HomeMy WebLinkAboutPenney Engineering Inc. - 7/27/1993P Eli N EY ENGINEERING, INC
Environmental Engineers
July 27, 1993
Mr. Marcel Boelitz
DEP - SOUTHEAST REGIONAL OFFICE
20 Riverside Drive
Lakeville, MA 02347
(508) 946-2862
RE: Hatheway & Patterson Company, Inc.
DEP Site No. 4-0571
Progress Report for June, 1993
Dear Mr. Boelitz:
This progress report is intended to update the Department on the activities involved in
the performance of the Supplemental Phase II Comprehensive Site Assessment and
the Interim Measure assessment being conducted by Penney Engineering at the
Hatheway & Patterson site.
Interim Measure Assessment
A limited test pitting program was conducted in accordance with the February 23, 1993
Interim Measure Proposal by Penney which was conditionally approved by the
Department in a letter dated March 10, 1993. A series of test pits were excavated at
the site on June 24, 1993 using a backhoe operated by Swanson Excavating
Contractors of Walpole, MA under the supervision of Penney personnel. The test pit
locations will be plotted on an Interim Measure Plan which will be submitted with the
Interim Measure Design report upon completion. The two objectives addressed by the
test pitting program were:
1. To assess the extent of free -phase oil floating on the groundwater east of wells
MW-6 and MW-12; and
2. To determine whether the plywood barrier installed along the eastern bank of the
Rumford River in 1974 is preventing the free migration of floating product to the
existing STM.
In order to accomplish the first objective, eight test pits (TP-1 through TP-8) were
excavated on the southern portion of the site, generally south and east of the bedrock
outcrop. Observation wells OW-8, OW-9 and OW-10 were installed in test pits TP-1,
125 High Street, Mansfield, MA 02048 (508) 261-1288 FAX (508) 261-1208
Recycled Paper
Mr. Boelitz
July 27, 1993
Page 2
TP-7 and TP-8, respectively. The observation wells consisted of ten -foot lengths of
four -inch, perforated PVC drain pipe, with a series of 5/8-inch holes placed
approximately 1 1/2 inches apart along the length of the pipe. The observation wells
were installed in order to measure groundwater elevations and to monitor the presence
of any floating oil. Evidence of residual oil contamination was encountered in the
subsurface soils below a depth of approximately five feet in test pits TP-1, TP-5, TP-6,
TP-7 and TP-8. Shallow bedrock was encountered in TP-3, TPA TP-5 and TP-6,
preventing observations of the groundwater at those locations.
In order to accomplish the second objective of the test pitting program, three test pits
(TP-9, TP-10 and TP-11) were excavated along the eastern side of the Rumford River.
Each of the test pits consisted of a trench excavated perpendicular to the suspected
location of the plywood barrier. Once the plywood barrier was located, a test pit was
excavated on the eastern side of the barrier. A test pit was also excavated on the west
side of the barrier at TP-11.
Evidence of residual oil contamination on the soil was detected in test pits TP-9 and
TP-11. Observation wells OW-11 and OW-12 were installed in TP-9 and TP-11,
respectively. No evidence of residual oil contamination was detected in the soils in test
pit TP-10 and no floating product was observed on the groundwater at that location.
Therefore, no observation well was installed at location TP-10.
Upon excavation, the interior of each test pit was measured and observed. The
subsurface conditions encountered were logged in the field and soils were described
using a modified Unified Soils Classification System. Test pit logs were prepared and
will be presented in the Interim Measure Design report. Soil samples were collected at
various depths at each location and field screened for the presence of TVOCs using an
OVM. The results of field screening were recorded on the test pit logs.
During the excavation visibly contaminated soils were segregated from visibly clean
soils. Care was taken during backfilling to return the excavated materials to their
interval of origin. Observation wells were placed in selected test pit excavations upon
completion, and backfilled with the native material.
The newly installed observation wells were surveyed for vertical elevation, gauged for
water levels and assessed for the presence of free -phase floating product as described
in the following sections. The results of those activities are summarized in Table 1.
Seven groundwater observation wells (OW-1 through OW-7) were installed on June 22,
1993 by Penney within the wetlands south of MW-12. The wells were composed of
approximately five-foot lengths of four -inch, perforated PVC drain pipe and were
installed with the aid of a spade and post hole tool to a minimum depth of 24 inches.
Perforations consisted of a series of 5/8-inch diameter holes located approximately 1
PENNEY ENGINEERING, INC
Mr. Boelitz
July 27, 1993
Page 3
1/21, apart along the length of the pipe. Wells OW-1 through OW-4 were placed
immediately surrounding the visibly affected area of oil breakout south of MW-12. Well
OW-5 was placed approximately 50 feet downgradient of the breakout area. Well OW-
6 was placed south of well MW-10 to determine groundwater topography in that area.
Well OW-7 was placed inside the wetlands edge east of the breakout area.
The locations of the observation wells will be plotted on an Interim Measure Plan which
will be submitted with the Interim Measure Design report upon completion._ The wells
were intended to determine the extent of free -phase oil on the groundwater within the
wetlands south of MW-12. Subsequent well gauging conducted on July 21 found all
seven observation wells to be dry.
Supplemental Phase II Activities
Survey
An instrument survey was performed on July 2, 1993 in order to determine the
elevations of the measuring points for all site monitoring wells, observation wells,
piezometers, sumps and river gauging stations. With the exception of MW-1, the
elevation of a marked location on the top of the PVC riser pipe in each monitoring well
and piezometer was measured. The elevation of MW-1 was measured to the lip of the
inner protective gate box. Measuring points were marked on each of the observation
wells and sumps.
The vertical datum used in the survey was a square chisel cut on the granite bridge
abutment at the spillway. The elevation of the benchmark had been previously
established by Guerard Survey at 170.99 feet above the National Geodetic Vertical
Datum (NGVD) of 1929. All elevations have been referenced to the established
vertical datum. The elevations, recorded to the nearest 0.01 foot, are presented in
Table 1. The survey was completed in a manner which closed on the original
benchmark.
Well Gauging
Well gauging activities were conducted at the site on July 21, 1993. The depth to water
was measured relative to the surveyed measuring point of each monitoring well,
observation well, piezometer and sump and recorded to the nearest 0.01 foot. The
water levels were determined using an electronic water level indicator. Upon
completion of the water level measurements, selected locations were assessed for the
presence of free -phase floating product. A disposable, polyethylene bailer was
lowered to approximately one-half its length into the water table and retrieved for
inspection. The results of the water level measurements and floating product
assessment are presented in Table 1.
PENNEY ENGINEERING, INC
Mr. Boelitz
July 27, 1993
Page 4
TABLE 1
WELL GAUGING RESULTS
Measuring Point
Depth to
Groundwater
Free -Phase
Location
va io
Groundwater
Elevation
Oil (inches)
MW-1
172.00
9.84
162.16
MW-2
175.74
10.82
164.92
sheen
MW-3
174.15
11.40
162.75
none
MW-4
174.52
10.00
164.52
MW-5A
173.15
10.65
162.50
none
MW-513
172.55
10.05
162.50
MW-6
172.76
10.51
162.25
film
MW-7A
171.50
11.58
159.92
film
MW-713
169.48
9.78
159.70
MW-8A
173.05
13.05
160.00
none
MW-86
173.64
13.59
160.05
MW-9A
173.05
13.47
159.58
MW-96
173.05
12.92
160.13
MW-10
165.95
6.45
159.50
MW-11
174.06
9.25
164.81
MW-12
171.73
12.15
159.58
film
PW-1
170.25
10.70
159.55
OW-1
162.47
---
OW-2
162.26
---
OW-3
162.55
OW-4
163.86
-
-
OW-5
162.13
-
-
OW-6
161.55
--
-
OW-7
162.24
-
-
OW-8
169.12
9.66
159.46
OW-9
170.91
8.95
161.96
film
OW-10
170.72
-
-
OW-11
168.79
9.02
159.77
none
OW-12
170.56
11.47
159.09
film
P-1
174.44
13.99
160.45
P-2
177.07
13.07
164.00
P-3
170.60
11.35
159.25
none
P-4
169.02
9.87
159.15
none
P-5
165.21
6.08
159.13
none
OSA
165.02
5.87
15915
none
OS-2
165.41
6.27
159.14
none
STM Recovery Sump
164.97
5.85
159.12
sheen
Recovery Well #1
170.50
8.71
161.79
none
Recovery Well M-1
171.63
9.06
162.57
film
Rumford River #1
171.82
6.79
165.03
Rumford River #2
171.71
7.30
164.41
River Gauge
158.89
0.30
158.59
Mr. Boelitz
July 27, 1993
Page 5
Summary
During the month of June, 1993, Penney conducted field investigations as part of the
Supplemental Phase II Comprehensive Site Assessment and the Interim Measure
Assessment required at the site. These activities included the completion of a test
pitting program, an instrument survey and a complete round of well gauging. The
activities performed relative to the Interim Measure will be fully described in an Interim
Measure Design report which will be submitted to the Department shortly. The report
will include a plan showing the test pit and observation well locations.
We will continue to keep your office informed of the progress of the Phase II
assessment and the Proposed Interim Measure activities. Please call us if you have
any questions.
Yours truly,
PENNEY ENGINEERING, INC
Paul D. Vigeant Ralph P. Penney, PE
Staff Scientist President
cc: Hathaway and Patterson
Mansfield Board of Health
Mansfield Conservation Commission