HomeMy WebLinkAboutCapital 5 Year Plan FY 2020-2025DEFINITIONS0 WIN The following are the four capital project classifications and their respective definition. Each proposed capital project contained in the CAPITAL IMPROVEMENTS PROGRAM — FISCAL YEARS 2020-2025 is assigned a classification. URGENT: An URGENT project is one that would address a situation which could impose a hazard to life, safety, or cause disruption of a vital service if not carried —out immediately. A project will also be considered URGENT if it is required for immediate compliance with any town, state, and/or federal regulation(s). This would have to be an FY 2020 project. PRIORITY 1: A PRIORITY 1 project is one that would address a situation, which, if deferred, could become a financial burden resulting from increasing maintenance expenses, severely reduce service delivery, or increasingly pose a public safety hazard such as deteriorated road, sidewalk or bridge conditions, unsafe municipal buildings, or other similar physical deterioration. This would typically be an FY 2020 or 2021 project. PRIORITY 2: A PRIORITY 2 project is one that constitutes a preventive/maintenance measure which if not undertaken as scheduled, could lead to physical deterioration, curtail economies of operation, pose a significant economic hardship or a downgrade in service. Examples include repairs, renovations or construction of facilities that, if postponed, could hamper program activities and service delivery and potentially lead to a PRIORITY 1 project. This would typically be an FY 2021, 2022 or 2023 project. PRIORITY 3: A PRIORITY 3 project is one that can be deferred or which anticipates long—range town development. Examples include, but are not limited to, projects which will provide a higher level of service, improve existing operations, enhance efficiency or productivity, or ensure that the delivery of services and performance of daily departmental operations will, in the future, generally reflect modern standards, methods, and concepts. Projects could include (a) land acquisition, (b) road or infrastructure expansion, (c) building replacement, or (d) advance planning for capital projects. This would typically be an FY 2025 project (or beyond). 0 0 0 0 0 0 00000§ O O o 0 0p 000000 000000 O O O O o o L1 ut VT LT OOo OO0 00000LLOOLONOv0OOMM �ya 00000 Ow w OOMM mN olrook o -1 is m o 0 0 0 of of m Y M M t0 V1 d 0 n M d I� N � N 00 Y ut n N O O M m O M M N N VT W N VI CO N O d h N O N M N VI W m VT i/! V/T LT N N l/f N 0 0 0 0 0 0 O O O O O p 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 UT VT VT V1 O O O O V1 VT VY O VT V} V1 O v/T O VT Vl O O LT O VF O VT N L} O O O O O O O O O tD N O O N u1 u1 O Vi N O O O M M y tp t0 l� m of O O O m m O O ,,, vT vT vT oo m m m UT LT VT h 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 a0 0 0 0 0 V) V) L} LT LT N r/4 00 LT V1 V/! O +A Vf OO OO i/T OO vi Li OO OO N OO V1 VF O � O d a O (V �1 L6 Ci if V O e0 00 O O O YN L} N m 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 rl N VT VT V1 O O Uf O uT VF V} O of VI O O V} O N L} O O UT O O O v/1 O LT O N O O O O ut O VI O O O O O O O � N 1l1 O O 1� i(1 N ci o0 Oi O O O O O M tO t0 M M N N M ti n 00 M vt O O ut O N N u> L} V1 O O LT O L1 VT O O LT VT O LT LT i/T LT N O VT O LT O LT U} O O 0 0 O O O O O O O O O O O 00 00 yNy O ed V1 V! '.j rl N N LT N Li N rl N N N y 00 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 00 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 O O O O O op U} h N N LT LT O O VT VT LT O VT N O L1 V/T O VF VF O N VT O � LT O VT Vf O m O O O O O O O m O O O LL O O O N VI O O LL O O O �N N � N N LaT N VN LSF N N N LL VT N N u N N OO 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 a) 0 0 0 0 0 0 C V} V} L? VT U} VT LT 00 L} VY OO 00 i/T V} VT OO LT 00 N VT 't/T VT N LT ` VT 00 ur ut N 00 N M M O O ut F 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 O O O O ul VI W O vml umf W ur VI i/1 O� Dc. C N N N N N J m m m m m C 00 a t m a C dA a C m a WE F C m a a r a L Y a Y 41 Y a C ?0 C � E a Y C L a r o.Y t °'•' o.Y as t? u1 a s a E a i a 0 E a 5 a 0 E a p > > O E = p 9 a m 0 E p p p > W W W W 6 W d u K 6 6 6 K y W W O. J N LL Z ~ a 3 aQ � LL Z a O a o � Z W VI N bD N a) cV1 a N N a C G m m c c a a a a p LL LL p p 0 0 0 0 0 0 O O O O o 0 0 0 0 0 0 0 0 0 0 0 0 0 N O o 0 0 V1 111 O L} N 0 0 0 V} V} O O O O VT 'V1 LT L! lR iA VT N N O V/T O M O O O O M M N N N O O N O O O O O O N N N O O w N N A M O tO O1 l0 111 O N VI V1 M m ry O M N N h tO a N f\ 00 N 1I1 N 1� O N M N N N N N O N tO V l0 O w l!1 01 N M M �/T � W~ N M N N h 00 L} Vi �A Vf VT N 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 C 0 0 0 0 0 0 VT VT VT VT VT 1A VF VF V! U} 00 Oo VF N V} N VT N iA N In LT Ll i? O O O O b t00 N � O O M O V1 O m 111 M �y O O tip Y�y fy Vhf n N N O b M M O1 111 t/1 � M Ol Vf N v? N vF N V1 v/T V} VT 00 Oo LT v1 Vf LT 00 Oo v' UT v' VS VF N vF N VT Vf N N � O O O O � a O N O O O O 00 N 111 O Iri O W T Ol O O N Y N V 10 Ol N LT iA OO Ol LL Vf M VT a Ol N N O1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 O 0 0 0 0 0 0 ei N a/f +/T VT O O V! V' v1 v' O O of VI Vi N N N v1 N N V} N VT O 0 0 0 0 0 0 N O O OO H 0 0 vt O O M O O O C) t0 O O OD M VI 1p O M Ol QI O O N M 111 M N 01 I11 V1 M N L} N O O N N a V1 N N P N 1 iNA N O m 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 O O O 0 0 0 0 Vf Vf N N 00 Oo VT vT N N 00 Oo V} VT vT N V1 V! V� L} LT Vf VT N O O O O O O N W W O C V O O ti tom- yNy IIO 1Yy t/1 +A O O 1!1 iy I� ti to N N N N le 111 Lf V' LT h N N y m 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 O m O O O O O O p, C N L} N 00 t/� 00 N i/T VT VT VT N N VI} VT VT VT N VT N N VT iA i? N C i/f O N OO Q M 111 O ri N N H � N 1^11 OM1 W N IA LL N �y v' iA 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 O O O O O O 0 0 0 0 0 0 — O LF N Vf A o O O O O O O 0 0 0 0 0 0 0 LL to O1 of lO O tD N V1 O LL 111 O ri M T O � N V O v1 W O 00 N N 00 � d' N o0 N O 00 M N d' N O O N N eY yNy d' N .-1 Lf M ei VT N V! lA N m O O O O O O 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 o m O O O O O O C U} V} N UT V} V? to to v/> V1 +/! V! N VT VT VF N N SIV Vl iA O 1/T O OC N O � O O O O O N H Lr� M N V m N 1- 000000 000000 000000 u1 In _000000 _0000vl M W 10 N O N 0 0 0 N N o o M 111 LL 00 O W Vf O of N W o e0 0 v1 O1 N ly O W O1 1� N r N b W O v1 m M a O Ou N N N K VNT R .V a-IF/� — — Ca G M jp jp N C a« m cs a nt E avt m E mv= 0 y,yv= as c w O O O m 3 0 O w 5 O w 7 K m J W a M i IY m m i W O. m> W w M W Yd 1y-1 N N W Q 12 LL Q W d J � Z ~ a 14 aQ U� LD O O N 111 Z kv a W a « v 3 1°- r w - w m m T T c c — 0 U V 0 0. o a O�o 0 0 0 o o o 0 o o 0 0 0 O O W O u O M VF N N N h O O N O O O O O m �0 0 o0 m C a O H O O a N O O O N M O N a _y d O pdp Y N a l0y !- O Vf w m O V m H V O M N O O O d C4 ~ 4 N M L~f N N v! Vt 0 0 0 0 0 0 0 O 0 0 0 0 0 0 0 0 0 0 0 0 0 0� 0 0� �A VT LT V� N N t00 O O O� O O N Lr 00 0 o M N O O N O O O M M N ON N V NV fr W W VNT N I� Ol N N 0 0 0 0 0 0 0 O 0 0 0 0 0 0 0 0 0 0 0 0 0 0 N C tayV 0 O O dY. O O O O dd d O ya W O N ON M N 4 O~f LL N 1�. N N M VT N Vf rj N L! Vf N lA N 0 0 0 0 0 0 0 O 0 0 0 0 0 0 0 0 0 0 0 0 eMi O O vT O O Vf O V' V! Li N v! O O V! 0 0 0 VT O N O M O O N O O O O O O � O 00 O 00 to O O O O O O N N N N H w O N 0 0 0 0 0 0 0 O 0 0 0 0 0 0 0 0 0 0 0 0 O O VT O O VV O �A vF N Vf N O O V' of 0 0 0 0 O O O O O O O O O O O n O a0 ei O O O O O O yNy }ry} }ryY tart ut 00f VT rn N y 00 0 0 0 0 0 0 0 O m 0 0 0 0 0 0 a1 0 0 0 0 0 0 tr C O O N O O lA 0 L! C N V1 V1 to O O C N N L! O O O Q O Vl O O M O O '- O O O N N N N M N N N N �"� m N N IY IL 0 0 0 0 0 0 0 O 0 0 0 0 0 0 O O O O O O Lf 00 t/1 a/} Lf 00 00 vA � N VT LT N 00 00 � N N 00 N VF 00 O O N v0f N N Vf h 0 0 o m o 0 0 0 0 0 0 a vim opo vi $ dg n 0000 O M� M N lN0 O N N O N +N/i ti N gLL � H LL LL a - i-- o o m o 0 o M o 0 0 0 0 0 0 0 0 0 0 0 0 ON m 0 4fl LLyy N O N w O }LL N im/T ia/1 M LL LL J d m jp d N jp U Yii 'O v L p, L a a d d d a N cii a o 0 0 o n n d o m e m N LL O 10 O4 C L W- (7 1 Z V Z U Z C O Z F> m LL u LL 00 O L Wil Q w VI QJQ K O LL Q J K O Z W W ~ Z C d W d N a3 a3 3 0 c c o 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 o m m o 0 0 o m ao 0 a H H N O O m m N N O 1p N N N Ol 10 o NN aOmp r« r r NOOO 6 4M� '6VM+1 vlaV a N 06 N M N N N N M Ill N N N N N N 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 N N N N N N N N N N N N N N N N N N 0 0 0 0 0 0 N�y O O O tp O t0 yN � O N V1 1� O ilt ll1 N N l0 M N of N N a N N N N 0 0 0 0 0 0 0 0 0 0 0 0 O O O O N N O O O O N N N N N N N N N N N N N N N N O N e 0 W N O O O W 0 0 O N N O O O N N tl. ry M h O N t0 N I� N N N N {N/F LWT L al 000000 000000 0000 010 0000aw N O Ill N O O O vl O \ O V1 N 0 0 0 a0 ttf O N O M M M Ill N V O h tll M CT M N N N m \ m T LL } LI. N .ti N vLr t 1 .ti N a ei N 0 0 0 0 0 0 0 0 0 0 0 0 O O O O u1 VI O O O O vt N N N N N N N N N N N N N N N O N N N N O O O N N O tp !D O O O t0 O V OO1 06 6 epi IY M 00 1 N h V 00 h ari 00 00 N N N N N 7. y 00 C 0 NNNNN 0 0 0 0 0 N UD � 0 NNNNNN 0 0 0 0 0 00 C 0 NN 0 0 0 N 0 0 0 N 0 0 0 0 0 G O v01 IOII O V O toll O M VI N o rl v ( oM uoi uNi LL 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 LL N N N N N N LL N N N N N N N N N N N N 0 0 0 0 0 0 LL 0 0 0 0 0 0 Oi O N N M m M N N N O 1l1 M N N N 00 0 0 0 0 0 0 00 0 0 0 0 0 0 b0 0 0 0 0 0 0 0 0 0 0 0 0 'a 'ca •a o 0 00 00000 N N N o o vi vi ui o o vi o N N O N rNi d' m m O N 2 LMT �miT r Z 0 N 0 N 0 N 0 N 0 N 0 N 0 N 0 N 0 N 0 N 0 N 0 N 0 N 0 N 0 N 0 N 0 N 0 N 0 0 O 0 N o n m N O m wO O O W pN N N y' N J m N N m VI m m N m N « m S u E m« m 5 u E m r .9.S 'N u E m °^ 'N F_ u E m H N N 'O a y C N VI 9 p, y C N V �, y C V.2 2, L '� m� O m = p '5 W� O m p '� m 0 i P E m m C E m O' c W N K W m K W N W V GC a a Ul a o a O W_ V' Z r m N J J F 0 0 0 0 0 0 w 0 0 0 0 0 0 a O .-i ut O ti N m Vel 7 M LLtJ O 0 j a a a I^it V V = V 3 W r y W E o o E m `m E v v y Q Q a 3 m m @ 0 o c In o c� M o 00 m 0 0 0 0 0 0 0 O o 0 0 M �n o O o 0 0 m ; m m M o O 0 O o D m m o OO 0 0 Np 0 O 0 O 0 O 0 N 0 0 0 0 0 0 0 0 m Y1 m m o O 0 N 0 O 0 O o N M n m n crz c N O O O mO V Q 0 ��/1 m n O� N N w �N-1 vel b O N eQi epi W VY N Uf L} N N V1 N VF N ry" 'M N ri nj h N N N Q` N N N N N N N N N N N H H N N W O O O o0 0 0 O O O O O O O O O O O O O O 00 O O 0 O 0 O 0 O O O O o O O 0m 0 0M O O OOVn1D1 O OO1 O O ' O 0 Vf 0 m o M ei i/F N N M 0 O O M M o 0 0 M LT VI �? N Vr �I1 Y1 O O Y1 m O n n O N M M N N M M N N N N Ymf W 01 Of Oi Of V1 Of m W N N N N H N Vf M M N M N N {IF N 0 0 0 0 N �0 N N H N 00 0 O O O O O O O O O O O O O O O 00 O O O O O O NO O O N O o O 0 O 0 O N O N O O LI N 1A O N O O O O M O •'I O e'1 O rl M Vl 1/1 'I 1/1 rl N IG m M b VF N N N 1A Lf N N N 1/! N O O O O O O O O O O O O O O O O O O o O m 0 0 0 0 0 0 0 O O O O M O O O O m M m m O O O O O O M M 0 O 0 O 0 N 0 O 0 O 0 O 0 N O O O O O O O O M M O N O O O O O N M n 01 O O O 01 O O' M' O' O O 06 O O' V1 VI N O lU' O tp 06 v1 .4 O ei OO M vt YI 0p o M Q M Q to vt e4 N N 1A m O' 1/t e -I N O N V! M VT N N N N N +A tR V! iM1 ry V! v/T N Q^ N yQ N N U` c w o o a 'm m m m Y .� ; 'S « v « a c0� c m u u E E o T3 m E E c U O ins Z m U c w p p a w w\ U m E m m N E m m m d 0= F 0 n N o a F v Y 3 f F m h N n m v v E c m U° c a c e aR h oci o h c m v m c m Y m 3\�N E E E UL° c m o m U o m p 0 0 E Y^ > a c o c o N y o 0 i N C VI iY Z N 1L N C c E e 3y `w Nerd rA SA DEPARTMENT: Mansfield Schools PROJECT LOCATION: iDistrict-Wide PROJECT: iPaving and Concrete work I PRIORITY: Urgent DESCRIPTION: (Project Overview: ,This capital request is for paving sidewalks and roadways within the district. FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: A cs: Over 25,000 Square Feet Lots: Over 125,000 Square Feet fhe paving will be a combination of Mill and Over lay, and full depth mill. The asphalt vill be per the town specification, and will be performed by the awarded contractor. the majority or work will be Concrete work: 25,000 plus square feet of sidewalk replacement Benefits: and improve cracks in concrete and asphalt to prevent injuries Fall 2019 Special Town Meeting $)159,355 Free Cash/Article Turnbacks j Infrastructure 10 years DEPARTMENT: ,Mansfield Schools PROJECT LOCATION: Jordan/Jackson Elementary School i PROJECT: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: AC Controller 1 __. 1,Urgent j i The Jordan/Jackson controller would work with the new master controller to allow us to control the boiler and chiller operations in the school. At this time we have no visibility into the schools HVAC operations. Fall 2019 Special Town Meeting $1100,000.00 !Free Cash (Unreserved Fund Bal.) Buildings 120 years ev a DEPARTMENT: 'Mansfield Schools j PROJECT LOCATION: iMansfield High School and Quakers MS PROJECT: PtSirO5:i1i W DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: AC Controller 'Urgent !Fall 2019 Special Town Meeting $)100,000.00 'Free Cash (Unreserved Fund Bal.) Buildings _I 120 Years "ASO)" DEPARTMENT: (Mansfield Schools PROJECT: PROJECT LOCATION: (District -Wide (Security Check-in Stations PRIORITY: !Urgent DESCRIPTION: The buildings have been reviewed by a security architect and recommendations have been made to improve the security at the main entrances of each building. Some of the recommendations include: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: 3MPROVEMENT LIFE: jy Building a new vestibule area Adding security windows to existing offices Adding additional fare doors in hallways to limit access to the public stations will allow visitors to be checked into the visitor management :m without allowing them access to the building, Fall 2019 Special Town Meeting $ 500,000 Loan Order IBuildmg 20 years a91° DEPARTMENT: DPW Administration j PROJECT LOCATION: School Street- Design PROJECT: Conceptual/25% Design School Street (West to Rte. 140) PRIORITY: 1 i DESCRIPTION: This item is for the 25% design of School Street Safety Improvements from West Street to Rte. 140 consisting of new granite curbing and sidewalks on both sides, striped bike lanes and a reconfigured intersection of School Street, Spring Street and Willow Street. The Town has submitted a project initiation form to MassDOT for this project with a construction estimate $2,825,000 to be funded with State and Federal funds if the project is accepted at the December 6th MassDOT Project Review meeting. The 25% design cost is $95,000 and total project design cost is approximately FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: ,IMPROVEMENT LIFE: Fall 2019 Special Town Meeting $1300,000.00 [Loan Order Design !N/A 1 r DEPARTMENT: DPW -Administration PROJECT: PROJECT LOCATION: (Route 106 (Copeland Drive to Route 140) Final Design -Route 106 Phase 1 Improvements (Copeland to Rt. 140) PRIORITY: lUrgent i DESCRIPTION: Phase 1 from Route 140 to and including the Copeland Drive intersection was funded in and started in 2018 to try to combine with the MassDOT improvements of the lintersection of Route 140 and Route 106. FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: c item is for Phase 1 - Final Design of Route 106 from Route 140 to and including Copeland Drive intersection. Final design funding in the amount of $140,000.00 is led to finalize the engineering documents for construction. The goal remains to ,bine bidding and construction Nvith MassDOT improvements to the Rt. 140/Rt. intersection. The Commonwealth of Massachusetts has committed to the construction funds of X7,775,000.00 for the reconstruction of Route 106 for Phase 1 and Phase 2. jFall 2019 Special Town Meeting f $1140,000.00 j jLoan Order !Design IN/A DEPARTMENT: DPW -Administration PROJECT LOCATION: iNorton/Mansfield Rail Trail Extension PROJECT: Final Design - Norton/Mansfield Rail Trail Extension I PRIORITY: Urgent DESCRIPTION: This item is for the final design of Mansfield's portion of the Norton/Mansfield Rail Trail Extension. The 25% Public Hearing was held on August 15, 2019 and the project is now advancing to Final Design. The construction is funded by State and Federal 'funds programmed for FY2022 Statewide Funding at $3,996,490. FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: .IMPROVEMENT LIFE: Design Cost: °sted from CIP: $48,200 $48,200 .1 Future Funding PS & E $ 4,500 Bid & Construction Services $ 4,000 can be funded from the Annual Operating Budget. Fall 2019 Special Town Meeting $148,200.00 Free Cash/Loan Order Design IN/A 'AS AA DEPARTMENT: ;DPW -Administration PROJECT LOCATION: Rt. 106 (Copeland Drive to North Main Street) i PROJECT: (Conceptual/25% Design --Route 106 Phase 2 Improvements (Copeland to N. Main St.) PRIORITY: (Urgent DESCRIPTION: Phase 1 from Route 140 to and including the Copeland Street intersection was funded land started in 2018 to try to combine with the MassDOT improvements of the ntersection of Route 140 and Route 106. FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: item is for Phase 2 - Conceptual Design of Route 106 from Copeland Drive to including the North Main intersection. The initial cost of Phase 2 is $150,000. re will be a final design stage of this project that will require an additional cost of ),000 for a total cost of approximately $400,000 for the design, engineering, and >truction of Phase 2. ie Commonwealth of Massachusetts has committed to the construction funds of ,775,000.00 for the reconstruction of Route 106 for Phase 1 and Phase 2. Fall 2019 Special Town Meeting $ 150,000.00 (Loan Order - IDestgn IN/A r Qcrrrrr �;; o DEPARTMENT: ;DPW -Administration j PROJECT LOCATION: (Rt. 106 (Copeland Drive to North Main Street) PROJECT: (Final Design -Route 106 Phase 2 Improvements (Copeland to Rt. 140) PRIORITY: ;Urgent DESCRIPTION: This item is for Phase 2 -Final Design of Route 106 from Copeland Drive intersection (to and including the North Main intersection. Final design funding in the amount of ($250,000.00 is needed to finalize the engineering documents for construction. 2 - Conceptual design for Route 106 from Copeland Drive to and including the Main Street intersection was requested for funding for FY 2020. >.e Commonwealth of Massachusetts has committed to the construction funds of ,775,000.00 for the reconstruction of Route 106 for Phase 1 and Phase 2. FISCAL YEAR: Fall 2019 Special Town Meeting j PROJECT COST: $11250,000.00 PROPOSED FINANCING: ;Loan Order j EXPLANATION: Design j IMPROVEMENT LIFE: !N/A � 03 DEPARTMENT: DPW -Administration PROJECT LOCATION: 'Townwide PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: Permit Requirements Urgent new EPA permit requirements for stormwater discharges from Small Municipal rate Storm Sewer System (MS4) in Massachusetts was delayed one (1) year but has become effective July 2018. In 2016, we had Tighe & Bond develop a six (6) year ementation cost for this permit. Year one (1) was funded in FY 2018 and was held FY 2019 because of the one (1) year delay in the permit by EPA. submitted a required Notice of Intent to EPA on September 28, 2018 and will time to update the program. The schedule was budgetted as follows: $90,000 $ 109,000 $ 87,000 $ 90,000 $ 90,000 ese costs will be updated as new information develops and may increase any contamination is found in our outfalls that requires removal. 'Fall 2019 Special Town Meeting $(90,000 Free Cash (Unreserved Fund Bal.) Other IN/A ?} DEPARTMENT: DPW -Highway Division PROJECT LOCATION: (Various PROJECT: FaMST-IT i DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: ~IMPROVEMENT LIFE: and Parking Lot Maintenance Urgent funds are used in conjunction with Chapter 90 State Aid ($750,000+-) to in and/or reconstruct roadways, sidewalks, bridges and parking lots. examples of this work would be: sealing, trench repair, chip -seating, overlays, milling and overlay, full depth truction, handicap ramp reconstruction, sidewalk repairs, sidewalk replacement, repairs, bridge replacement design and all work associated with the above. urgency here is that when not properly funded like years past, our roadway structure continues to deteriorate and minor repairs become reconstruction. ent averaged cost per square yard for various levels of work; Per SQ. YD. Cost per mile of road at 24' wide h and Crack -seal $1.70 $23,936.00 -seal $5.75 $80,960.00 overlay $11.40 $160,512.00 and Overlay Local $17.60 $247,808.00 and Overlay Arterial Collector $22.50 $316,000.00 aim Local $38.50 $542,080.00 aim Arterial Collector $45.00 $633,600.00 Est above is in the order that a road would deteriorate and our cost to repair would Fall 2019 Special Town Meeting $[2,000,000.00 Loan Order Infrastructure I10 years �p1Nfi 1J DEPARTMENT: JDPW-Highway PROJECT LOCATION: Multi -Use Path PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: =IMPROVEMENT LIFE: Path State Grant Match (Urgent project is to rehabilitate the Multi -Use path to create an extension of the World II Veterans' Memorial Multi-purpose Trail. The Commonwealth's Department of >ervation and Recreation has pledged a matching grant amount of $264,790 to plete this project. This $70,000 amount will fund the Town's portion of this :ct. The expected completion date of this project is June 30, 2020. 1Fall 2019 Special Town Meeting .1 $170,000.00 1 Free Cash (Unreserved Fund Bal) Infrastructure ' 120 years l �o� roti J StV Ao, -Highway Division DEPARTMENT: DPW PROJECT LOCATION: (East St. Municipal Complex PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: Snow Blower (Urgent would replace our 2013 Prinoth sidewalk snow blower. included in our presentation when we went for the 2013 Prinoth, we would mately build the fleet to 4 units which would include 2 tracked and 2 wheeled, the Terence being the tracked are much more productive and costly and would be used y for snow, whereas the wheeled machines are multi -use so they are used all throughout the year. goes without saying that the main reason for clearing snow from sidewalks is to ovide safe clear sidewalks for the schools to open. We have also seen an increase of quests to expand our sidewalk clearing into areas not required for schools to open. (Fall 2019 Special Town Meeting .I $1155,000.00 j (Free Cash (Unreserved Fund Bal.) I Equipment 10 years DEPARTMENT: 'DPW -WATER DIVISION PROJECT LOCATION: 11675 West St. Mansfield, MA Albertini WTP PROJECT: fr T-16 "b DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: ,IMPROVEMENT LIFE: Albertini Treatment Plant - Ventilation System Upgrade (Urgent !The HVAC system in the Albettini Water Treatment Facility located at 1675 West 'Street in Mansfield is not providing sufficient ventilation and resulted in corrosion build' up on critical equipment used to operate the Well system. A new ventilation system needs to be purchased and installed on site to eliminate the "off -gassing" of sodium hydroxide chemical used inside the Plant. Modification of the HVAC system will reduce corrosion build up to and improve general air quality for Water Division staff. Total Project Cost: $76,000.00 j I � Water Division proposes the Town fund this project by the following means: Balance remaining from completed Albextini Water Transmission Main Project (Account No. 33-450-007-530000) $12,801.14 (Water Article Turnbacks $9,556.86 Water Retained Earnings $60,198.81 I, t I � Fall 2019 Special Town Meeting $112,801/$50,643/$9,557 1Cap. Proj./Water RE/Art. Tunis. Building 1 120 years tip; °oma s � SSI Fi48 no`,.��,., .. _ .. DEPARTMENT: DPW -WATER DIVISION PROJECT: PROJECT LOCATION: South Main St. and Rt 495 Bridge Water Main Repair PRIORITY: Urgent DESCRIPTION: IFY2019 Special Town Meeting authorized $133,000.00 to address a hazardous water imain condition in South Main Street under the Rt140/Rt495 bridge underpass. The (Water Division completed initial work to obtain MassDOT permit, traffic safety plan, and water supplies for interim water supply during construction. Town of Norton is unable to supply water resulting in a more costly temporary lection from Mansfield and the bid also came in high. The lowest bid to slip line is .00 approximately double the estimated cost. Costs for traffic management plan and implementation, temporary water lines, (excavation and paving is estimated at $60,000. I Project Cost $198.937.00 ly Authorized Amount $133,000.00 No. 614599-580194 Additional Funding Request 1 Earnings $ 65,937.00 FISCAL YEAR: Fall 2019 Special Town Meeting j PROJECT COST: $166,000 PROPOSED FINANCING: Water Retained Earnings EXPLANATION: Infrastructure ,IMPROVEMENT LIFE: 130 years FCANGT � l o Al DEPARTMENT: DPW -Water Division PROJECT LOCATION: RT. 106, Copeland Drive, School & Spring Street PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: 106, Copeland Drive, School & Spring Street Water Improvements URGENT project was funded by Article 6 of the 11/18 Town Meeting for $1,000,000. bids for this project came in higher than estimated with the low bidder at increased costs are mostly because part of this project is on Mass State road and have to comply with the requirements of the MassDOT Permit and most of the -k on Rt. 106 and Copeland Drive will be done at night. Additional project costs include materials to provide temporary water during construction, Police details, compaction testing, contingency and final paving on the State road. project estimate is $1,300,000. increasing borrowing authorization from $1,000,000 to $1,300,000. Fall 2019 Special Town Meeting $300,000 Loan Order Infrastructure 130 Years O O O O O O O Q O O N S 0 S S S S S OO O p O p S O p O O O] M O 0 O 0 O O w NV! VI N N N M N N N N N N W h N N O d V t Q h G H N N O O O C vin O N N m 9 O O S O d � N YO! h O O O N O N inn N H N N Q C N G N N N N N N K O S N S_ C O W S N S N O N d y V C W C � N W � E... i Yf YI Yf ei M Z 00 0 00 a N N N N pp 0 0Lr� 0 O O O S � N LY H N VMi N M M VI W N N a o 0 0 o O o 0 0 0 0 � O am a � O N N LO! N N N N N Q > O a a u a a F « W C v SSSS S S SSS S ' S S S d 0 0 0 0 O O p p 0 O -63 ba D O O O O m 0 Y1 d' Qt M M p p 0 O O N S O O Q Z _ Z Q W EL N b o t o d� �... mry m m m g y � E y > C i o CdJ •'J O a Z � E � O c N V N N N W. O d 10 m' Q E F F F G ¢ O a 2 Q a G u D w m m N H v v mo. a a°a° 0 0 33 a a t t D D O a s O o o8 w a0 0 0 0 C, . 000 C� C� C� �w ' w 0 0 0 0 0 — — — — — — — — — — — -- — — — — — F I- 0 0 00 0 0 O. C� Yrs 0 E 0 0 m H m m & :a m m 3 m u a lt u O 0 0 0 w > no. DEPARTMENT: DPW PubBldgs/SpecProj PROJECT LOCATION: 'Town Hall PROJECT: 11 9 :1 6` DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: ,IMPROVEMENT LIFE: Parking Lot Fencing request is to fund replacement of original equipment wood fencing at the Rear ng Lots of Town Hall. The existing fence is 22 years old and in very poor ition; it has been repaired and patched for a number of years. The new Fence will 8 foot and 6 foot high sections of heavy duty vinyl fencing as presently proposed. (Spring 2020 Annual Town Meeting; $100,000.00 [Free Cash Other 15 years �APPI � r DEPARTMENT: ;DPW-PubBldgs/SpecProj PROJECT LOCATION: (Town Hall PROJECT: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: `),,IMPROVEMENT LIFE: Improvements Full depth repairs/crack sealing, sealcoat and re -striping rear parking area at Town Hall. (Spring 2020 Annual Town Meeting] $1150,000.00 Free Cash (Unreserved Fund Bal) j ;Infrastructure j 10 years ASAOSti DEPARTMENT: iDPW PubBldgs/SpecProj PROJECT LOCATION: MENU FACILITY PROJECT: 10,1161 iilY`/I DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: 'IMPROVEMENT LIFE: Asbestos Abatement request is to fund Asbestos Abatement and associated improvements at the dA Facility located at County Street. This will cover the cost of abatement of the aminated flooring material and provide replacement flooring with no asbestos and similar building improvements. ISpring 2020 Annual Town Meeting' $145,000.00 Free Cash (Unreserved Fund Bal.) j 1Buddings 120 years o P 641 DEPARTMENT: IPOLICE PROJECT LOCATION: POLICE DEPARTMENT PROJECT: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: (IMPROVEMENT LIFE: 1 VESTS REPLACEMENT project is to purchase 35 ballistic vests that have gone past their warranty's useful Spring 2020 Annual Town Meeting] $130,000.00 1 Free Cash (Unreserved Fund Bal,) !F qu pment 15 years AS A DEPARTMENT: Mansfield Schools PROJECT LOCATION: (Quakers Middle School PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: ,IMPROVEMENT LIFE: Aging Boiler iPriority 1 pct Overview: project was recommended by Tighe & Bond in the 2016 CIP Recommendation >rt. The district must look ahead at replacing boilers before the end of their useful ect Benefits: district will see energy savings, safety improvements and decreased ongoing itenance costs once boilers are replaced. Project Cost: Will seek out updated cost estimates. In addition, the district will seek funding from the MSBA Accelerated Repair Program. Spring 2020 Annual Town Meeting $1300,000.00 Loan Order Building 125 Years PROJECT: DEPARTMENT: Mansfield Schools PROJECT LOCATION: (Mansfield High School Replacement PRIORITY: ,Priority 1 DESCRIPTION: JWe have 2 boilers that are from the 1960°s and need constant repair, currently we Iare reparing tubes within the boiler to stop leaks. This project is likely to be eligible for reimbursement from the Mass. School Building Authority. FISCAL YEAR: ISpring 2020 Annual Town Meeting; PROJECT COST: $1800,000.00 1 PROPOSED FINANCING: (Loan Order EXPLANATION: Buildings IMPROVEMENT LIFE: 125 years n � ' DEPARTMENT: IParks & Recreation j PROJECT LOCATION: jPlymouth Street Recreational Facility PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: a k MPROVEMENTLIFE: Plymouth Street Playground: Equipment Removal & New Equipment Installation (Priority 1 2017Appropriated Funds $75,000 CIP Funding $25,000 Recreation Revolving Funding Due to the addition of more stringent ADA playground regulations since project initiation, we are no longer able to construct the Plymouth Street Playground for $100,000 as originally anticipated. A site study was performed in June 2018 determining playground equipment & surfacing costs for a total of $313,000. With the addition of (4) pieces of equipment added to the June 2018 study, an additional appropriation of $200,000 is required to complete this project. Spring 2020 Annual Town Meeting $1156,954/$43,046 1P&Rec Rev. Fund/Art. Turnbacks Infrastructure (20 years y'Q�FcNcr i� Aos DEPARTMENT: DPW -Sewer Division PROJECT LOCATION: iSewer Improvements PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: yIMPROVEMENT LIFE: Sewer Collection System Improvements are proposing to annually fund sewer collection system improvements. This may ide sewer line replacement or rehabilitation or pump station improvements. If e funds are not fully spent in a given fiscal year they can be combined with another to complete a larger project. Spring 2020 Annual Town Meetings $1200,000 1 Sewer Retained Earnings j Other l0years j z ?g SAS h6s DEPARTMENT: DPW Water Division PROJECT: PROJECT LOCATION: lWaterMeter & Radio Reader (Erts) METER REPLACEMENT PROGRAM PRIORITY: 1 DESCRIPTION: Purchase quantities of meter reading equipment needed to continue with an ongoing (meter replacement program; 650 new water meters with radio readers (Erts). se meters and erts will replace existing units that were installed over a period of :n years starting in the year 1999. readers have a ten to fifteen year battery operation life before the battery goes dead. Water Division is in year five of a nine year replacement program. goal is to replace all 7500 water meters and erts by fiscal year 2024. wrican Water Works Association (AWWA) Standards recommend that water meters replaced every ten years to keep up with the unaccountable water that is lost due to age of the meter. FISCAL YEAR: (Spring 2020 Annual Town Meeting( PROJECT COST: $1110,000 j PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: Water Operations Budget Equipment 110 Years v �pANI ! � •.. o� E- } DEPARTMENT: DPW -Water Division PROJECT LOCATION: I Water Division Fleet - 500B East St. 11 PROJECT: 10,119];1Yr�E DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: Vehicle Replacement (3) 1_ I three (3) new pick up trucks for the Water Division fleet to replace the truck vehicles: v fleet vehicles will replace three older model trucks with high mileage: Vehicle #56 - 2009 GIVIC Sierra/over 100,000 miles Vehicle #58 - 2009 GMC Sierra/over 100,000 miles Vehicle #61 - 2007 Chevrolet Silverado/over 120,000 miles ISpring 2020 Annual Town Meeting! $190,000 jWater Enterprise Ret. Earnings jVehicles 5 Years o ' DEPARTMENT: ;DPW -Water Division PROJECT LOCATION: (Dustin Water Treatment Plant - 500B East St. PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: ,IMPROVEMENT LIFE: Greensand & Filter Tank #1 Repair original green -sand filter tank #1 was put out of service due to a broken pipe at the Dm of the tank. The original green -sand media which was used to treat iron and ganese had to be removed to determine the extent of repair needed. Funding is requested to hire a qualified contractor to complete the repair, purchase and install new green -sand filter plus material, test equipment and have filter tank #1 restored to service. Spring 2020 Annual Town Meeungj $170,000 Water Retained Earnings [Infrastructure 10 Years w Pv rNS A y DEPARTMENT: Electric I PROJECT LOCATION: Ongoing Misc. Capital Items PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: a�MPROVEMENT LIFE: Projects budget item includes ongoing capital work such as pole replacement and lation of new wire for service reliability. �SANOT �/ {3^�" a ` "fib",• =- r DEPARTMENT: 'Electric PROJECT LOCATION: IJEWELL STREET I PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: *IMPROVEMENT LIFE: i Street Underground Circuit IFY2021 $1325,000.00 !Capital Budget Infrastructure I 145 pears 2 0 > � r o DEPARTMENT: Electric s PROJECT LOCATION: Various Locations PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: +.IMPROVEMENT LIFE: 11. Metering Infrastructure project is to connect the existing electric meters to a radio read system. project is on hold for further study. ....._._................... . FY2021 $150,000.00 Capital Budget (Equipment 120 years I J A xt � 9-0rF�ASAO\SS�4„ DEPARTMENT: Electric PROJECT LOCATION: (West Church Street I PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: ` JMPROVEMENT LIFE: Church St. Yard Storage Infrastructure 1 _I project is for a new storage area building at the pole yard to cover material, :les and equipment This budget includes phase 1 of a 2 phase project. Phase 2 is eted at $300,000. PROJECT: PRIORITY: DESCRIPTION: DEPARTMENT: jEle'dric PROJECT LOCATION: (Various Locations New Vehicles (1 f #28 (2001) based upon age and maintenance is currently MMED's spare line truck needed for emergency restorations. Heavy duty work vehicles (e.g. Line Digger) are expected to be replaced every 15 years for reliability purposes. FISCAL YEAR I FY2021 PROJECT COST: $1300,000.00 PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: Capital Budget j Vehicles 17-15 years O O O OOON OH OM OmO OOO OVf4 ON O1 O O NO OO OOme4 NO N O O' ll1 10 le VI O O 0 N V0 NOO VOOI NOO O V0 N O C O O NOO] NN NOOO N mN Fp NOOON VOOOr1O1 N VY N h N N N N M M V! N N Vr O O O O O O O O O O O O N N N N N K N h N N W Vr `d u S� O 0 O O O O O QOO O O O O O O O N N N N N O O O O N O y O N V1 N O O VaI Y1 C d M M c M O M V! N Vr Y1 O O O O O O O O O O O O � a Y c a g 0 0 o 0 0 0 o 0 0 0 0 0 C N Vi a? N N N N Vs N N N Y! N Cry 6 IV 9 ty C C W 'gyp d a 0 0 0 0 0 0 0 0 0 0 o 0 C N N V1 N N N N N N N N N O a s S N N OOO O O O O O O O O OcOO O O OO 0O O OO O O U o O O N tf1 O O O O c Oi Cl 1616 V1 V1 N Vl d O y� N d' C V1 VI O n n O O W m N N M M d L!'NN "I N N Vr N N N L! N N N ti V1 N N V! N V 1 N m N m N IL dl O O O O O O O O O O O C a N N N N NO N N N N N N N C a d � m n O mo 0 0 0 0 0 0 0 0 0 E i N N N N N N N N N Q O a n u a 0 o 000 0 0 co 0 0 0 0 0 0 c o o 0 o 0 0 O 3 000 00 000 000 000 `�� 000 00 «y"� 000 O gtivl O O V1 v YI e O M O 0n O O n O1 Oe Vf O W W N N W E N N V1 N N N vR N '1 m V O+ o h N H d N O Q 6 m v w 23 y v m E a m m v a n o N yN U 6 d. O 3 W LL E O C a a o m o a d ry c a d` U YI h d h E 6 E p d U p dl 'C O F d F O d � v 3 E E ?+ E E �mpd F. Em pm dm com E >m E0m 0O vpm E ° E c O n d 3 p> n d N n d n d «¢ '^ a vi n d Z n d m O n d O n d > n d 2 0 F- m 00 0 -0 S O vi 0 K O O Z 0 a 0 N UI 4p dl ¢ C C N T (o m m V V aG g m m v_,m � E E s t mm d rc d a d m= n 6 o G 4 i L OG a Q S 2 0 0 n G N yH O LL 4 6 6 N Z O 0 n0 0 > 6 6 0 O G> V V O O O O O O O O O O O O O O O O O O N O O O N O N N N N N N N N 49 O O O yO O O N O O O O O O O O O O O O N N N N N N N N N N N N L W N d U L � N O O O O 00 O O O O O O N N N N N N N N N N N N N C y C 9 O O O O O O O O O O O O " a Y c a g o 00 0 0 0 0 0 0 0 000 O O C p O O O O O N O N N N N N N N i O O O0 O O N N N N N w 'a C C w v s O O O O O O O o O o 0 0 C N N N N N N N N N N N N O W 1' O O O O 00 O O O O O O = N N N N N N N N N N N N ryH V W tL N N N N N N N N N C � `a a n m O N N N N E y 7 N N N N N Q O u a a u a ¢ C 9 O O O O N W N N O 0 0 O O o N O O E Val t�if 3 N N M M N 'O � Q a` n H c m c a+ e o m c m E « E « « E Q N � Q v 0 d O d 0 a d 0 O U w e a m Aa H ,a m -oz 2 mm u E 46 W O Q VI a 0 Q N 0 ¢ N N ¢ N W m N 1- � N ✓ N � N F � 0 ~ P.r VI o f A w 5 N E W Nt N N N N O 2 0 u G s z° `w Lw Lw e ey c rudiH 33 . ea ° a a y a a a s ¢¢ a s a a 0 a s a s A wr F tN( a v, DEPARTMENT: DPW-PubB1dgs/SpecProj PROJECT LOCATION: (Town Hall PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: ,IMPROVEMENT LIFE: i y Remove and Replace Roof to Include Central Addition/Old Air Shafts Design & Bid l s is to remove the 2 -existing roofs that exists from the original building and remove air shafts below roof elevation and re-route with new PVC roofing system and .ove asbestos contained in existing roofing system. This project will be to pay for design of the roof and then the costs associated with bidding the project as per the curement laws. w DEPARTMENT: DPW-PubBdgs/SpecProj PROJECT LOCATION: (Plymouth Street Fire PROJECT: irTi' ST"T"b DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: `IMPROVEMENT LIFE: Flooring 12 request is to replace the flooring in the living areas of the Fire Station that has oded its useful life. % wl r > o r DEPARTMENT: (POLICE PROJECT LOCATION: (POLICE DEPARTMENT PROJECT: iw"F%S;T6'il DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: � MPROVEMENT LIFE: CRUISER REPLACEMENT AS PER CHIEF'S PLAN D-2 12 Police Chief has created a cruiser replacement schedule based on usage and ities within the Police Department. This project is to replace the vehicles as Detective Vehicle - $45,000 = $45,000. G A' DEPARTMENT: Fire Department PROJECT LOCATION: 500 East St. Public Safety Complex PROJECT: ir�iCOTHT"b DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: ,IMPROVEMENT LIFE: P Car one replacement `a Car One Car one is a 2010 Ford Expedition, SUV with _just over 55,000 miles. This vehicle has served as the Chiefs vehicle, responding to emergency incidents on a daily basis. Car one has been very dependable but has begun to show signs of decay. Both the undercarriage and the rear door are displaying decay to due age and environmental exposure. The cost of replacing Car one is estimated to be at $50,000. Fall 2020 Special Town Meeting $ 50,000 Free Cash (Unreserved Fund Bal.) Vehicles 5 years :�c��iircr ��8r ni °ns DEPARTMENT: Mansfield Schools PROJECT LOCATION: (District -Wide PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: c• Paving and Concrete work 12 :ct Overview: capital request is for paving sidewalks and roadways within the district. m Over 25,000 Square Feet Lots: Over 125,000 Square Feet Fhe paving will be a combination of Mill and Over lay, and full depth mill. The asphalt vill be per the town specification, and will be performed by the awarded contractor. rhe majority or work will be Concrete work: 25,000 plus square feet of sidewalk replacement Benefits: and improve cracks in concrete and asphalt to prevent injuries Fall 2020 Special Town Meeting $ 200,000 _I Free Cash (Unreserved Fund Bal.) Infrastructure 10 years DEPARTMENT: IMansfield Schools PROJECT LOCATION: (High School PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: Auditorium Improvements Carpet & Paint Priority 2 Project Overview: This is the second phase of auditorium improvements. It was originally proposed to CIP in the fall of 2017 but was deferred. In FY19, air conditioning was added and the sound system replaced. In this phase, carpeting will be replaced. The ceiling and walls will be painted. (Fall 2020 Special Town Meeting $170,000.00 Free Cash !Building 10 years j �i verr � o 9e DEPARTMENT: DPW-Administration PROJECT: 1 .fir I CO7 i_"b DESCRIPTION: PROJECT LOCATION: 1Townwide Permit Requirements Priority 2 1 The new EPA permit requirements for stormwater discharges from Small Municipal Separate Storm Sewer System (MS4) in Massachusetts was delayed one (1) year but has now become effective July 2018. In 2016, we had Tighe & Bond develop a six (6) year implementation cost for this permit. Year one (1) was funded in FY 2018 and was held until FY 2019 because of the one (1) year delay in the permit by EPA. We submitted a required Notice of Intent to EPA on September 28, 2018 and will continue to update the program. The schedule was budgetted as follows: FY'20 $90,000 FY'21 $ 109,000 IFY'22 $ 87,000 IFY'23 $ 90,000 j FY'24 $ 90,000 These costs will be updated as new information develops and may increase substantially if any contamination is found in our outfalls that requires removal. I � I FISCAL YEAR: Fall 2020 Special Town Meeting 3 PROJECT COST: $1109,000 PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: Free Cash (Unreserved Fund Bal.)_ Other _ 1N/A o WWDEPARTMENT: DPW -Administration PROJECT: PRIORITY: DESCRIPTION: PROJECT LOCATION: (North Main & County Streets Final Design New Road North Main to Howe Street (2 This item is for the final design of a new roundabout at the intersection of North Main Street, County Street and Angell Street with a road over the rail yard, relocating the rail crossing and continuing to the existing end of Howe Street. The estimate for the final design and the total road project design cost is $345,000. The estimate to design the rail improvements is approximately $201,000. The rail improvements are needed in the rail yard in order to relocate the rail crossing so that it can accommodate the crossing of a single rail and the relocation of the Noonan uploading. We are trying to have MassDOT Rail Division pay for the design of the improvements but we do not have a commitment. FISCAL YEAR: Fall 2020 Special Town Meeting PROJECT COST: $345,000 j PROPOSED FINANCING: EXPLANATION: dMPROVEMENT LIFE: Loan Orders (Design IN/A r `a9�fp Al : y DEPARTMENT: iDPW-Highway Division PROJECT LOCATION: Various PROJECT: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: -IMPROVEMENT LIFE: and Parking Lot Maintenance i (Priority 2 ;e funds are used in conjunction with Chapter 90 State Aid ($750,000+-) to stain and/or reconstruct roadways, sidewalks, bridges and parking lots. cal examples of this work would be: k -sealing, trench repair, chip -sealing, overlays, milling and overlay, full depth nstruction, handicap ramp reconstruction, sidewalk repairs, sidewalk replacement, ,e repairs, bridge replacement design and all work associated with the above. urgency here is that when not properly funded like years past, our roadway structure continues to deteriorate and minor repairs become reconstruction. ent averaged cost per square yard for various levels of work; Per SQ. YD. Cost per mile of road at 24' wide h and Crack -seal $1.70 $23,936.00 -seal $5.75 $80,960.00 overlay $11.40 $160,512.00 and Overlay Local $17.60 $247,808.00 and Overlay Arterial Collector $22.50 $316,000.00 aim Local $38.50 $542,080.00 aim Arterial Collector $45.00 $633,600.00 list above is in the order that a road would deteriorate and our cost to repair would Fall 2020 Special Town Meeting $12,000,000.00 (Loan Order j Infrastructure �10 years DEPARTMENT: DPW -Highway Division PROJECT LOCATION: Highway Garage PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: ,JMPROVEMENT LIFE: 1-1 /2 Ton 4X4 Dump Truck w/Snowplow Priority 2 is truck is similar to our existing Ford F -550s in the fleet. It would replace a 2001 rd F-450 that is used daily in the operations of the Highway Division. It would also equipped with a stainless steel dump body and a snowplow for winter operations. $45,000.00 $12,000.00 $25,000.00 $4,000.00 (Fall 2020 Special Town Meeting $186,000.00 jFree Cash (Unreserved Fund Bal.) j !vehicles If 10 years j M;��� , s o,2 DEPARTMENT: (Parks & Recreation PROJECT LOCATION: ,Plymouth Street Recreational Facility PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: JMPROVEMENT LIFE: Plymouth Street Playground: Equipment Removal & New Equipment Installation Priority 2 7Appropriated Funds 1000 CIP Funding ,000 Recreation Revolving Funding ue to the addition of more stringent ADA playground regulations since project itiation, we are no longer able to construct the Plymouth Street Playground for 00,000 as originally anticipated. A site study was performed in June 2018 !tertnining playground equipment & surfacing costs for a total of $313,000. With the ldition of (4) pieces of equipment added to the June 2018 study, an additional rpropriation of $200,000 is required to complete this project. final $25,000 for this project will be funded at the Fall 2020 Special Town Meeting, !Fall 2020 Special Town Meeting $25,000.00 Free Cash (Unreserved Fund Bal.) jInfrastructure j 20 years j DEPARTMENT: ;DPW -Sewer Division PROJECT LOCATION: ( Sewer Improvements PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: ,IMPROVEMENT LIFE: a' Sewer Collection System Improvements 2 We are proposing to annually fund sewer collection system improvements. This may include sewer line replacement or rehabilitation or pump station improvements. If these funds are not fully spent in a given fiscal year they can be combined with another year to complete a larger project. DEPARTMENT: DPW -Water Division _i PROJECT LOCATION: (Water Fleet Vehicle - 500B East Street PROJECT: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: 1 11 VEHICLE EQUIPMENT PURCHASE - DUMP TRUCK 12 _ (1) heavy duty six wheel dump truck for the Water Division fleet. seven years ago the Water Division's dump truck was removed from its active of vehicles because the frame had rusted to the point that it could not be repaired. dump truck vehicle was disposed of in a Town surplus bid. A dump truck is essential equipment to respond to water main breaks. At the present time when a water emergency occurs, instead of immediately responding to the break, the Water Division first needs to locate a dump truck to borrow or rent a dump truck. The Water Division routinely reaches out to the Highway Division to check availability to borrow equipment. If it's available, additional time is used to locate where the equipment is, verify it's ready for use, and coordinating manpower to pick up the truck from the other department. If a dump truck is not available internally because they are in use or have sanders on them, the Water Division is forced to hire an outside contractor and incur significant added costs for equipment rental & crew. wing a dump truck in the Water Division fleet again would improve response time -water emergencies, eliminate unnecessary costs to hire outside contractors, and help save lost water resources. •'l 00 o 0 0 0 0800000000 no 0 0 0 0 n o o on oo N N O O O O O O O O O O O O 0 O 0 O 0 O 0 O 0 O 0 h 0 O 0 11= O O O O O 0 O 0 0 O 0 O 0 0 0 O 0 O 0 O 0 dy O O O O �, I/1 W N t/1 Y1 O N Vl Ips O O O O O O O 6 e O O' O O O N M N M M M N Q N N N O N N N N N N N� N M N N lnO {N/! N N O O O --------------- OO O O N N N N N N N 00 OO O O 00 MW O O N N O S N N O O 0 N O W 0 W m M Vl N W N N N N N O O O O O O O N N N N N N N O O O 0 O O O N N N N N N N 00 OO 00 O O N N N N S S N N S S ME NNO 0p00000 O pp S 0 0 0O N 0 O OOOO O C O0C000O OOO O 0 0 0 0 OO Q N N tO N H N v1 N tO N M N v1 N N N t0 N M N M Q v1 N Y1 N Vf N V1 N N to N O N vl N vt N N M N N N N N N N N no O O O O O O O O N N N O O O O O O N N O 00 O N L N N N N N n N N N N W N no 0Q 0 o mO 0 S 0 0 0 0 0 O 00 00 000 0000000 OOOOOOOOOOOoOYg n o S o n n o nN nm SC O O 00 0 tll vi NNviON i 1 OOOO Og000 O O' N H ei b N m O N M N Q N Nw N N N 'i N N Q M M 4 N 0 N n N mL N N m Ih N N n 1p N N N N N �y N N NN N NNNN �y^ N N N C L E E~ c w q a .3 u c w v n o aa o m 01 E E E p �n w nod u ob d C fl O m C_ N O O O D N U N N N C N O N y UI 16 U N q N a L y U C U 6 a 6 N 6 W L O> 6_ O O M N __ •P y W 'O W O i+ O u O O z O h w¢ tr O > o .o O 6 K .rC o o w Q a u c •E c c c 0 v E 'y a E m E m s u E m E 3 s E E c o E E N g N x C x C N E N U O M E N N ~ UO U= O •- C Y C N N c n '0 3 3 3 n E m .-� a o H E a V a 3> O w¢ « t= t7 z :n 'oo a o w o o a a o w Q u' E w w w o 2 a> m m m m O w c d Z a r t- 1- O G V O g N a` ¢ ow w 0 a m in x o x x a o w G a a cc m m m m m m m m h E E 6 6 4 a w w 10 C 6 6 y� 0 0 0 0 0 0 0 0 N Z Z Z Z Z Z Z Z p p �' O O 0 0 0 0 0 0 0 0 0 0 0 o g o g o 0 0 0 0 0 +ort o 0 n n o o a 0 0 0 0 0 0 N N N N N N O O O O O O O O O O N N N N N N N N N N d V L 0 0 N O O O O O O O O O O O O O N N N N 00 00 N N N O O N O O O N O O O tMp b � N a � N N N N N s Q N N a V L yyV � C N O O O O O O O O O O O O O O N N N N N c 08 N O O 00 N O a2 00 0 o cg o0" `d y c e w •� CT fL 0 0 0 o g m 0 O o 0 0 N N N G C N N N N N O O O i G N N d L' O O 0 O O O O O O O N N N O N O N L N N N N N el N a N N fL O N O N O N O O O OO C O N O N O N $ $ OO O y O O O a d 9 O N N N N VOi ; YO! a n u a n u Q 0 0 0 0 0 0 0 0 0 0 0 0 0 0 N N N N N N o � a o 0 0 0 0 0 0 M ° a o 0 oo 0 0 0 0 0 a wo � voi ouoi w a ,a 6 G w N w c c a e MM E Y' E E 'u v vTi E o tQ_- Yn a `a p Q y n >> Q� a v 6 a o O O 0 a m m 0 N N N+ N (7 'd 6 Z 1.: u 04 N N O 'm O E E E w 4 E in m E N N ry v d d d z v v W p ry Z D Z D Z 0 u 0 2i K vni 3 G �• T d! d! mm C C �ro�ro r�� 3 3 _= o o °• a s a a 0 0 a s C C C D O ,Cj 3 0 u 0 u 00 0 0 00 0 0 00008o K K N N K N N N 0 N 0$ O O O N N v0i o O N O d o Nz N O � O M ei ONE N N N K K N H N ri N K K N h N N N O O Op O pK O N O VO! N O O O O N N N O O rl N N' N �v 0 m `gym m m N NKK H N M` K N K K O O O O O O O O O O N N N N N K N N N O O O Nm N K O O O O O O O O O O K K N N N N K K K K O O O O O O O O O O O K K N N N N N N N K O O oO N O O O O O O O O O O N N N N K K K K K OO O O M K O O O O O O O O O O N N N N K K K K K O V; e^i N N O O O O O O O O K K N N N N N G O' m r K 0 0 0 0 0 0 N N N N K N O O O O O O O O O O O O N N K K 'VF K N O O O N O N0 O O N O a� M N ON N .ti L1 K K N I� K N K G � y W a 'u ° N •' q m O 10 m a>° u u N N m O N o Li o _q h N N MiS N d h tJ m m O o> r w v o Z w D o Z w C O it O Z O c c e W W 0 n a o. o. 0 0 :�9tFDAI A DEPARTMENT: jDPW-PubB1dgs/SpecProj PROJECT LOCATION: jPublic Building Department PROJECT: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: k MPROVEMENT LIFE: Trademaster Van 12 1 vehicle is to replace a former School Department van that is a 2009 Ford Van. van is used daily in the Public Building Department. Spring 2021 Annual Town Meeting $140,000.00 !Free Cash (Unreserved Fund Bal.) ( Vehicles 10 years o Pqi tick.. �. pp FSADA5 DEPARTMENT: JDPW _ 1 PubBldgs/SpecProj PROJECT: PROJECT LOCATION: I TOWN HALL I Interior Upgrades & Improvements PRIORITY: 12 DESCRIPTION: The public meeting rooms and common areas have not had a significant upgrade in facilities or furnishings since the original occupancy in 1997. Much of the furnishings are from the previous Town Hall or have been donated when declared surplus by local companies. Each conference room would receive new conference/committee tables and modern artwork. Both rooms recently had new audience chairs and tables installed. Through this project, the 2nd Floor would receive a new conference table, and the 3rd Floor would receive a new conference table and conference table chairs to better accommodate the types of meetings held there. The 3rd Floor conference room would 'receive new carpet and fighting, as well as raised lettering TOWN OF MANSFIELD in (the main meeting room. New display cabinets would be placed in the hall for Town FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: )nally, it includes new building directories and work associated with having nic message boards to replace existing outdated bulletin boards. We propose to the lower storefront at the main building entrance which has deteriorated due conditions. (Spring 2021 Annual Town Meeting $1110,000.00 Free Cash (Unreserved Fund Bal.) Buildings (Various life expectancies s F, DEPARTMENT: DPW-PubBldgs/SpecProj PROJECT LOCATION: (Town Hall _i PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: Fire Alarm Upgrade / Panel Replacement 12 11 is to replace the Fire Alarm System at the Town Hall. (Spring 2021 Annual Town Meeting $160,000.00 1Free Cash (Unreserved Fund Bal.) Buildings 120 years a o DEPARTMENT: DPW-PubBldgs/SpecProj PROJECT LOCATION: IDPW Departments PROJECT: FaTICOTIT_" DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: ,IMPROVEMENT LIFE: Replacement of Radio Networks 2 I of the DPW Radio System. o� q `4 ASA DEPARTMENT: POLICE PROJECT LOCATION: (POLICE DEPARTMENT PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: r\IMPROVEMENT LIFE: CRUISER REPLACEMENTS AS PER CHIEF'S PLAN COMMAND (2 Police Chief has created a cruiser replacement schedule based on usage and .ities within the Police Department. This project is to replace three cars as follows: Vehicle Replacement - $45,000 Vehicle Replacement - $45,000 anand Vehicle Replacement - $55,000 otal = $145,000 �1NL i DEPARTMENT: POLICE PROJECT LOCATION: (POLICE DEPARTMENT PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: i LESS THAN LETHAL TECHNOLOGIES The Police Department remains committed to the investment in less than lethal technologies. The Department endeavors to continue efforts at acquiring, training and street level utilization of emergent less than lethal technologies. Technologies such as Taser(s) and 40mm low velocity impact rounds, have resulted in the (1) preservation of (2) life reduced officer and municipal liability (3) lowered the instances of officer injuries. Funds will be used to continue with both the Taser and 40mm program and emergent technology. ,Spring 2021 Annual Town Meeting) $115,000.00 jFY22 Operating Budget (Equipment `10 years E1N�T y� v �w. iFp.) DEPARTMENT: ;POLICE PROJECT LOCATION: IPOLICE DEPARTMENT PROJECT: Fri T" N-1 DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: ]IMPROVEMENT LIFE: CRUISER REPLACEMENTS AS PER CHIEF'S PLAN D-4 12 The Police Chief has created a cruiser replacement schedule based on usage and priorities within the Police Department. This project is to replace vehicles as follows: D-4 Detective Vehicle - $45,000 = $45,000. (Spring 2021 Annual Town Meeting] $45,000.00 jFY22 Operating Budget Vehicles I 15 Years �a DEPARTMENT: POLICE PROJECT LOCATION: (POLICE DEPARTMENT PROJECT: Ia qii5:ili 61a DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: `IMPROVEMENT LIFE: 2 REPLACEMENT CRUISER M-8 er M8 is a front line patrol unit. The unit will be 4 years old and is expected to mileage above 75,000. The cruiser will be replaced with a current model year rolet Tahoe PPV 4WD. Upfitting will be done through MHQ, Norfolk County Wav or another certified State Contracted vendor. (Spring 2021 Annual Town Meeting€ $155,000 Free Cash (Unreserved Fund Bal.) Vehicles 15 years �2 0: AS AOASSP DEPARTMENT: IPOLICE PROJECT LOCATION: (POLICE DEPARTMENT _i PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: 'IMPROVEMENT LIFE: CRUISER REPLACEMENT CRUISER M-10 2 er M10 is a front line patrol unit. The unit will be 4 years old and is expected to mileage above 75,000. The cruiser will be replaced with a current model year rolet Tahoe PPV 4WD. Upfitting will be done through MHQ, Norfolk County -Wav or another certified State Contracted vendor. (Spring 2021 Annual Town Meetmgj ��55,000 jFree Cash (Unreserved Fund Bal.) ! !vehicles j S years ,Qc�ciwcr`:_ S o NA DEPARTMENT: POLICE PROJECT LOCATION: (POLICE DEPARTMENT PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: ;,IMPROVEMENT LIFE: CRUISER REPLACEMENT CRUISER M-13 er M13 is a front line patrol unit. The unit will be 4 years old and is expected to mileage above 75,000. The cruiser will be replaced with a current model year rolet Tahoe PPV 4WD. Upfitting will be done through MHQ, Norfolk County Wav or another certified State Contracted vendor. 'Spring 2021 Annual Town Meeting' $155,000 Free Cash (Unreserved Fund Bal.) Vehicles 5. years o ��,rr°onsno�� DEPARTMENT: !POLICE PROJECT LOCATION: POLICE DEPARTMENT PROJECT: 12 CRUISER REPLACEMENTS AS PER CHIEF'S PLAN COMMAND DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: 12 The Police Chief has created a cruiser replacement schedule based on usage and priorities within the Police Department. This project is to replace three vehicles as follows: Command Vehicle Replacement - $55,000 D-5 Detective Vehicle - $55,000 = $110,000. (Spring 2021 Annual Town Meeting] $110,000.00 j Free Cash (Unreserved Fund Bal.) Vehicles j 15 years j o � a As A DEPARTMENT: POLICE PROJECT LOCATION: POLICE DEPARTMENT PROJECT: FaTINT011 "b DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: ,IMPROVEMENT LIFE: CRUISER REPLACEMENTS AS PER CHIEF'S PLAN T-1 12 The Police Chief has created a cruiser replacement schedule based on usage and priorities within the Police Department. This project is to replace three vehicles as follows: Command Vehicle Replacement - $55,000 Prisoner Transport Vehicle T-1 - $62,500 Animal Control Van ACO -1 $45,000 = $162,500. (Spring 2021 Annual Town Meetings $162,500.00 Free Cash (Unreserved Fund Bal) I (Vehicles 15 years J G yi DEPARTMENT: !POLICE PROJECT LOCATION: (POLICE DEPARTMENT PROJECT: 12 DESCRIPTION: REPLACEMENTS AS PER CHIEF'S PLAN ACO -1 Police Chief has created a cruiser replacement schedule based on usage and cities within the Police Department. This project is to replace three vehicles as .nd Vehicle Replacement - $55,000 r Transport Vehicle T-1 - $62,500 Control Van ACO -1 $45,000 = $162,500. FISCAL YEAR: Spring 2021 Annual Town Meeting PROJECT COST: $145,000.00 j PROPOSED FINANCING: EXPLANATION: 'IMPROVEMENT LIFE: 1Free Cash (Unreserved Fund Bal.) 1 Vehicles 15 years Pa "P fOASI U\ ,U ✓t 1� DEPARTMENT: Fire Department PROJECT LOCATION: Town -wide PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: j MPROVEMENT LIFE: Rescue 34 Ambulance Priority 2 Rescue 34 Rescue 34 is a 2014 Ford E450, Road Rescue ambulance with 117304 miles. This vehicle has needed service and typically, as age and usage increases and the mileage goes well over hundred thousand, cost of repairs increases dramatically. Other items within the ambulance are also reaching the end of their life cycle. This is right in line with the ambulance revolving account schedule, established at town meeting in 2011 for this explicit purpose. The cost of replacing Rescue 34 and several key pieces of equipment is estimated to be at $350,000. Rescue 34 has run front line but will move to reserve status in the Fall of 2019 and will remain in that capacity until its projected replacement in FY24. $300,000 of the cost of this ambulance will be paid for from the Ambulance Revolving Fund, and $50,000 will be paid for from Free Cash. May 2021 Annual Town Meeting $ 350,000.00 Ambulance Rev. Fund/Free Cash Vehicles 10 years e J v DEPARTMENT: (Mansfield Schools PROJECT" LOCATION: District -Wide PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: Replace Plow Truck Priority 2 Overview: ment of a plow truck. District is proposing a 3/4 ton pickup with an 8 foot 11 May 2021 Annual Town Meeting $'50,000 Free Cash (Unreserved Fund Bal) j !Vehicles X10 years j 1 0 DEPARTMENT: (Mansfield Schools_ PROJECT LOCATION: (District -Wide PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: improvements 'Priority 2 :t Overview: ,vements and replacements of aging equipment and surface area based on 2016 completed by Playground Inspections of New England. t Benefits: improvements and general upkeep. ;Spring 2021 Annual Town Meeting; $1250,000.00 Free Cash (Unreserved Fund Bal.) Equipment 20years QCINCT TMJ, & O ti DEPARTMENT: .Mansfield Schools PROJECT LOCATION: (District -Wide I PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: ,IMPROVEMENT LIFE: 1 of Special Education Mini Bus Priority 2 Overview: the oldest mini bus in our fleet. ,ject Benefits: stay ahead of costly repairs and to prevent delays in busing due to maintenance Spring 2021 Annual Town Meetingf $170,000.00 Free Cash (Unreserved Fund Bal.) Vehicles (5 years j DEPARTMENT: Mansfield Schools j PROJECT LOCATION: Robinson Elementary School PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: ,IMPROVEMENT LIFE: AC Controller Priority 2 The Robinson controller would work with the new master controller to allow us to control the boiler and chiller operations in the school. At� this time, we have no visibility into the schools HVAC operations May 2021 Annual Town Meeting .i 250,000.00 j Free Cash (Unreserved Fund Bal.) (Buildings 120 years 1=n o Y NIV ASA" DEPARTMENT: ;Mansfield Schools j PROJECT LOCATION: (District -Wide PROJECT: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: ,IMPROVEMENT LIFE: of Unit Ventilators 1Priority 2 Project Overview: This was a fall 2017 request to CIP which was deferred. Planned replacement of three units which are the oldest throughout the district. This project was recommended by Tighe & Bond in the 2016 CIP Recommendation Report. :ct Benefits: allow us to follow recommended scheduled replacements. Spring 2021 Annual Town Meeting $1100,000.00 1Free Cash (Unreserved Fund Bal.) j Equipment 120 years ='Q Ep\wcr r�3; 10, DEPARTMENT: 'Mansfield Schools PROJECT LOCATION: 'High School PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: Replace Track Surface Priority 2 >ject Overview: is project was proposed to CIP in the fall of 2017 but was deferred. 2013, the track was patch resurfaced with latex. This was meant to last 5 years. v surface will be polyurethane which will have a 10 year life span. oject Benefit: e are proposing that the turf field be replaced in 2021. Both the turf field and track eface will have 10 year life spans. The district would like to stagger the two projects spread cost. (Spring 2021 Annual Town Meeting' $350,000.00 Loan Order j iInfrastructure 10 years o 9 DEPARTMENT: ;Mansfield Schools PROJECT LOCATION: (Mansfield High School PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: l Gym Floor Replacement Priority 2 floor in the gym is repaired every year. There are many areas in the gym that floor is too thin to repair. The floor needs to be replaced. jSpring 2021 Annual Town Meeting; $1500,000.00 j 1Loan Order ,. 1 Buildings 120 years 1NC! /eP S�4 0 l As �, DEPARTMENT: !Mansfield Schools PROJECT LOCATION: District -Wide PROJECT: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: ;Lighting Upgrades 12 _. lighting project has two components that are equally important to the 1- The current lighting throughout the district is older fluorescent lighting and electronic ballast technology. Light bulbs are expensive to buy and cumbersome to dispose of at end of life. In many cases, the ballast cost alone can be as much as a new LED Fixture. The new lighting will dramatically reduce repair costs and will reduce the energy consumption in the district We have students within the district that have medical conditions requiring ?D lighting. We have been able to magnetic the accommodations to this int as they have been limited in scope. As the students move through the ;tem the requirements will become more expansive and will include rnmon areas like hallways, gyms, auditoriums, etc. We need to plan now to grade all schools with LED lighting !Spring 2021 Annual Town Meeting $150,000 IFree Cash (Unreserved Fund Bal.) !Equipment 20 years �c�ucr i, r o F DEPARTMENT: ;Mansfield Schools i PROJECT LOCATION: Robinson Elementary School PROJECT: L DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: t Exterior Doors Priority 2 Replacement of exterior doors at the school that are beyond repair. These doors have holes and are rusted, most have door hardware issues that have been repaired numerous times. (Spring 2021 Annual Town Meeting] $I50,000.00 Free Cash (Unreserved Fund Bal.) Buildings 25 years j WIN DEPARTMENT: DPW -Administration PROJECT LOCATION: iEngineering PROJECT: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: (IMPROVEMENT LIFE: Plotter & Scanner 1 2 1 plotter/scanner will replace the existing machine that is about 10 years old. (Spring 2021 Annual Town Meeting $20,000 ; FY22 Operating Budget j (Equipment 110 years I L q DEPARTMENT: DPW -Sewer Division PROJECT LOCATION: (Sewer Improvements PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: Sewer Collection System Improvements I2 are proposing to annually fund sewer collection system improvements. This may ade sewer line replacement or rehabilitation or pump station improvements. If e funds are not fully spent in a given fiscal year they can be combined with another to complete a larger project. (Spring 2021 Annual Town Meeting] $1200,000 i Sewer Retained Earnings !Other j 10 years i' DEPARTMENT: iDPW-Water Division PROJECT LOCATION: (Water Meter & Radio Reader (Erts) PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: '.IMPROVEMENT LIFE: METER REPLACEMENT PROGRAM I2 Purchase quantities of meter reading equipment needed to continue with an ongoing meter replacement program; 650 new water meters with radio readers (Erts). These meters and erts will replace existing units that were installed over a period of seven years starting in the year 1999. Ext readers have a ten to fifteen year battery operation life before the battery goes dead. Water Division is in year four of a nine year replacement program. goal is to replace all 7500 water meters and erts by fiscal year 2024. American Water Works Association (AWWA) Standards recommend that water meters be replaced every ten years to keep up with the unaccountable water that is lost due to the age of the meter. Spring 2021 Annual Town Meeting $1110,000.00 �FY22 Operating Budget (Equipment „I 10 Years DEPARTMENT: DPW -Water Division PROJECT LOCATION: (Water Division 500B East Street PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: 1IMPROVEMENT LIFE: I2 Handheld Itron Meter Reading Devices water readers and mobile reader are over 12 years old and need to be updated. se units are the equipment that we need to read the water meters for billing Spring 2021 Annual Town Meeting] $150,10010.00 Water Enterp. Retained Earnings (Equipment 10 Years "Y r DEPARTMENT: DPW -Water Division PROJECT LOCATION: (Spring Street Water Mains PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: `IMPROVEMENT LIFE: I2 Main Repair project is to replace 3,080 ft of 6 -inch cast iron water main in Spring St. with h ductile iron main pipe. Spring 2021 Annual Town MeetingE $11,200,000.00 j Loan Order Infrastructure 140 years DEPARTMENT: 'DPW -Water Division PROJECT LOCATION: Water Division 500B East Street PROJECT: r� TrOT11i�6TA DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: ,IMPROVEMENT LIFE: 12 BACKHOE REPLACEMENT of one new heavy duty backhoe. The new backhoe equipment will be a worn-out 2002 John Deere backhoe that has been heavily used. (Spring 2021 Annual Town Meeting! $1150,000.00 Water Enter?. Retained Earnings (Equipment 10 Years n O DEPARTMENT: Electric PROJECT LOCATION: Ongoing Misc. Capital Items PROJECT: 1014 to] It] DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: Various Projects 12_ I budget item includes ongoing capital work such as pole replacement and lation of new wire for service reliability. (Spring 2021 Annual Town Meeting, $11,102,500 Capital Budget Various Project Types Various o { DEPARTMENT: Electric PROJECT LOCATION: 'Town -wide PROJECT: .�iMMUR DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: Fiber Commercialization Project 12 project will expand the fiber optic system in the industrial park and prepare for nercialization of fiber optic services. !Spring 2021 Annual Town Meetingi $1400,000.00 Capital Budget Infrastructure 1Various s nsno° DEPARTMENT: ;Electric PROJECT LOCATION: Town -wide PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: Distribution Auto Switches automatic switching equipment on distribution circuits to improve outage se time and outage restoration time. Spring 21 Annual Town Meeting $1300,000.00 Capital Budget (Infrastructure Various p — eas rAl DEPARTMENT: ;Electric PROJECT LOCATION: Town -wide PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: x IMPROVEMENT LIFE: �2 1 Replace truck #21 pickup truck (a 2012 F250 with 55,000 miles on it) based upon age and maintenance. Also replace the backhoe (1996) that has seen increasing maintenance costs in the past few years. Spring 2021 Annual Town Meeting $1150,000.00 (Capital Budget j ,vehicles I10 years ,� r N C y s"o 3 3 0 0 gjg 00 Q " DEPARTMENT: iMIS PROJECT LOCATION: (Town Hall, 6 Park Row, Mansfield, MA 02048 PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: of town's historical records - Building Department Priority 3 is a consecutive phase of the town's initiative to convert all paper documents and rds into digital format. Currently, the large amount of the documentation of Public lth, Conservation and Town Clerk's departments is readily available in digital form all public records are accessible via the town's website. inn this next phase, we .est that the Building department's records are also converted accordingly. Fiscal Year 2022 $1200,000.00 Free Cash (Unreserved Fund Other 140 years j o $,gym r T DEPARTMENT: DPW-PubB1dgs/SpecProj PROJECT LOCATION:iTown Mall _i PROJECT: FaTINT"T "i DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: 13 Wall Painting is to upgrade painting in various common areas of Town Hall. Fiscal Year 2022 1 A V130,000.00 Free Cash (Unreserved Fund Bal.),j Buildings 110 years to o t4 1d b DPW PuBgs/SpecPro� 1, 0111 DEPARTMENT: _ - _ PROJECT LOCATION: (Town Hall PROJECT: Security Monitoring System for Exterior and Interior (Closed Circuit) PRIORITY: DESCRIPTION: �3_ is to install CCTV cameras in all the common areas of Town Hall. FISCAL YEAR: Fiscal Year 2022 PROJECT COST: $180,000.00 PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: 'r Free Cash (Unreserved Fund Bal.) 1 Equipment _t 110 years �n f DEPARTMENT: ;DPW PubBidgs/SpecProj PROJECT LOCATION: (Library PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: 3. Library Upholstered Furniture & Blinds request is to replace the tired and worn furniture and blinds at the Library. z` o DEPARTMENT: ;DPW-PubBldgs/SpecProj PROJECT: PRIORITY: DESCRIPTION: PROJECT LOCATION: Library 13 Cameras and Panic Buttons The public library is a welcome space for all town residents • An increase in social issues such homelessness and the opioid crisis have brought more people into the library with issues beyond library staff s training • Libraries must be proactive in protecting staff and patrons in our space • The library building layout allows for certain areas to be out of sight from staff • The library is eager to protect our resources from theft and damage • The parking area is unmonitored and there have been past issues with unreported damage to vehicles Cost of security systems Prices for security camera systems fall in the range of $10,000 - $20,000 depending on the type of camera and the wiring needed (survey of other libraries in MA) FISCAL YEAR: iFiscal Year 2022 PROJECT COST: $120,000.00 PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: r There are vendors on the MHEC vendor list There are grants available through MITA FY22 Operating Budget JEqutpment I10 years QBE i-. Il. DEPARTMENT: !DPW-PubBdgs/SpecProj PROJECT LOCATION: Plymouth Street Fire PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: S IMPROVEMENT LIFE: Overhead Doors (3 FY2022 $1120,000.00 Free Cash (Unreserved Fund Bal) j lBuildings (20 years DEPARTMENT: DPW-PubBdgs/SpecProj PROJECT LOCATION: Fisher Richardson House PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: ,,IMPROVEMENT LIFE: Fisher Richardson Renovations 13_ request is for renovations to Fisher Richardson House following up on Engineers FY2022 $1150,000.00 1Free Cash (unreserved Fund Bal) _j f Buildings 130 years 0 v W. ASA 6 DEPARTMENT: iDPW-PubBldgs/Speoroj PROJECT LOCATION: (Town Hall PROJECT: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: i (Replace Trane Rooftop Package AC Units and Make -Up Air Units 2_ l is to replace the 4 roof top units which are original to the building in 1996. This be coordinated with the roofing project. PROJECT: PRIORITY: DESCRIPTION: DEPARTMENT: jDPW-PubBldgs/SpecProj PROJECT LOCATION: (Town Hall Remove and Replace Roof to Include Central Addition/Old Air Shafts 12 s is to remove the 2 -existing roofs that exists from the original building and remove air shafts below roof elevation and re-route with new PVC roofing system and asbestos contained in existing roofing system. FISCAL YEAR: I FY2022 PROJECT COST: $1700,000.00 PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: 1Loan Order Building 120 Years �Fcierr oar S v,.. ISDEPARTMENT: DPW-PubBldgs/SpecProj PROJECT LOCATION: (Mansfield Green (Recycling Center) PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: r.. Gate and Office Trailer 13 o U DEPARTMENT: ,POLICE PROJECT LOCATION: (POLICE DEPARTMENT PROJECT: Command Vehicle (replacement) PRIORITY: 13 DESCRIPTION: The capital project entails replacing a front fine four-wheel-drive SUV with radio, first responder, scene management equipment and other accessories for use by the Police Departments Command Staff. In order to minimize mechanical failures and out of service time, front-line SUVs should not be more than 5 to 6 years old. Mechanical failures, increased maintenance costs, and extended out of service times adversely impact Police Department operational effectiveness and increase community risk. The !purchase of this vehicle is part of a strategic plan to reduce the age of the Police Departments fleet and to create a sustainable plan for scheduled replacement of command vehicles. Specifically, the goal is to replace one command vehicle every year. This will ensure that command vehicles are never more than six years old. as command ,vehicles are replaced they will become staff cars for department business. This will (ensure that our staff cars would not be more than 7 to 10 years old. FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: will be purchased through PCC or GBPC Contract(s) county contracts; Mirak et or Liberty Chevrolet. Vehicle up -fitting will be done through MHQ, Norfolk Two way or other certified state contract up -fitter. Fiscal Year 2022 $55,000 Free Cash (Unreserved Fund Bal.) Vehicles 15 years j r o "A, I Ws� DEPARTMENT: ;POLICE PROJECT LOCATION: IPOLICE DEPARTMENT PROJECT: irk T6" DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: t>. CRUISER REPLACEMENTS AS PER CHIEF'S PLAN D-5 i 3_ _I Police Chief has created a cruiser replacement schedule based on usage and ities within the Police Department. This project is to replace three vehicles as Vehicle Replacement - $55,000 Detective Vehicle - $45,000 = $100,000. j FY2022 $45,000.00 !FY22 Operating Budget [Vehicles j 15 years ... F�AIJLT � ao X39 tFU 1S A10x DEPARTMENT: Fire Department PROJECT LOCATION: Both Fire Stations PROJECT: Mol[Y7;iYY'ill DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: 1 SCBA Gear Replacement Priority 3 SCBA The Mansfield Fire Department is preparing for the NFPA mandated replacement of aging and worn positive pressure self-contained breathing apparatus (SCBA). The SCBA purchase involves the SCBA harness, cylinder, face piece and a spare cylinder. We will specify that each unit be equipped with an integrated personal alert safety system and a buddy breathing capability for instances of fire fighter rescue. Each unit will be ordered to meet the current standard on self-contained breathing apparatus promulgated by the National Fire Protection Association. The cost associated with the SCBA is approximately $7095 per harness, $1040per cylinder, $305 per face piece for a total projected cost of $8440. The Department is requesting a purchase of forty four units in order to replace 100% of the Department's current SCBA. The total cost of SCBA replacement is projected at $480,000. FY2022 $ 480,000.00 Free Cash (Unreserved Fund Bal.) Equipment 5 years ` DEPARTMENT: Fire Department PROJECT LOCATION: Both Fire Stations PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: Vision 21 Replacement Master Box Priority 3 Vision 21 We addressed funding the replacement of the three Vision 21 Receiving units for the municipal fire alarm system several years ago through a town meeting vote that established an account for all radio and related technology needs with a fee of two hundred dollar per year for those with a radio box protecting their property. This removed the burden of a cost, to the majority of taxpayers, that was specific to radio system, the supervision of the property and fire protection systems and the associated service provided by the Fire Department. The three original units were installed in 2000 by Signal Communications of Woburn, Mass. Units are placed at the Public Safety Dispatch Center, the fire station at 500 East Street and the fire station at 10 Plymouth Street. These units receive and interpret signal from every Fire Alarm Radio Box transmitter throughout Mansfield, and are an integral part of the municipal fire alarm system. The three unit system provides for redundancy in the event of failure of one Vision 21, The current units function 24 hours a day, 365 days a year. The original units are regularly serviced by the manufacturer according to their recommendations and worked trouble free for the ten years. We have already replaced all units over a three year period but, in order to maintain compliance with the National Fire Protection Agency (NFPA) and their standards, the Fire Department must look into replacing these pieces of equipment every ten years to ensure that the municipal fire alarm system maintains its integrity. This request is based on that timetable and constitutes the ten year mark IWb26Wa $ 28,000.00 Fire Master Box Revolving Fund Equipment 20 years eFC1NCl„., IM ­ASANs� DEPARTMENT: ;Mansfield Schools PROJECT: PROJECT LOCATION: iDisttict-Wide s i [Paving and Concrete work PRIORITY: 13 DESCRIPTION: Project Overview: This capital request is for paving sidewalks and roadways within the district. m Over 25,000 Square Feet Lots: Over 125,000 Square Feet The paving will be a combination of Mill and Over lay, and full depth mill. The asphalt Twill be per the town specification, and will be performed by the awarded contractor. The majority or work will be Concrete work: j 25,000 plus square feet of sidewalk replacement ,c I Project Benefits: (Repair and improve cracks in concrete and asphalt to prevent injuries FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: ,IMPROVEMENT LIFE: r Fiscal Year 2022 f $1500,000.00 j jFree Cash (Unreserved Fund Bal) 1 [Infrastructure 10 years Py DEPARTMENT: Mansfield Schools PROJECT LOCATION: IMans6eld High School j PROJECT: Ir N .i"i DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: 1IMPROVEMENT LIFE: Controller CPriority 3 The Mansfield High School controller would work with the new master controller to allow us to control the boiler and chiller operations in the school. At this time we have no visibility into the schools HVAC FY2022 $1150,000.00 Free Cash (Unreserved Fund Bal.) Buildings 120 years 2 o. 9 DEPARTMENT: (Mansfield Schools PROJECT LOCATION: (District -Wide PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: ,!MPROVEM ENT LIFE: of Unit Ventilators Priority 3 act Overview: was a fall 2017 request to CIP which was deferred. Planned replacement of three which are the oldest throughout the district. This project was recommended by e & Bond in the 2016 CIP Recommendation Report. ect Benefits: allow us to follow recommended scheduled replacements. FY2022 $150,000.00 Free Cash (Unreserved Fund Bal.) Equipment �20years 9 ' tAID- s DEPARTMENT: Mansfield Schools PROJECT LOCATION: Jordan/Jackson Elementary School PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: lMPROVEMENT LIFE: Library Flooring ackson Library Carpet Replacement The current carpet in the Jordan/Jackson library has reached the end of its useful life. The carpet is bunching, torn, and worn through in spots. The Library is a hub of learning for the elementary school where activities often require students to sit on the floor. We are not providing a quality learning environment. This project would replace the existing carpet with new carpet squares that could be replaced more easily as they become worn. Fiscal Year 2022 $1100,000.00 Free Cash (Unreserved Fund Bal.) _I 11nfrastructure 1 10 years p1NCI /pl ,z 9 0' w U„ DEPARTMENT: Mansfield Schools PROJECT LOCATION: Qualters Middle School PROJECT: li�"i DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: Floor Refinish and Repaint Priority 3 plete strip of the existing finish, repair any damaged boards and repaint lines and refinish the surface. FY2022 I 3I100'000.00 Free Cash (Unreserved Fund Bal..) j Buildings 120 years w. a DEPARTMENT: ;Mansfield Schools PROJECT LOCATION: Mansfield High School PROJECT: S DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: nIMPROVEMENT LIFE: Replacement (Priority 3 i There is only I elevator at the High School and we have experienced more frequent breakdowns of the elevator. This unit has reached end of life. � o SAS AOAS " I DEPARTMENT: Mansfield Schools PROJECT LOCATION: (District -Wide PROJECT: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: improvements (Priority 3 :t Overview: roements and replacements of aging equipment and surface area based on 2016 completed by Playground Inspections of New England. t Benefits: improvements and general upkeep. FY2022 $ 250,000.00 'Free Cash (Unreserved Fund Bal.) Equipment 120 years DEPARTMENT: Mansfield Schools PROJECT LOCATION: (District -Wide PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: ;IMPROVEMENT LIFE: 13... Upgrades = lighting project has two components that are equally important to the l- The current lighting throughout the district is older fluorescent lighting and electronic ballast technology. Light bulbs are expensive to buy and cumbersome to dispose of at end of life. In many cases, the ballast cost alone can be as much as a new LED Fixture. The new lighting will dramatically reduce repair costs and will reduce the energy consumption in the district 2- We have students within the district that have medical conditions requiring LED lighting. We have been able to magnetic the accommodations to this point as they have been limited in scope. As the students move through the system the requirements will become more expansive and will include common areas like hallways, gyms, auditoriums, etc. We need to plan now to upgrade all schools with LED lighting FY2022 Annual Town Meeting j $150,000 !Free Cash (Unreserved Fund Bal) j Equipment j 120 years c J DEPARTMENT: ;DPW -Administration PROJECT: PROJECT LOCATION: Townwide Stormwater Permit Requirements PRIORITY: 1 _i DESCRIPTION: The new EPA permit requirements for stormwater discharges from Small Municipal Separate Storm Sewer System (MS4) in Massachusetts was delayed one (1) year but has now become effective July 2018. In 2016, we had Tighe & Bond develop a six (6) year implementation cost for this permit. Year one (1) was funded in FY 2018 and was held until FY 2019 because of the one (1) year delay in the permit by EPA. FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: We submitted a required Notice of Intent to EPA on September 28, 2018 and will continue to update the program. The schedule was budgetted as follows: FY'20 $109,000 IFY'21 $ 85,000 IFY'22 $ 87,000 FV23 $ 90,000 FV24 $ 90,000 !These costs will be updated as new information develops and may increase substantially Iif any contamination is found in our outfalls that requires removal. Fiscal Year 2022 $187,000 Free Cash (Unreserved Fund Bal.) (Other IN/A EcNcr �� 1 as o DEPARTMENT: DPW -Highway Division PROJECT LOCATION: (Various PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: Roadway/Sidewalk/Bridge and Parking Lot Maintenance 3 These funds are used in conjunction with Chapter 90 State Aid ($750,000+-) to maintain and/or reconstruct roadways, sidewalks, bridges and parking lots. examples of this work would be: Crack -sealing, trench repair, chip -sealing, overlays, milling and overlay, full depth reconstruction, handicap ramp reconstruction, sidewalk repairs, sidewalk replacement, bridge repairs, bridge replacement design and all work associated with the above. urgency here is that when not properly funded like years past, our roadway structure continues to deteriorate and minor repairs become reconstruction. Current averaged cost per square yard for various levels of work; Cost per mile of road at 24' wide $23,936.00 $80,960.00 $160,512.00 $247,808.00 $316,000.00 $542,080.00 $633,600.00 Est above is in the order that a road would deteriorate and our cost to repair would (FY2022 $12,000,000.00 Loan Order j Infrastructure 10 years Per SQ. YD. Patch and Crack -seal $1.70 Chip -seal $5.75 Thin overlay $11.40 Mill and Overlay Local $17.60 Mill and Overlay Arterial Collector $22.50 Reclaim Local $38.50 Reclaim Arterial Collector $45.00 Cost per mile of road at 24' wide $23,936.00 $80,960.00 $160,512.00 $247,808.00 $316,000.00 $542,080.00 $633,600.00 Est above is in the order that a road would deteriorate and our cost to repair would (FY2022 $12,000,000.00 Loan Order j Infrastructure 10 years � o U n DEPARTMENT: DPW -Sewer Division PROJECT LOCATION: iSewer Improvements PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: ISewer Collection System Improvements i3_ are proposing to annually fund sewer collection system improvements. This may ade sewer line replacement or rehabilitation or pump station improvements. If e funds are not fully spent in a given fiscal year they can be combined with another to complete a larger project. e . ' > r o^ a r .. OA5 DEPARTMENT: ;DPW -Water Division PROJECT LOCATION: Water Meter & Radio Reader (Errs) PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: ,IMPROVEMENT LIFE: 13 REPLACEMENT PROGRAM ase quantities of meter reading equipment needed to continue with an ongoing replacement program; 650 new water meters with radio readers (Erts). meters and erts will replace existing units that were installed over a period of seven years starting in the year 1999. t readers have a ten to fifteen year battery operation life before the battery goes dead. e Water Division is in year four of a nine year replacement program. e goal is to replace all 7500 water meters and erts by fiscal year 2024. ierican Water Works Association (AW WA) Standards recommend that water meters replaced every ten years to keep up with the unaccountable water that is lost due to the age of the meter. FY2022 $1110,000.00 j Water Enterp. Retained Earnings Equipment 10 Years j eons no`s' `� DEPARTMENT: DPW -Water Division PROJECT LOCATION: (Prescott Wells #8 & #9 500 East St. PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: Wells #8 & #9 Plant Study i3 1 Design the improvements needed to Prescott Well No. 8 and No. 9 including state permits, generator and two new wells. wells have high amounts of iron and manganese and are in the need of being :ed to be able to stay in pumping service. i oh DEPARTMENT: 'DPW -Water Division PROJECT LOCATION: (Water Treatment Plants PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: CONTROL SYSTEM UPGRADE & REPLACEMENTS 3_ ATER OPERATION CONTROL SYSTEM; Upgrade and replace the water System ad Data Control (SCADA) system that operates the treatment plants and well imping systems. FY2022 $1200,000 Water Retained Earnings IEquipment 120 DEPARTMENT: DPW -Water Division PROJECT LOCATION: DPW Water Division Headquarters i PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR PROJECT COST: PROPOSED FINANCING: EXPLANATION: 'IMPROVEMENT LIFE: 2 Water Pickup Trucks 13 I Purchase two (2) new pick up trucks with plow for the Water Division fleet. e -,v fleet vehicles will replace two older model trucks with high mileage: #56 - 2009 GMC Sierra #51 - 2013 Chevrolet Silverado o AS as DEPARTMENT: Electric PROJECT LOCATION: Ongoing Misc. Capital Items PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: ,IMPROVEMENT LIFE: r Various Projects 3 budget item includes ongoing capital work such as pole replacement and lation of new wire for service reliability. FY2022 $11,157,625.00 _ 'Capital Budget Various Project Types Various j �a ASO DEPARTMENT: Electric PROJECT LOCATION: iTown-wide PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: ,IMPROVEMENT LIFE: 13 Commercialization Project project will expand the fiber optic system in the industrial park and prepare for commercialization of fiber optic services. IFY2022 $1400,000.00 Capital Budget Infrastructure jVarious s9sP"rFo t° _ .. .. e DEPARTMENT: ;Electric PROJECT LOCATION: (Town -wide I PROJECT: �Y�A DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: Distribution Auto Switches 13 automatic switching equipment on distribution circuits to improve outage time and outage restoration time. ,FY2022 $1300,000.00 Capital Budget Infrastructure Various W r oqI S`U s DEPARTMENT: Electric PROJECT LOCATION: (Town -wide PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: 13 Vehicles ce car 9 (2008 Ford Taurus with 29,000 miles on it) which is the car used by the tions department based upon age and condition. Also replace truck 19 the dump (2003 Dump truck with 16,000 miles on it) based upon age and maintenance. FY2022 $1300,000.00 (Capital Budget Vehicles 10 years mo o 0 0 O 0 0 o 0 0 0 0 0 M 0 0 o 0 0 o 0 0 0000 0 o o c� 0 o 0 0 0 0 0 o 0 0 0 o 0 p p 0 0 0 0 0 0 0 o e o Q V1' VI 0 0 0 0 0 0 0 �l1 in N Vf' M N 0 O 0 .-I 0 «1 0 m� 0 V1 0 pf p p` o 0 0 0 0 0 0 0 0 o 0 0 0 0 0 0 O 0 O o O S O l0 m N N M N m V1 O fi N N Q 'i m N (I� 1p m VI l0 �A rl V1 M �/1 M tO 1R M N N VI 'i V1 m p O N Vf V1 O O O N V1 Ot m O O '1 Q M ei V M. H V M N OF 00 N N 0 N M _- N N N 'O0 N N N 10/! pp O ON O 0 p O O 00 p O S O O M M m O O N N vrvj �N/! N N N M N N 0 N H N N O O O N O N O N O O O O N N N N K OOO O O OtD OmN OO OON O ONN 008 O ON Oe'1 C.k O OO O O OO OO S PO- O c OO O OL!1 NO N N NOV1 p NON NOt0 u VOF M iO/F N h MO tlf N +oi. 0 0 0 0 8 0 S aoi� voi. m o m 0 O ,L6-i .oi ti ti h N 0 0 0 - H N O O C OOOO 0Vf OO p0OO00 Om p pO m O 0 0 r 0 O o O O O O O 0 OOOOO OOm . NlO0V0l N0YmI a0M/1 V0VII 1m0/1 VOVIV 1�ORO NOM M V0! V0F N0 N0 ONO O OnN N01 Nm O N0MN V0NI 10 N0M1p NMeOi N0 +OO NNN E H c v Y ao m ° w E E E o v a m E E u a c W a v c w m a° EJ o a s h vS w u a > 0 oE v a o E a o lovv u S w u a °. u P, E o ° h«sona am.oE iid ov- �Snar ¢ a o cva o 'c> Y Da w — E Y .eouu-Oo0n °uELL Ea > aa a E d c >¢ a a E n 0 0 0 0 0 0 auE a o uuuuuuo w0¢M xxo$ n a o Y D m o N N 00 a9 Q N N 9 9 Q C t c d °' i a 4 LL c c L Q x x 'c c �+ 3 00 00 N 00 0 0 $ 0 0 0 o O O O o 0 0 0 N N N O 8 O O 0 0 0 0 0 0 0 0 0 0 0 0 O O N 8 O O 0 0 0 0 0 0 O O O O O N rl OJ m N M N O M O N b K N N N N N aA N 0 N M M N N O O O00 0 00 0 N O N N O O O O O WW} N � 8O eNi N N N N N N N N O S O N 8 O O O N O o O cb O O O m O O o W n o ON O OOON N N N VN N N N O O O O O O O O N N N {I1 N N N b t0 O .ti r N V! N H O O N p N O O O LOy VOj OO O O C O O O O O' N {I1 Y} N N N 0 h N N N y O O O OO O 0 0 0 0 0 0 VF Vf N O N O 08 0 0 0 0 0 0 0 0 0 0 0O N -00000; 1 0W p O N O O coil 001 Vf M N b H VNl 'Oj`NN i/1 VF K G w n C 9 6 C C > N O 0 = oa E c a a a m rv° v Q M w o O s o o o E m a o 0 E °1x E.Nn a� N ° a a Ni� N h fj N N N Yn h N N C A F J N q N N o f I— W E E N E o r o Y N w z°oo z°C u°C u°.a333o e e Q Q y y m m c c ° > 0 u 0 u I I I I I I 1 171 1 ,r O K a J H a tg 0 Z LL 6' W_ �" 0 as >os, 04 A DEPARTMENT: ;Finance MIS PROJECT LOCATION: (Town -wide PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: GIS Flyover Update 3 Flyover for renewing aerial imagery data in the town's Geographic Information System. These data facilitate most current base map and digital orthophotography used by town authorities and public to get most current information of the built and natural landscape. Depending on the municipal growth of our community, such flyover service should be performed approximately but no later than every five years. 1 FY2023 I $165,000.00 Free Cash (Unreserved Fund Bal.)1 (Other I 15 years PROJECT: Iola �77Y11'21 DESCRIPTION: DEPARTMENT: DPW-PubBldgs/SpecProj j PROJECT LOCATION: ILibrary/COA Replace Carpet (Phased Approach Throughout Building) 1 3.._. .._. ._.. _.__.� is to do a phased approach to replace carpet in the Library much of which is 30+ old. FISCAL YEAR: 1FY2023 PROJECT COST: $1230,000.00 PROPOSED FINANCING: EXPLANATION: A�MPROVEMENT LIFE: Free Cash (Unreserved Fund Bal.) ,Buildings 120 years f s n, DEPARTMENT: (DPW-PubBldgs/SpecProj PROJECT LOCATION: (Library/COA PROJECT: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: '(IMPROVEMENT LIFE: Wall Painting 13 is for various ceiling and some wall painting at Library and COA. I FY2023 $130,000.00 1FY23 Operating Budget j 1 Buildings 120 years CANCt /� p .. moo, i DEPARTMENT: IDPW-PubBldgs/SpecProj PROJECT LOCATION: Library/COA PROJECT: �Y� DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: }IMPROVEMENT LIFE: Fan Coil Units, Liebont System and Outdoor Condensing Units 3 _ This is to replace Fan Coil units and Liebont Systems at Library/COA and exterior condensing units. FY2023 $100,000.00 Free Cash (Unreserved Fund Bal.) Equ pment �20 years �DEPARTMENT: DPW-PubBldgs/SpecPro* PROJECT LOCATION: (Library/COA PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: pIMPROVEMENT LIFE: 3_ Monitoring System for Exterior and Interior (Closed Circuit) is to supply a CCTV System at Library in common areas and parking lots. o AlA DEPARTMENT: JDPW-PubB1dgs/SpecProj PROJECT LOCATION: (Library / COA PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: Fite Alarm Upgrade / Panel Replacement 13 4 i o � DEPARTMENT: jDPW PubBldgs/SpecProj PROJECT LOCATION: Library / Council On Aging PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: Parking Lot Lighting Upgrade 13 request is to fund an upgrade of the Parking Lot Lighting for the Library/COA ding which is presently a unix of 3 separate lighting systems; MMED flood lights, inal equipment parking lot lights fed from the Library, and 4 parking lot lights fed n Memorial Park Fields. This project would complete the plan when the Parking was constructed in 2018; that plan made provisions for new lighting and 1 FY2023 E $180,000.00 Free Cash (Unreserved Fund Bal) Infrastructure 125 Years ; 9t�0 1 DEPARTMENT: POLICE PROJECT LOCATION: (POLICE DEPARTMENT PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: Vehicle (replacement) The capital project entails replacing a front line four-wheel-drive SUV with radio, first responder, scene management equipment and other accessories for use by the Police Departments Command Staff. In order to minunize mechanical failures and out of service time, front-line SUVs should not be more than 5 to 6 years old. Mechanical failures, increased maintenance costs, and extended out of service times adversely impact Police Department operational effectiveness and itrerease community risk. The purchase of this vehicle is part of a strategic plan to reduce the age of the Police Departments fleet and to create a sustainable plan for scheduled replacement of command vehicles. Specifically, the goal is to replace one command vehicle every year. This will ensure that command vehicles are never more than six years oi& is command vehicles are replaced they Nvill become staff cars for department business. This will ensure that our staff cars would not be snore than 7 to 10 yeas old. will be purchased through PCC or GBPC Contrict(s) county contracts; blirak et or Liberty Chevrolet. Vehicle up -fitting will be done through 1VI1IQ, Not -folk Two way or other certified state contract up -fitter. FY2023 $155,000 Free Cash (Unreserved Fund Bal..) Vehicles 5 years moo„ DEPARTMENT: ,POLICE PROJECT LOCATION: (POLICE DEPARTMENT PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: jIMPROVEMENT LIFE: CRUISER REPLACEMENTS AS PER CHIEF'S PLAN T-2 3 j The Police Chief has created a cruiser replacement schedule based on usage and priorities within the Police Department. This project is to replace one vehicle as follows: Transport Vehicle T-2 - $62,500 = $62,500. aucr � OASA DEPARTMENT: POLICE PROJECT LOCATION: (POLICE DEPARTMENT PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: ?IMPROVEMENT LIFE: EMERGENT LESS THAN LETHAL TECHNOLOGIES 3 i e Police Department remains committed to the investment in less than lethal hnologies. The Department endeavors to continue efforts at acquiring, training and ;et level utilization of emergent less than lethal technologies. Technologies such as ;er(s) and 40mm low velocity impact rounds, have resulted in the (1) preservation of fife reduced officer and municipal liability (3) lowered the instances of officer cries. Funds will be used to continue with both the Taser and 40mm program and Ler emergent technology. t DEPARTMENT: Fire Department PROJECT LOCATION: Town -wide PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: ')IMPROVEMENT LIFE: Rescue 33 Ambulance Priority 3 Rescue 33 Rescue 33 is a 2014 Ford E450, Road Rescue ambulance with 117304 miles. This vehicle has needed service and typically, as age and usage increases and the mileage goes well over hundred thousand, cost of repairs increases dramatically. Other items within the ambulance are also reaching the end of their life cycle. This is right in line with the ambulance revolving account schedule, established at town meeting in 2011 for this explicit purpose. The cost of replacing Rescue 33 and several key pieces of equipment is estimated to be at $350,000. Rescue 33 has run front line but will move to reserve status in the Fall of 2019 and will remain in that capacity until its projected replacement in FY23. This ambulance will be paid for from the Ambulance Revolving Fund and the General Fund. FY2023 $ 350,000.00 Ambulance Rev Fund/Free Cash Vehicles 10 years 0 0 ri DEPARTMENT: Fire Department PROJECT LOCATION: Town -wide PROJECT: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: )IMPROVEMENT LIFE: Squad 4 Replacement Priority 3 5 uad 4 Squad 4 is a 2005 Ford F550 with a flatbed body which houses a 400 gallon water tank and pump. This vehicle is used for brush fires, is in very good condition and has only 7972 miles. Replacement may not be warranted in FY21 but some refurbishment to the pump and body may be ideal to extend the working life of a solid piece of equipment. The cost to replace this vehicle is currently estimated to be $150,000 but a refurb would be considerably less. FY2023 $ 61,000 Free Cash (Unreserved Fund Bal.) Vehicles 10 years 2 O' DEPARTMENT: Fire Department PROJECT LOCATION: Town -wide PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: pIMPROVEMENT LIFE: 12 -lead Auto Defibrillators Priority 3 X -Series 12 lead Cardiac Monitor Each ambulance is equipped with an Automatic External Defibrillator that allows paramedics the ability to apply a 12 lead EKG to monitor and identify the nature of heart activity which determines treatment level and drug intervention. They are further able to share this specific information with the physician while still at the scene. This specific equipment is the single most Important tool on the ambulance and its failure would be catastrophic to patient care and our ability to maintain our ambulance license. The life expectancy for this equipment is five to eight years. The purchase allowed the department to maintain one newer model on each front line ambulance with the older model serving the reserve vehicle. In the event of a failure of any of the three, there would be no downtime in our ability to provide ALS care. The cost of this equipment is estimated at $35,000. FY2023 $ 35,000.00 Free Cash (Unreserved Fund Bal.) Equipment 5 years o o � sF sAoz DEPARTMENT. Fire Department PROJECT LOCATION: Both Fire Stations PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: )IMPROVEMENT LIFE: Vision 21 Replacement Master Box Priority 3 Vision 21 We addressed funding the replacement of the three Vision 21 Receiving units for the municipal fire alarm system several years ago through a town meeting vote that established an account for all radio and related technology needs with a fee of two hundred dollar per year for those with a radio box protecting their property. This removed the burden of a cost, to the majority of taxpayers, that was specific to radio system, the supervision of the property and fire protection systems and the associated service provided by the Fire Department. The three original units were installed in 2000 by Signal Communications of Woburn, Mass. Units are placed at the Public Safety Dispatch Center, the fire station at 500 East Street and the fire station at 10 Plymouth Street. These units receive and interpret signal from every Fire Alarm Radio Box transmitter throughout Mansfield, and are an integral part of the municipal fire alarm system. The three unit system provides for redundancy in the event of failure of one Vision 21. The current units function 24 hours a day, 365 days a year. The original units are regularly serviced by the manufacturer according to their recommendations and worked trouble free for the ten years. We have already replaced all units over a three year period but, in order to maintain compliance with the National Fire Protection Agency (NFPA) and their standards, the Fire Department must look into replacing these pieces of equipment every ten years to ensure that the municipal fire alarm system maintains its integrity. This request is based on that timetable and constitutes the ten year mark FY2023 $ 28,000.00 Fire Master Box Revolving Fund Equipment 20 years PROJECT: PRIORITY: DESCRIPTION: DEPARTMENT: Fire PROJECT LOCATION: East St. Fire Station FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: (IMPROVEMENT LIFE: Lucas Machine Auto Chest Compressor Priority 3 Autopudse/Lucaas This device greatly enhances resuscitation efforts, effective sustained delivery of cardiac compression and is customized to a patient's size and age. Two original units were purchased in 2007-2008 at no cost to the town. One replacement has been purchased since. Life span of the units is approximately five to ten years. The cost is approximately $15,000 per unit. We had planned to move an older model to the reserve ambulance thus equipping all three however due to issues with one unit we were able to use it as trade in value to obtain a new unit which is called a Lucas machine at the cost of $15,000. This unit has been in service and has already aided firefighters in saving a person in cardiac arrest. A Lucas machine will be part of the equipment needed with the purchase of the new ambulance in FY23. The cost is estimated to be $15, 000. FY2023 $ 15,000.00 FY23 Operating Budget Equipment 5 years � r n, } y DEPARTMENT: Mansfield Schools PROJECT LOCATION: (Mansfield High School & Robinson ES PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: ,IMPROVEMENT LIFE: 11'riority 3 Roof repair expense is continuing to climb, and the roofs will be at the end of the useful life. This project is likely to be eligible for reimbursement from the Mass. School Building Authority. FY2023 X12,300,000.00 ILoan Order (Buildings 125years IL AS g* DEPARTMENT: !Mansfield Schools. PROJECT LOCATION: (Mansfield High School PROJECT: Cft , r*T,. iulTJl DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: !Roof HVAC Replacement i !Priority 3 i -�- . # - . - . • s^ -- replaced. FY2023 $100,000.00 j (Free Cash (Unreserved Fund Bal.) Buildings i20 years b s o,Fw DEPARTMENT: Mansfield Schools PROJECT LOCATION: IQualters Middle School PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: JIMPROVEMENT LIFE: HVAC Controller (Priority 3 1 The QMS controller would work with the new master controller to allow us to control the boiler and chiller operations in the school. At this time, we have no visibility into the schools HVAC operations. IFY2023 $1150,000.00 (Free Cash (Unreserved Fund Bal) Buildings (20 Years ay,;QC1111`i �� ' ry v O' As DEPARTMENT: !Mansfield Schools j PROJECT LOCATION: !District -Wide PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: Replacement of Unit Ventilators Priority 3 pct Overview: was a fall 2017 request to CIP which was deferred. Planned replacement of three which are the oldest throughout the district. Tlus project was recommended by e & Bond in the 2016 CIP Recommendation Report. ect Benefits: allow us to follow recommended scheduled replacements. FY2023 r $50,000.00 Free Cash (Unreserved Fund Bal.) j Equipment �20 years I J o'. 6 4 r DEPARTMENT: Mansfield Schools PROJECT LOCATION: IJordan/Jackson PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: ?IMPROVEMENT LIFE: of Sewer Ejector Pump - Construction Phase (Priority 3 ect Overview: was a request to CIP in the fall of 2017 but was deferred. Repairs were made in 8 that significantly helped. Long term needs are to replace the pump but our ultants have had differing opinions on when to replace it. ction phase will consist of work needed to repair, upgrade or replace the system. FY2023 $500,000.00 (Loan Order (Equipment 120years J , SAS A D\� e4 a� DEPARTMENT: Mansfield Schools PROJECT LOCATION: (District -Wide PROJECT: 19, 0bI DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: 4NIPROVEMENT LIFE: Bathroom Renovations lPriority 3 Project Overview: This request was made to CIP in the fall of 2017 but was deferred. School bathrooms are aging and need to be renovated. Update fixtures and furnishings to be more student friendly. Update the floor to make it more efficient to clean. IM023 ] ,I 100,000.00 (Free Cash (Unreserved Fund Bala } j Budding 20 years rcq oAs DEPARTMENT: iMansfield Schools PROJECT LOCATION: District -Wide PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: 21MPROVEMENT LIFE: Lighting Upgrades 13 Upgrades: lighting project has two components that are equally important to the 1- The current lighting throughout the district is older fluorescent lighting and electronic ballast technology. Light bulbs are expensive to buy and cumbersome to dispose of at end of life. In many cases, the ballast cost alone can be as much as a new LED Fixture. The new lighting will dramatically reduce repair costs and will reduce the energy consumption in the district 2- We have students within the district that have medical conditions requiring LED lighting. We have been able to magnetic the accommodations to this point as they have been limited in scope. As the students move through the system the requirements will become more expansive and will include common areas like hallways, gyms, auditoriums, etc. We need to plan now to upgrade all schools with LED lighting DEPARTMENT: Mansfield Schools PROJECT LOCATION: (Roland Green School PROJECT: loll :iYll'7 DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: )IMPROVEMENT LIFE: Feasibility Study (Priority 3 Feasibility study to determine the decommissioning of the building, what hazards exist and what would be needed to move the school to a new location. IFY2023 $I50,000.00 (Free Cash (Unreserved Fund Bal.) (Design [NSA � V DEPARTMENT: iDPW-Administration i PROJECT LOCATION: (Townwide PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: iIMPROVEMENT LIFE: I3 Permit Requirements new EPA permit requirements for stormwater discharges from Small Municipal rate Storm Sewer System (MS4) in Massachusetts was delayed one (1) year but has become effective July 2018. In 2016, we had Tighe & Bond develop a six (6) year ementation cost for this permit. Year one (1) was funded in FY 2018 and was held FY 2019 because of the one (1) year delay in the permit by EPA. submitted a required Notice of Intent to EPA on September 28, 2018 and will tinue to update the program. The schedule was budgetted as follows: $109,000 $ 85,000 $ 87,000 $ 90,000 $ 90,000 hese costs will be updated as new information develops and may increase any contamination is found in out outfalls that requires removal. IFY2023 $190,000 Free Cash (Unreserved Fund Bal.) j !Other (NSA ee"Our r o` p ' Y'' , DEPARTMENT: IDPW-Highway Division PROJECT LOCATION: (Various PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: 'f[MPROVEMENT LIFE: and Parking Lot Maintenance Urgent funds are used in conjunction with Chapter 90 State Aid ($750,000+-) to in and/or reconstruct roadways, sidewalks, bridges and parking lots. examples of this work would be: sealing, trench repair, chip -sealing, overlays, milling and overlay, full depth traction, handicap ramp reconstruction, sidewalk repairs, sidewalk replacement, repairs, bridge replacement design and all work associated with the above. urgency here is that when not properly funded like years past, our roadway Lstructure continues to deteriorate and minor repairs become reconstruction. averaged cost per square yard for various levels of work; Cost per mile of road at 24' wide $23,936.00 $80,960.00 $160,512.00 $247,808.00 $316,000.00 $542,080.00 $633,600.00 list above is in the order that a road would deteriorate and our cost to repair would FY2023 $12,000,000.00 Loan Order Infrastructure 10 years Per SQ. YD. h and Crack -seal $1.70 -seal $5.75 k overlay $11.40 and Overlay Local $17.60 and Overlay Arterial Collector $22.50 aim Local $38.50 aim Arterial Collector $45.00 Cost per mile of road at 24' wide $23,936.00 $80,960.00 $160,512.00 $247,808.00 $316,000.00 $542,080.00 $633,600.00 list above is in the order that a road would deteriorate and our cost to repair would FY2023 $12,000,000.00 Loan Order Infrastructure 10 years DEPARTMENT: DPW -Sewer Division PROJECT LOCATION: (Sewer Improvements PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: b I3 Collection System Improvements are proposing to annually fund sewer collection system improvements. This may ade sewer line replacement or rehabilitation or pump station improvements. If e funds are not fully spent in a given fiscal year they can be combined with another to complete a larger project. IFY2023 $1200,000.00 (Sewer Retained Earnings j (Other 10 years � o u DEPARTMENT: DPW -Water Division PROJECT LOCATION: tFoolish Hill Underground Storage Tank PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: !IMPROVEMENT LIFE: Design & Install Membrane Cover at Foolish Hill Tank 3 and installation of an exterior membrane cover on top of the 2MG Foolish Hill FY2023 $1500,000.00 Loan Order (Infrastructure 130 Years storage tank, including repairs. -' FcNCI p ,a DEPARTMENT: DPW -Water Division PROJECT LOCATION: (Prescott Wells No. 8 and No. 9 PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: `''IIMPROVEMENT LIFE: Phase Improvements Prescott Wells #8 and #9 (3 _1 1 -tion Phase: Implementation of pumping design improvements based on design recommendations for these wells. a i p 3Oh p� 4 DEPARTMENT: DPW -Water Division PROJECT LOCATION: Water Meter & Radio Reader (Errs) PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: 3 REPLACEMENT PROGRAM ase quantities of meter reading equipment needed to continue with an ongoing replacement program; 650 new water meters with radio readers (Errs). These meters and erts will replace existing units that were installed over a period of seven years starting in the year 1999. Err readers have a ten to fifteen year battery operation life before the battery goes dead. Water Division is in year four of a nine year replacement program. goal is to replace all 7500 water meters and erts by fiscal year 2024. American Water Works Association (AW WA) Standards recommend that water meters be replaced every ten years to keep up with the unaccountable water that is lost due to the age of the meter. FY2023 $11 10,000.00 (Water Enterp. Retained Earnings (Equipment j 110 Years DEPARTMENT: DPW -Water Division PROJECT LOCATION: IDPW Water Division Headquarters PROJECT: !�� DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: Water Replace Truck #55 3_ one new utility truck for the Water Division fleet. fleet vehicle will replace an older long body model utility truck with high mileage: #55 - 2008 Ford 550 FY2023 $1180,000.00 (Water Enterp. Retained Earnings ;Vehicles 10 Years t� ory 09 o co sAo, DEPARTMENT: DPW -Water Division PROJECT LOCATION: DPW Water Division Headquarters PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: Water Pickup Trucks i3 i two (2) new pick up trucks with plow for the Water Division fleet. fleet vehicles will replace two older model trucks with high mileage: #56 - 2009 GMC Sierra #51 - 2013 Chevrolet Silverado FY2023 $190,000.00 Water Enterp. Retained Earnings Vehicles 110 Years Y os DEPARTMENT: IElectric PROJECT LOCATION: Ongoing Misc. Capital Items PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: f Various Projects I3 budget item includes ongoing capital work such as pole replacement acid Ration of new wire for service reliability. IFY2023 3[1,215,506.00 E [Capital Budget j IVarious Project Types IVarious �""INCI' o DEPARTMENT: Electric PROJECT LOCATION: Town -wide PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: 'II ROVEMENT LIFE: Fiber Commercialization Project 3 project will expand the fiber optic system in the industrial park and prepare for of fiber optic services. FY2023 $1400,000.00 11 1 Capital Budget Infrastructure IVarious DEPARTMENT: jEllectric PROJECT LOCATION: (Town -wide PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: \jII IPROVEMENT LIFE: 3 Auto Switches automatic switching equipment on distribution circuits to improve outage time and outage restoration time. FY2023 _ _I $1300,000.00 Capital Budget Infrastructure (Various 4 Q`�cvacr r� " L 9 U r AAVS' DEPARTMENT: JElectric PROJECT LOCATION: (Town -wide PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: jN[PROVEMENT LIFE: New Vehicles 3 _! pickup truck 10 (2012 F250 with 27,000 miles on it) which is used by station s based upon age. Also replace truck 23 (2000 with 22,000 miles on it) a digger based upon age and maintenance. FY2023 s $350,000.00 Capital Budget Vehicles (10 Yeats S N O O S N O O O S O O N S N N N N N N 0 0 N N N OI Ol Q N N N M e'I N N Ifl M N N N N H N N N N N N N N C O �• O h 0 O om 0 0 0 N 0 N 0 N 0 00 0 O o O O N o N 0 N G O O S S d O 0 O O M M M d V i V a C Q � N 0 S S O N N N E O O O O O O O ,W A N NeNi eNi 6 d a N N N N N C d C W 'gyp Q: 0 S S C N N h h N N N N H N > C O h N N N N N N N N O W W �M' rl N N 4L V°F N m N N N O S O N N N N p O O S m Oa N N N O O 9 O O O O O O O O 6 0 6 Q u ¢ 0 O N 0m O S 0 O 0 0 0 S 0 S 0 O 0 S 0 N o N O N o N 00 p N O O d&60 O O 0�1 E NO N M N Villi YNf i1 iNCR NN N �•' NN N N d O y� Q a` G W 'O O N « RE O N « a s O m a+ O m W E o w w w E o ¢ E E o K E ON S m � 12.2 U O C n C O d y C a a F w S 1- a O d F > E t r c 0" OR a uc d a o z o lX3tn3 d 3 3 MM d m 0 0 a33 3 3 O N O N O O N N N 0 O 0 O 0 N w O O N O N N N N lD N O O 0V O tp ryOry1� h M 0 N N V0Y N N 0 N O O O O O O N N O N W 10 O O O tp Y N N N tp N N M ttOi O N ryO�I N O h Y1 N h N H ON pN N W S O O O M M N N N N N N vin N N H N N N N S O O M N N N H N N N O O H N H VO! {OI! N N O O O W N O O N Lt h N H N i0R N N 00 0 0 N O O O N N tD O O O O {p V N H 4%� M O N 0 r1 I� N a pp a N � > E o 0 46 46 o m m o E F ono O w E V'� c Z D O 2 Lzz Z C c_ C_ x Y O D a d w w n n 0 0 xrF DEPARTMENT: DPW-PubBidgs/SpecProj PROJECT LOCATION: (Library PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: ,JMPROVEMENT LIFE: Library Meeting Room 13 L and upgrade the painting, flooring and lighting in the Library Meeting Room. FY2024 $125,000.00 (Free Cash (Unreserved Fund Bal,)_, Buildings 125 years CINDY � � 2 0 DEPARTMENT: POLICE PROJECT LOCATION: [POLICE DEPARTMENT l PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: JMPROVEMENT LIFE: CRUISER REPLACEMENTS AS PER CHIEF'S PLAN COMMAND (3 Police Chief has created a cruiser replacement schedule based on usage and rides within the Police Department. This project is to replace a vehicle as follows: Command Vehicle Replacement - $55,000 = $55,000. IFY2024 I $155,000.00 [ (Free Cash (Unreserved Fund Bal.) [Vehicles j 15 years [ i �t o � V DEPARTMENT: (POLICE PROJECT LOCATION: (POLICE DEPARTMENT PROJECT: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: a IMPROVEMENT LIFE: LESS THAN LETHAL TECHNOLOGIES Police Department remains committed to the investment in less than lethal anologies. The Department endeavors to continue efforts at acquiring, training and !et level utilization of emergent less than lethal technologies. Technologies such as ;er(s) and 40mm low velocity impact rounds, have resulted in the (1) preservation of life reduced officer and municipal liability (3) lowered the instances of officer tries. Funds will be used to continue with both the Taser and 40mm program and emergent technology. FY2024 $1 15,000.00 Free Cash (Unreserved Fund Bal.) (Equipment 110 years s o „ t4 x�, Fins noes DEPARTMENT: IPOLICE PROJECT LOCATION: (POLICE DEPARTMENT PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: ,IMPROVEMENT LIFE: CRUISER REPLACEMENTS AS PER CHIEF'S PLAN D-3 j 3 Police Chief has created a cruiser replacement schedule based on usage and ities witivn the Police Department. This project is to replace a vehicle as follows: Detective Vehicle Replacement - $45,000 = $45,000. o' F �^ QASA�\s . DEPARTMENT: Fire Department PROJECT LOCATION: Both Stations PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: ,IMPROVEMENT LIFE: F Thermal Imaging Cameras replacement with second set Thermal imagers are used for search and rescue, to identify fire spread, locations and heat sources. They are an important tool in all fire calls and are used everyday to enhance the safety of the fire fighters and the ability to find and reach victims in fire conditions. The thermal imager further serves to reduce damage to structures by isolating a specific area of a heat source, even in walls. More efficient updated technology with enhanced graphics and a reduced more manageable size, like most electronic equipment, greatly improves the capabilities during the most critical of times. Currently only the engines are equipped with these units. In replacing these cameras we will be looking to add one to the Tower Truck as well. The cost of the cameras is estimated at $10,000 each. This is considered a priority three purchase. FY2024 $ 20,000 Free Cash (Unreserved Fund Bal.) Equipment 10 years i z o DEPARTMENT: Fire Department PROJECT LOCATION: Town -wide PROJECT: I01011163 YY'2 DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: ,IMPROVEMENT LIFE: Squad 5 Replacement Priority 3 Sduad 5 Squad 5 is a 2005 Ford F550 with a flatbed body which houses a 400 gallon water tank and pump. This vehicle is used for brush fires, is in very good condition and has only 7972 miles. Replacement may not be warranted in FY21 but some refurbishment to the pump and body may be ideal to extend the working life of a solid piece of equipment. The cost to replace this vehicle is currently estimated to be $150,000 but a refurb would be considerably less. FY2024 $ 150,000.00 Free Cash (Unreserved Fund Bal.) Vehicles 10 years Q �aNur �1 / �. o �r ♦� ��A9A0A5� DEPARTMENT: Fire Department PROJECT LOCATION: Both Fire Stations PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: ,,,IMPROVEMENT LIFE: Vision 21 Replacement Master Box Priority 3 Vision 21 We addressed funding the replacement of the three Vision 21 Receiving units for the municipal fire alarm system several years ago through a town meeting vote that established an account for all radio and related technology needs with a fee of two hundred dollar per year for those with a radio box protecting their property. This removed the burden of a cost, to the majority of taxpayers, that was specific to radio system, the supervision of the property and fire protection systems and the associated service provided by the Fire Department. The three original units were installed in 2000 by Signal Communications of Woburn, Mass. Units are placed at the Public Safety Dispatch Center, the fire station at 500 East Street and the fire station at 10 Plymouth Street. These units receive and interpret signal from every Fire Alarm Radio Box transmitter throughout Mansfield, and are an integral part of the municipal fire alarm system. The three unit system provides for redundancy in the event of failure of one Vision 21. The current units function 24 hours a day, 365 days a year. The original units are regularly serviced by the manufacturer according to their recommendations and worked trouble free for the ten years. We have already replaced all units over a three year period but, in order to maintain compliance with the National Fire Protection Agency (NFPA) and their standards, the Fire Department must look into replacing these pieces of equipment every ten years to ensure that the municipal fire alarm system maintains its integrity. This request is based on that timetable and constitutes the ten year mark FY2024 $ 28,000.00 Fire Master Box Revolving Fund Equipment 20 years 1e�a� o. o _ pAs. DEPARTMENT: Mansfield Schools PROJECT LOCATION: High School PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: „IMPROVEMENT LIFE: Replace Turf Field (Priority 3 i :ct Overview: turf was last replaced in 2013 with a 10 year life span. xt Benefit: district would like to stagger the costs and efforts of the turf field and track .ce. The longterm benefits include easier maintenance, aesthetics and safety. mw . o 0 4 DEPARTMENT: Mansfield Schools PROJECT LOCATION: (District -wide PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: Replace Dumptruck Priority 3 Currently, we have a used dump truck that we received from the DPW, the truck will need replacement in FY24. *Y2024 I $90,000.00 (Free Cas h(Unreser ved Fund Bal.) (Vehicles j 10 years J, r. � v � PqJ 1 ,. FOASAO\S ._ ._ .. aw DEPARTMENT: !Mansfield Schools PROJECT LOCATION: District -Wide PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: pIMPROVEMENT LIFE: Lighting Upgrades 13 I Upgrades: lighting project has two components that are equally important to the 1- The current lighting throughout the district is older fluorescent lighting and electronic ballast technology. Light bulbs are expensive to buy and cumbersome to dispose of at end of life. In many cases, the ballast cost alone can be as much as a new LED Fixture. The new lighting will dramatically reduce repair costs and will reduce the energy consumption in the district We have students within the district that have medical conditions requiring '13 lighting. We have been able to magnetic the accommodations to this int as they have been limited in scope. As the students move through the >tem the requirements will become more expansive and will include mmon areas like hallways, gyms, auditoriums, etc. We need to plan now to grade all schools with LED lighting 1FY2024 Annual Town Meeting $1100,000 1Free Cash (Unreserved Fund Bal.) _1 Equipment 120 years i J o �gtEOAsAVSte �DEPARTMENT: DPW -Administration PROJECT LOCATION: ITownwide PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: (3 Permit Requirements new EPA permit requirements for stormwater discharges from Small Municipal rate Storm Sewer System (MS4) in Massachusetts was delayed one (1) year but has become effective July 2018. In 2016, we had Tighe & Bond develop a six (6) year ementation cost for this permit. Year one (1) was funded in FY 2018 and was held FY 2019 because of the one (1) year delay in the permit by EPA, submitted a required Notice of Intent to EPA on September 28, 2018 and will tinue to update the program. The schedule was budgetted as follows: $109,000 $ 85,000 $ 87,000 $ 90,000 $ 90,000 hese costs will be updated as new information develops and may increase substantially any contamination is found in our outfalls that requires removal. I FY2024 $190,000 (Free Cash (Unreserved Fund Bal.) I (Other _i (N/A ..'ry11 "Nur >I v, q v sao�ry DEPARTMENT: ;DPW -Highway Division r PROJECT LOCATION: (Various PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: ,IMPROVEMENT LIFE: Roadway/Sidewalk/Bridge and Parking Lot Maintenance i (Urgent funds are used in conjunction with Chapter 90 State Aid ($750,000+-) to in and/or reconstruct roadways, sidewalks, bridges and parking lots. examples of this work would be: sealing, trench repair, chip -sealing, overlays, milling and overlay, full depth duction, handicap ramp reconstruction, sidewalk repairs, sidewalk replacement, repairs, bridge replacement design and all work associated with the above. urgency here is that when not properly funded like years past, our roadway structure continues to deteriorate and minor repairs become reconstruction. ent averaged cost per square yard for various levels of work; Per SQ. YD. Cost per mile of road at 24' wide h and Crack -seal $1.70 $23,936.00 -seal $5.75 $80,960.00 .overlay $11.40 $160,512.00 and Overlay Local $17.60 $247,808.00 and Overlay Arterial Collector $22.50 $316,000.00 aim Local $38.50 $542,080.00 aim Arterial Collector $45.00 $633,600.00 Est above is in the order that a road would deteriorate and our cost to repair would FY2024 $2,000,000.00 Loan Order Infrastructure 10 years o yr e v DEPARTMENT: DPW -Sewer Division PROJECT LOCATION: (Sewer Improvements PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: (Sewer Collection System Improvements 13 are proposing to annually fund sewer collection system improvements. This may ide sewer line replacement or rehabilitation or pump station improvements. If e funds are not fully spent in a given fiscal year they can be combined with another to complete a larger project. Q�p\NCY �t J S G.. DEPARTMENT: ;DPW -Water Division I PROJECT LOCATION: j Stearns Ave PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: jMPROVEMENT LIFE: 3_ Avenue Water Main Replacement .ce 4,700 feet of six-inch AC water main locating in Stearns Avenue (from Bonney to Carriage House Lane) with 8 -inch ductile iron main. Replace water service the main to the curb box when needed. IFY2024 $11,300,000 (Loan Order j 11nfrastructure 150 i 2 O P DEPARTMENT: DPW -Water Division PROJECT: PRIORITY: DESCRIPTION: PROJECT LOCATION: Water Meter & Radio Reader (Errs) 3.. REPLACEMENT PROGRAM zhase quantities of meter reading equipment needed to continue with an ongoing er replacement program; 650 new water meters with radio readers (Erts). se meters and erts will replace existing units that were installed over a period of m years starting in the year 1999. readers have a ten to fifteen year battery operation life before the battery goes dead. Water Division is in year four of a nine year replacement program. goal is to replace all 7500 water meters and erts by fiscal year 2024. ierican Water Works Association (AW WA) Standards recommend that water meters replaced every ten years to keep up with the unaccountable water that is lost due to age of the meter. FISCAL YEAR: FY2024 PROJECT COST: $1100,000.00 PROPOSED FINANCING: EXPLANATION: JMPROVEMENT LIFE: FY24 Water Operating Budget 1Egwpment 110 Years tie , snob. DEPARTMENT: IDPW-Water Division PROJECT LOCATION: (Water Division Fleet - 500b East St. PROJECT: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: Replace Gate Valve Operating Equipment �3 - Water Division uses its 2012 gate valve operating machine on a regular basis to n and close main gates. The equipment is also used to clean out material located in main gate box. to general wear and tear over the past 7 years it needs to be replaced. z o ' n DEPARTMENT: DPW -Water Division PROJECT LOCATION: DPW Water Division Headquarters PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: (IMPROVEMENT LIFE: Water Replace Truck #55 one new utility truck for the Water Division fleet. fleet vehicle will replace an older long body model utility truck with high mileage: #55 - 2008 Ford 550 o.'SAoc DEPARTMENT: Electric PROJECT LOCATION: (Ongoing Misc. Capital Items PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: )IMPROVEMENT LIFE: Various Projects 13- budget budget item includes ongoing capital work such as pole replacement and Ilation of new wire for service reliability. 1FY2024 $11,2761,21812, (Capital Budget (Various Project Types Various _.� o- P°F� snosc DEPARTMENT: Electric PROJECT LOCATION: IMMED Office PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: �MPROVEMENTLIFE: Office Improvements I 3 Office Improvements at the MMED office. I FY2024 $150,000.00 1Capital Budget Building 120 DEPARTMENT: Electric PROJECT LOCATION: (Town -wide PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: Fiber Commercialization Project project will expand the fiber optic system in the industrial park and prepare for of fiber optic services. z o o s n, DEPARTMENT: iElectric PROJECT LOCATION: (Town -wide i PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: New Vehicles 3 pickup truck 10 (2012 F250 with 27,000 miles on it) which is used by station s based upon age. Also replace truck 23 (2000 with 22,000 miles on it) a digger based upon age and maintenance. ME 111111 INS III I HE I 0 m 7 0. DEPARTMENT: ;MIS PROJECT LOCATION: (Town Hall, 6 Park Row, Mansfield, MA 02048 C PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: of town's historical records - Police Department (Priority 3 This is a consecutive phase of the town's initiative to convert all paper documents and records into digital format. Currently, the large amount of the documentation of Public Health, Conservation and Town Clerk's departments is readily available in digital form and all public records are accessible via the town's website. inn this next phase, we request that the Police department's records are also converted accordingly. ,ahcaNaT i , � f C DEPARTMENT: DPW PubBldgs/SpecProj PROJECT LOCATION: (MUNICIPAL COMPLEX PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: 13 Shed Feasibility Study & Cost Study existing Salt Shed at Fruit Street does not have sufficient capacity (900 tons) and olicates winter operations based on its location and size. It would be used as ional storage capacity for difficult winters. Feasibility Study would determine the best location within the Municipal Complex to construct a new 3,000 Ton Salt Shed with a Brine Building, especially looking at s within the ACEC Area. The Study would provide a preliminary site plan, urinary building design, cost estimates, and a good overall picture of what is needed QrC\NCI ITT-..,. o=s 4 DEPARTMENT: DPW-PubBldgs/SpecProj j PROJECT LOCATION: (Municipal Complex PROJECT: DESCRIPTION: Salt Shed Municipal Complex 13 This is an estimated amount of funding that will be required to construct a new Salt Shed at the Municipal Complex. In the initial plan this was part of the project but removed and requested that it be brought to CIP Committee at a later date. E FISCAL YEAR: FY2025. PROJECT COST: $13,000,000.00 PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: Loan Order Building 130 years QcC1NCi �/r r. DEPARTMENT: DPW- Pub Bldgs/SpecPr9i PROJECT LOCATION: (Library/COA PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: JN[PROVEMENT LIFE: Replace Carpet (Phased Approach Throughout Building) 3 is to do a phased approach to replace carpet in the Library much of which is 30+ old. FY2025 $1100,000.00 !Free Cash (Unreserved Fund Bal) Buildings !20 years .T FCINCY �➢)� is DEPARTMENT: ;DPW-PubBldgs/SpecProj PROJECT LOCATION: (Library/COA PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: ,IMPROVEMENT LIFE: 13- Fan Coil Units, Debont System and Outdoor Condensing Units is to replace Fan Coil units and Liebont Systems at Library/COA and exterior ensin¢ units. FY2025 $185,000.00 FY25 Operating Budget IEquipment _ (20 years o -Ste DEPARTMENT: iDPW-PubB1dgs/SpecProj PROJECT LOCATION: ILibrary/COA PROJECT: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: ,IMPROVEMENT LIFE: Remove and Replace Roof (EDPM) and Shingle Roof 13 is to replace the shingle & EDPM roofing systems at the Library/COA. The M is original to the buildings and the shingle portion was done in 1996 after a ifacturer defect. Q / U Y NSA DEPARTMENT: DPW-Pub6ldgs/SpecProj j PROJECT LOCATION: (Library/COA PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: ~IMPROVEMENT LIFE: Ceiling Painting 13 1 is for various ceiling and some wall painting at Library and COA. e i DEPARTMENT: jDPW-PubBldgs/SpecProj PROJECT LOCATION: (North Common PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: 13 is to build Pergola at the North Common in the area of the flag pole. This area prepared for a Pergola when the project was done a number of years ago. FY2025 $110,000.00 (Free Cash (Unreserved Fund Bal.) Buildings 130 years C r � d - NtF�A1 A0,K `� DEPARTMENT: (DPW-PubBldgs/SpecProj PROJECT LOCATION: (Fruit Street Salt Shed PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: Salt Shed Roof Replacement 13 is to replace the roofing system on the existing salt shed that was constructed in which will just be shy of 30 years old at time of funding. z a r o ¢ - oP DEPARTMENT. ,POLICE r PROJECT: PRIORITY: DESCRIPTION: PROJECT LOCATION: (POLICE DEPARTMENT PHASE I BODY CAMERAS The Town of Mansfield Police Department will be exploring the purchase and use of Officer worn body cameras in the coming years. This is due to the high liability associated with the profession and the advent of easy to use cameras. It is an unfortunate by-product of the profession that complaints and uses of force incidents occur frequently. The cameras, when coupled with the existing cruiser cameras provide a ready source of firsthand evidence of the incidents. They help insulate the police department, officers, and community from civil liability while supporting transparency, and engendering trust in the community. FISCAL YEAR: (FY2025 PROJECT COST: $150,000.00 PROPOSED FINANCING: EXPLANATION: ,IMPROVEMENT LIFE: 1FY25 Operating Budget Equipment 15.years .. .� DEPARTMENT: POLICE PROJECT LOCATION: (POLICE DEPARTMENT PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: PHASE II BODY CAMERAS 13 Town of Mansfield Police Department will be exploring the purchase use of Officer worn body cameras in the coming years. This is due to the 1 liability associated with the profession and the advent of easy to use aeras. It is an unfortunate by-product of the profession that complaints and s of force incidents occur frequently. The cameras, when coupled with the ;ting cruiser cameras provide a ready source of firsthand evidence of the dents. They help insulate the police department, officers, and community n civil liability while supporting transparency, and engendering trust in community. FY2025 $150,000.00 J �FY25 Operating Budget Equipment j �5_years 'QP�c�Ncr�i�� o a i r DEPARTMENT. Fire Department ' p PROJECT LOCATION: East Street Station PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: Rescue 34 replacement Rescue 34 Rescue 34 is a 2010 Ford E450, Road Rescue ambulance with over 120,000 miles. This vehicle has had work done in the last few years but has not been in need of significant service. Typically, however, as age and usage increases and the mileage approaches or exceeds one hundred thousand, cost of repairs increases dramatically along with the possibility of catastrophic failure. During FY25 the mileage will exceed this milestone. Other items within the ambulance will also reaching the end of their life cycle. The purchase of an new ambulance continues to provide us with two ambulances in good working order and continue to maintain a third which, despite significant mileage, will serve as the reserve. Included in the cost of the ambulance will be a power cot with loading system, a Cardiac Monitor and a Lucas machine. The timing of this purchase remains right in line with the original ambulance revolving account schedule, established at town meeting in 2011 for this explicit purpose. The cost of replacing Rescue 34 and several key pieces of equipment is estimated to be at $350,000. FY2025 $ 350,000 Free Cash/Ambulance Revolving Vehicles 5 years DEPARTMENT: Fire Department PROJECT LOCATION: 500 East St. Public Safety Complex PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: r,IMPROVEMENT LIFE: Car two replacement 3 Car Two Car Two is a 2011 Ford Expedition, SUV with just growing mileage. This vehicle has served as the Deputy Chiefs vehicle, responding to emergency incidents on a daily basis. Car Two has been very dependable but will be fourteen years old upon replacement in fy25. The cost of replacing Car one is estimated to be at $50,000. WK13011 $ 50,000 Free Cash (Unreserved Fund Bal.) Vehicles 5 years Q l" O C, PNt lh "' 'VDEPARTMENT: Fire Department PROJECT LOCATION: 500 East St. Public Safety Complex PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: Car three replacement 3 Car Three Car Three is a 2011Ford Explorer, SUV with growing mileage. This vehicle has served as a fire prevention vehicle, responding to emergency incidents and is out on the road for inspections on a daily basis. Car Three has been very dependable but will be fourteen years old upon replacement in fy25. The cost of replacing Car Three is estimated to be at $50,000. FY2025 $ 50,000 Free Cash (Unreserved Fund Bal.) Vehicles 5 years L r r �01NOT )i>� 2 ,' onsnorv. DEPARTMENT: Fire Department PROJECT LOCATION: 500 East St. Public Safety Complex PROJECT: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: ,IMPROVEMENT LIFE: Car Four replacement 3 Car Four Car Four is a 2011 Ford Explorer,purchased at the same time as C2 and C3, and with growing mileage. This vehicle has served as a fire prevention vehicle, responding to emergency incidents and is out on the road for inspections on a daily basis. Car Four has also been very dependable but will be fourteen years old upon replacement in FY25. The cost of replacing Car four is estimated to be at $50,000. FY2025 $ 50,000 Free Cash (Unreserved Fund Bal.) Vehicles 5 years r o. SAos DEPARTMENT: Fire Department PROJECT LOCATION: East Street Station PROJECT: PRIORITY: 2 Vehicle Extrication tools DESCRIPTION: Vehicle Extrication Tools are used in motor vehicle accidents, forced entry into buildings and incidents involving industrial machinery. With the purchase of new vehicles and a regional grant in FY20, the need for the replacement of multiple sets of this equipment has diminished. FY25 will require the purchase of one full sets of jaws of life along with various other parts of the extrication packages such as the replacement of air bags that lift vehicles, cribbing, hand tools and a hydraulic generator. The cost is estimated to be $93,600. FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: )IMPROVEMENT LIFE: FY2025 $ 93,600 Free Cash (Unreserved Fund Bal.) Equipment 10 years 2 0. n � � o�Nf �As N\s DEPARTMENT: Mansfield Schools PROJECT LOCATION: 'lQualters Middle School PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: (IMPROVEMENT LIFE: iPriority 3 Roof repair expense is continuing to climb, and the roof will be at the end of the useful life. This project is likely to be eligible for reimbursement from the Mass. School Building Authority. FY2025 $11,800,000.00 (Loan Order Buildings 120 years OAR AoDEPARTMENT: Mansfield Schools PROJECT: PRIORITY: DESCRIPTION: PROJECT LOCATION: (District -Wide Bathroom Renovations (Priority 3 ject Overview: s request was made to CIP in the fall of 2017 but was deferred. School bathrooms aging and need to be renovated. Update fixtures and furnishings to be more lent friendly. Update the floor to make it more efficient to clean. FISCAL YEAR: FY2025 PROJECT COST: $1100,000 PROPOSED FINANCING: EXPLANATION: ,IMPROVEMENT LIFE: IFree Cash (Unreserved Fund Bal.) 1 (Building 120 years I i o n o C, a DEPARTMENT: 'DPW -Highway Division _4 PROJECT LOCATION: 'Various PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: and Parking Lot Maintenance Urgent These funds are used in conjunction with Chapter 90 State Aid ($750,000+-) to maintain and/or reconstruct roadways, sidewalks, bridges and parking lots. examples of this work would be: Crack -sealing, trench repair, chip -sealing, overlays, milling and overlay, full depth reconstruction, handicap ramp reconstruction, sidewalk repairs, sidewalk replacement, bridge repairs, bridge replacement design and all work associated with the above. urgency here is that when not properly funded like years past, our roadway structure continues to deteriorate and minor repairs become reconstruction. Current averaged cost per square yard for various levels of work; Cost per mile of road at 24' wide $23,936.00 $80,960.00 $160,512.00 $247,808.00 $316,000.00 $542,080.00 $633,600.00 list above is in the order that a road would deteriorate and our cost to repair would FY2025 $13,000,000.00 j Loan Order Infrastructure � 10 years Per SQ. YD. Patch and Crack -seal $1.70 Chip -seal $5.75 Thin overlay $11.40 Mill and Overlay Local $17.60 Mill and Overlay Arterial Collector $22.50 Reclaim Local $38.50 Reclaim Arterial Collector $45.00 Cost per mile of road at 24' wide $23,936.00 $80,960.00 $160,512.00 $247,808.00 $316,000.00 $542,080.00 $633,600.00 list above is in the order that a road would deteriorate and our cost to repair would FY2025 $13,000,000.00 j Loan Order Infrastructure � 10 years o , PNt S\4 DEPARTMENT: DPW -Sewer Division PROJECT LOCATION: (Sewer Improvements PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: Sewer Collection System Improvements 3 are proposing to annually fund sewer collection system improvements. This may sde sewer line replacement or rehabilitation or pump station improvements. If e funds are not fully spent in a given fiscal year they can be combined with another to complete a larger project. I FY2025 $ 200,000.00 Sewer Retained Eamings j [Other - 1 0 Other10 years DEPARTMENT: DPW -Water Division PROJECT LOCATION: Gilbert St. from West St. to Walsh WTP PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: AC Water Main Replacement 3 8,500 feet of six-inch AC water main pipe in Gilbert St. with 12" DI pipe in West Street to the 12" water main at the Walsh Treatment Plant ! FY2025 $11, 40 0,0 00 Loan Order,_ Infrastructure 150 l 4� 'ONCY DEPARTMENT: IDPW-Water Division PROJECT LOCATION: (Water Division Fleet - 500b East St. PROJECT: PRIORITY: DESCRIPTION: FISCAL YEAR: PROJECT COST: PROPOSED FINANCING: EXPLANATION: IMPROVEMENT LIFE: Vehicle Replacement (1) one (1) new pick up truck with plow for the Water Division fleet. fleet vehicles will replace one older model truck with high mileage: Vehicle #65 - 2014 Chevrolet Silveradc,