HomeMy WebLinkAboutPermit Approval - 11/25/1998COMMONWEALTH OF MASSACHUSETTS
EXECUTIVE OFFICE OF ENVIRONMENTAL AFFAIRS
DEPARTMENT OF ENVIRONMENTAL PROTECTION
SOUTHEAST REGIONAL OFFICE
ARGEO PAUL CELLUCCI
Governor
November 25, 1998
Mr. John Dagostino
Town Manager
Mansfield Board of Selectmen
Town Hall
50 West Street
Mansfield, Massachusetts 02048
RE: PERMIT APPROVAL WITH CONDITIONS
Application for: BWPSWII
LANDFILL MAJOR MODIFICATION
POST -CLOSURE MONITORING PLAN LANDFILL GAS MONITORING. WELL. INSTALLATION PLAN
AT: Mansfield Municipal Landfill
East St/Rte 106
Mansfield, MA
Transmittal Number: 97779
Dear Mr. Dagostino:
TRUDY CORE
Secretary
DAVID B. STRUHS
Commissioner
The Department of Environmental Protection, Solid Waste Management
Section, (the "Department") has completed its review of a proposed landfill
gas monitoring well installation program for the Mansfield municipal landfill
(the "Landfill") located off East Street and found that it is technically
complete. The Department reviewed the gas well installation program pursuant
to 310 CMR 19.000 Solid Waste Management Regulations and the Department's
Landfill technical guidance manual (the "Manual"). The proposed program was
submitted by Camp Dresser and McKee Inc. ("CDM"), on your behalf. The
Department approves of the proposal subject to the conditions herein.
Background
On June 1, 1998 the Department issued an approval of the Landfill Major
Modification permit application regarding the Post -Closure Monitoring Plan for
the Landfill. .Pursuant to'condition 8 of that approval, CDM submitted
correspondence: on September 3, 1998, detailing a proposed landfill soil gas
survey. On September 15, 1998, CDM notified the Department of exceedances of
25 per cent of the Lower Explosive Limit (LEL) at the property boundary
20 Riverside Drive • Lakeville, Massachusetts 02347 • FAX (508) 947-6557 • Telephone (508) 946-2700
This information is available in alternate format by calling our ADA Coordinator at (617) 574-6872.
DEP on the World Wide Web: http://% w .magnet.state.ma.us/dep
ry
Ca Printed on Recycled Paper
2
detected on September 11, 1998 and proposed an additional soil gas probe
investigation. On September 23, 1998, CDM submitted a formal report with the
results of the September 11, 1998 field work.
On November 2, 1998, CDM submitted the results of field work performed
on September 17th and 24th, 1998. The results indicated that landfill gas had
migrated northward form the Landfill towards East Street and Landfill gas was
present at the southern edge of East Street. Results further indicated that
landfill gas was not located in a nearby manhole, nearby catchbasins, or a
surface drainage pipe.
Proposal
Based on the survey results to date, CDM proposes the following:
1) The installation of four (4) permanent gas monitoring wells near the
northern Landfill property boundary along East Street, at an
approximate 100 foot spacing,
2) The installation of the four wells within 30 days of the Department's
approval,
3) The utilization of soil gas probes every 500 feet along the landfill
eastern, southern and western property boundaries,
4) The investigation of the vertical extent of landfill gas withinthe
soil during permanent well installation, and,
5) The determination of appropriate corrective actions based on the
results of a landfill gas survey performed during permanent well
installation.
Approval
The Department has reviewed the above -referenced proposal and in accordance
with the authority granted pursuant to M.G.L. c.11l, s150A and 310 CMR 19.000
hereby approves of the Landfill Gas Well Installation Plan and Landfill Gas
Survey Plan subject to the following conditions:
1. The permanent probes shall be installed in accordance with the proposed
detail.
2. During the construction process odors, dust, erosion, noise and other
nuisance conditions shall be kept to a minimum. In the event a nuisance
condition exists, abatement measures shall be implemented immediately.
3. Within 30 days of completion of the gas monitoring well installation, a
construction certification report shall be submitted that includes: as
built drawings of the gas well locations and construction. Additionally,
quality assurance /quality control data and written certification that the
construction was performed in accordance with the Department's regulations,
requirements, the Manual and the approved design shall be provided in
accordance with 310 CMR 19.151(4).
4. During monitoring well construction, the Town must further investigate the
vertical extent of the soil gas. The Town must determine the appropriate
corrective action to mitigate the offsite subsurface migration of landfill
gas and submit a Corrective Action Design application (BWPSW25) detailing
the proposed mitigative action.
5. In the interim, the Town shall take all actions necessary to ensure public
health and safety due to the off -site landfill gas migration including but
not limited to:
a) Notification to the Board of Selectmen, Board of Health, Department of
Public Works, Fire Chief, Building Inspector and any other appropriate
Board or town official and all entities which have utilities on or under
East Street of the status of landfill gas migration and continuing
investigation efforts.
b) All potentially affected buildings shall be monitored on a quarterly
basis, at a minimum.
c) Wherever, there are penetrations of the building foundation, the area in
the immediate vicinity should be screened for combustible gases.
d) All confined spaces within all buildings should be screened for
combustible gases.
e) If at any time monitoring detects the presence of any combustible gases
at, or in excess of, 10% of the Lower Explosive Limit at any location
within the buildings or within any utility conduits on -site or off -site,
the Town shall notify the Department's Bureau of Waste Site Cleanup -
Emergency Response Section within two (2) hours of the exceedance as per
310 CMR 40.0321(1)(a) of the regulations.
Upon.installation of the permanent gas monitoring system, gas monitoring
(using wells and probes) must be performed quarterly pursuant to 310 CMR
19.132(40(b), until otherwise approved by the Department. As recommended in
the Manual, one quarter should be during .the winter when the ground is
frozen. Where soil gas probes are utilized between the landfill and
residential areas, the probe spacing should be 100 feet unless it can be
demonstrated that exposed groundwater or wetlands are located between the.
landfill and any structures.
7. The Townmust undertake all actions necessary to protect public health and
safety. It is the Town's responsibility to comply with all other applicable
federal, state, and local statutes and regulations as a prerequisite to
conducting assessment work at the Landfill.
This Approval has been issued pursuant to M.G.L., Chapter 111, Section
150A. Any person or persons who are aggrieved by this action may appeal
pursuant to Chapter 30A. An appeal must be commenced no later than thirty
(30) days from the date of this Approval. Notice of an action or proceeding
to appeal shall be served on the Department upon the commencement of the
Appeal. In the event of an Appeal, the Department reserves the right to
reopen the permit proceedings, supplement the record and modify the permit.
In addition, the Department reserves the right to require additional
assessment or action as deemed necessary in order to protect and maintain the
environment free from objectionable nuisances, dangers and/or threats to
public health.
This information is available in alternate format by calling our ADA
Coordinator at (617) 574-6872. Should you have any questions regarding the
above points, or if you need additional information, please contact me at
(508) 946-2884 or Dan Connick at (508) 946-2833 or write to he letterhead
address. Please refer to Transmittal #97779 in any corres ondence to this
office regarding this Approval.
Solid Waste
E/DC/re
ion
4
cc: Mansfield Town Board of Health
Town Hall
50 West Street
Mansfield, MA 02048
ATTN: Mr. Scott Liete
Mansfield Town Engineer
Town Hall
50 West Street
Mansfield, MA 02048
ATTN: Mr. Lee Azinheira
Camp Dresser & McKee
10 Cambridge Center
Cambridge, MA 02142
ATTN: Mr. Richard Spieler
DEP - Boston
ATTN: J. Doucett