discussed the buildout analysis for the MSROD zoning district. He presented
three scenarios using GIS models for each dimensional requirement.
• By right residential scenario
• By right mixed -use scenario
• Special permit incentive 3 scenario
The scenarios considered existing uses, environmental constraints, and dimensional
requirements. Mr. Villa reviewed each scenario's results for the number of multi -family units,
affordable units, mixed -use commercial uses, and special permit incentives. Ms. Smead noted
that the affordable units are not a direct ten percent of the overall build -out number because they
calculated parcel by parcel and not all the parcels are capable of generating affordable units.
Mr. Villa then explained the test fits and case study parcels incorporating items such as the
number of units and parking. He then presented test fit interface software results depicting visual
architectural designs for each scenario. They also presented visual designs for the existing
Planning Board Meeting Minutes 3/27/24 Page 3 of 7
MSROD "A" and the MSROD Expansion "C". The presented images are not plaimed, but only
for visual purposes of the case study exercise.
Ms. Smead said that areas with significant environmental constraints were not included in the
calculations.
Mr. Harper explained the economic feasibility analysis for a simple real estate pro forma looking
at cost and income assumptions for development. The team modeled test fit scenarios for the
contemplated districts looking at base zoning, mixed -use, and full -incentive builds, where
applicable. Interest rates and construction costs are considered and every tenth unit is affordable
(10% inclusionary). Modeling scenarios considered varied bedroom mixes, tested lower interest
rates, and the team then created alternate scenarios with cost savings. Mr. Harper reviewed the
draft results and observations. He noted that the incentives are not good in the sense that a
developer would build by right or mixed -use tier because the incentives are too expensive.
Mr. Harper said the next steps would be to refine the scenarios and adjust assumptions based on
the test fits and build out analysis.
Ms. Smead then reviewed the next steps:
April
• Summarize digital platform results
• Fiscal impact analysis,
• Public hearing on MSROD extension
• Revising and refining build -outs, test -fits, and market analysis
• Design guidelines draft
May
• Town meeting on MSROD extension
• Finalize design guidelines
• Drafting zoning templates for future development areas and housing strategies
Ms. Smead added that relating to the market feasibility analysis, the assumption is that someone
is going to have to buy the land, which is very expensive in Massachusetts. Not many people
who own land can develop it themselves. If there were a scenario where someone did own the
land and could develop or partner with a developer it could open the feasibility a bit. There are
envhournental, infrastructure, and cost constraints that are out of the control of the town.
Mr. Penney suggested that increased rents, purchase prices, and reduced interest rates should be
taken into consideration.
Discussion ensued relating to increased construction costs, and rising housing and rental prices.
Future building will result in increased property values and there was hope for lower interest
rates and building costs.
Ms. Raposa explained the expansion areas including the subdistricts would bring the Town over
the total unit requirement. The next presentation will be at the April 10" meeting.
Planning Board Meeting Minutes 3/27/24 Page 4 of 7
Ms. Raposa reviewed the six (6) proposed amendments for the Town Meeting.
• Item 1 (Warrant Article 13): Amend Recreational Facilities Definition (§230-3.2.D) - to update
the definition to provide clarity on allowable recreational uses.
• Item 2 (Warrant Article 14): MSROD Phase H (§230-5.12 and Zoning Map) - to amend the
Mansfield Station Revitalization Overlay District (MSROD) district to extend along the west side
of Oakland Street to the Chocolate Factory (east side of railroad tracks).
• Item 3 (Warrant Article 15): Special Permit/Site Plan Approval Recommendation (§230-
5.5G) - to delete this section entirely as it is an outdated practice.
• Item 4 (Warrant Article 16): Zoning Board of Appeals Appointments (§230-7.2) - to make
the terms for associate members of the Zoning Board of Appeals (ZBA) consistent with the
ZBA's charter under the Town Code Section 5.4.
• Item 5 (Warrant Article 17): Special Permit for Open Space Percentage Relief (§230-4.10) -
to add a dimensional special permit to be issued by the Planning Board to provide flexibility for
reuse/expansion of PBD and Industrially zoned land.
• Item 6 (Warrant Article 18): Add B4 Zoning District to Sign Bylaw (§230-4.7) - to correct an
oversight during the adoption of the B4 zoning district at ATM 20 M
The Planning Board would have the ability to update the items during the public hearing.
Ms. Raposa told the Board that Item 2 for MSROD Phase II was submitted to the Attorney
General's Office for pre -review. The Attorney General's office did not have continents on the
proposal but offered comments on the proposal that was approved last year relating to the
performance standards of the site plan approval process. Relating to potential four to six -story
multi -family developments that would not be in character with adjacent neighborhoods, the
Attorney General's office noted that this may raise future issues with the Fair Housing Act.
Ms. Raposa said that the draft compliance model was sent to the State in February and it is
currently being reviewed, but it could take up to ninety days from the original request for the
State to reply.
Mr. Cerretani said that the next meeting would focus on MSROD Phase II. Ms. Raposa said
that FinCom has been invited to participate in the public hearing process.
Ms. Raposa gave a brief discussion on what has not been reviewed yet, mainly the surrounding
towns' comparison fees and engineering peer review. After a brief discussion of fee
comparisons, the Board decided to review the fees at a firture meeting.
Planning Board Meeting Minutes 3/27/24 Page 5 of 7
There was a brief review of deadlines for application submission and submission of additional
material before Planning Board meetings and allowing the presentation of new material by an
applicant at the hearing.
Motion to continue the hearing to April 10, 2024, at 7:15 pin. (Penney/Corsillo)
Seven (7) in favor, Zero (0) opposed, Zero (0) abstained PASSES
Mr. Cerretani expressed that he thought that it was a good meeting and productive. The
presentation was well done and there were good public and Board comments. Mr. Cerretani
recommended that the Board gather connnents into writing to present to the TOD team for
design consideration.
Mr. Corsillo expressed concern about traffic back up to the railroad tracks at the proposed rotary
design.
Ms. Friedman noted business owner concerns about slower business during the construction
process.
Planning Board Meeting Minutes:
January 24, 2023
Motion to approve the minutes as presented (/Corsillo/Feck)
Six (6) in favor, Zero (0) opposed, Zero (0) abstained PASSES
February 14, 2024
Motion to approve the minutes as presented and amended (Feck/Ashrnan-Collins)
Five (5) in favor, Zero (0) opposed, One (1) abstained PASSES
February 28, 2024
Motion to approve the minutes as presented (Feck/Ashman-Collins)
Five (5) in favor, Zero (0) opposed, One (1) abstained PASSES
March 20, 2024
Motion to approve the minutes as presented (Feck/Friedman)
Six (6) in favor, Zero (0) opposed, Zero (0) abstained PASSES
Planning Board Meeting Minutes 3/27/24 Page 6 of 7
Ms. Ashman -Collins and Ms. Friedman noted that they attended CPTC sessions.
Ms. Friedman attended the firearms session and said that she would submit a summary of the
session to Ms. Raposa.
Motion to adjourn at 9:23: pm (Pemiey/Corsillo)
Seven (7) in favor, Zero (0) opposed, Zero (0) abstained PASSES
The date of the Next Planning Board Meeting is April 10, 2024 at 7: 00 p. m.
SharonFriedman, Clerk
Documents Presented at the Meetin
A. 24.2o Z 4--
Date of Approval
1. Sarah Raposa, Director of Planning and Development meeting memo dated 3/27/24
2. 50 West Street Proposed Plans and Drawings for new COA building
3. Mansfield MSROD Expansion Update Presentation by JM Goldson dated 3/27/24
4. Notice of Planning Board Hearing Relative to Proposed Zoning Bylaws Amendments
distributed 3/19/24 for public hearing date 4/10/24
5. Revised draft Policies & Procedures of the Planning board with Site Plan Approval and
Special Permit Rules and Regulations dated 3/27/24
6. Draft Minutes for January 24, 2024, February 14, February 28, 2024, and March 20, 2024
Planning Board Meeting Minutes 3/27/24 Page 7 of 7