HomeMy WebLinkAboutCONSERVATIONminutes10202008-20081119190609
Conservation Meeting
October 20, 2008
Present: Joseph Mulkern, Chair; Paul Boyden, Vice Chair; Jack Smith; Carole Matthew;
Michele Grenier, Conservation and Environmental Planner.
11. Meeting called to .order at7:04 pm.
2. Request for a Certiflcateof Compliance: Michael Baldasarre, 103 Elyse
Road -#211-0815 .
The Notice of Intent was filed in April 2008 for the construction of an in-ground pool
with a patio around the pool with fencing and landscaping. A portion of the project was
located in a Natural Heritage are of endangered and lor special concern species.
Michele told the Commission everything has been done according to the plan submitted
and she recommends a Certificate of Compliance be issued.
Paul would like Michele to take pictures.
Approved 4-0.
Hearing ended at 7:06 pm
1.3. Request for Determination of Applicability: Mass Highway Department.
Thomas McGuire and William Travers were present.
The proposed project will begin at the North Attleborough town line and will run
northerly to the Mansfield/Foxborough line. The major wetland crossing is the Wading
River. Work will include asphalt milling to a depth of 1% inch, resurfacing with 1% inch
of asphalt, reflective paving markers, repairing shoulders and medians, selective clearing
and thinning of trees and vegetation along the edge of the road to re-establish vehicle
recovery zones and for sight distance/visibility of signs. Tom told the Commission the
trees have not been trimmed in 20 years due to the reduction of the work force.
Guardrails will be repaired or replaced as needed.
Paul asked where the funding for the work would come from. Tom told him the project
would be 90% federally funded with 10% coming from the state. This is a 7 million
dollar project. The work would start next summer.
Michele rode with Mass Highway along the areas of work and the only area of concern is
around the brook. Sedimentation control, consisting of hay bales and/or silt fence, will
be placed and inspected by Michele. All the work will occur within the existing roadway.
Paul made the motion to accept the proposal for the pavement milling and resurfacing
of Route 1-95 from the North Attleborough town line to the Foxborough town line and to
issue a Negative 3 Determination. Siltation/hay bales will be placed as needed and
inspected by Michele.
Jack seconded.
Passed 4-0.
Hearing ended at 7: 13 pm
.4. Request for Determination of Applicability: Cynthia Hobbs-Barrett, 16.
Shannon Lane. .
Steve Rumba, Collins Civil Engineering Group was present.
The RDA was filed for the up-grade of a residential septic system within the 100 ft.
buffer of bordering vegetated wetlands.
The new leaching field will be in the front of the house on existing lawn outside the 100
ft. buffer zone. Existing plumbing will remain in the back of the house and connect to
the new tank ("0" box), to be installed outside the 50 ft. A new plumbing pipe will wrap
around to the front to the new field. Only work in the buffer zone will bethe trenching
for the new pipe. Silt fence will be installed around the work limit. The wetland line has
been properly delineated.
Jack made the motion to accept the plan for 16 Shannon Lane as submitted, dated
September 13, 2008, and to issue a Negative 3 Determination. Siltation/hay bales at
the limit of work will be installed and inspected by Michele.
Paul seconded.
Passed 4-0.
Hearing ended at 7:26 pm.
5. Amendment to an existing Order of Conditions:. Charles Sylvia. & Glen
Christi no, 5 LakeviewAvE!nue - #211-0770. .
Charles Sylvia, the homeowner was present. The amendment to the Order of
Conditions, dated July 14, 2006, is to enable Mr. Sylvia to build a dock and repair a
stone wall on the property.
Michele told the Commission the house is complete and the plantings Conservation
requested are done.
Carole wondered if the amendment would be good for 3 years or if it would follow the
time frame of the Order of Conditions. Michele said the amendment would only be good
until the current Order of Conditions runs out. Only an extension of an Order allows
more time.
2
Michele spoke to Heidi Davis about the proper way to handle the amendment; a plan
should be attached with a letter to the Order of Conditions stating the Commission
approved the amendment.
Michele thanked Mr. Sylvia for coming forward about the dock because she has found
numerous docks on the lake that were never permitted.
Paul asked Mr. Sylvia to use plastic decking instead of pressure-treated lumber. He told
Mr. Sylvia he would need to submit an as built when the work is completed.
Paul made the motion to accept the amendment to the Order of Conditions for 5
Lakeview Avenue, plan revised 10/14/2008, referencing the word dock. Michele will
write a letter to be attached to the file along with an inspection schedule; Mr. Sylvia is to
keep Michele apprised of the work. An as built will need to be submitted before a
Certificate of Compliance can be issued.
Jack seconded.
Passed 4-0.
Hearing ended at 7:37 pm.
16.. Notice ofIntent:.DavidDiamolld,>1910IdElm Street
I
Liz Dupre of Clear Water Environmental and David Diamond, the homeowner, were
present.
The Notice of Intent was filed for the replacement of a septic system within the 100 ft.
buffer of bordering vegetated wetlands.
The new system will be on the existing lawn. Michele recommends issuance of the
Order of Conditions with a hay bale line.
A Jet System, consisting of an advanced treatment tank, a pump chamber, an on-site
subsurface sewage distribution system and associated piping and grading, has been
approved by the Board of Health.
Wetlands were delineated by Engineering Consultants, Inc.
Paul made the motion to accept the plan for replacement of the septic system at 191
Old Elm Street as submitted with a silt fence/hay bale line to be inspected by Michele.
Carole seconded.
Passed 4-0.
Hearing ended at 7:20 pm.
7. Notice of Intent: Perry DiMascio, Williams Street - forest Heights - #211-
0822.. .
Ralph Maloon, RIM Engineering, and Stan Feck, the applicant, were present.
3
Also present: Michelle Busharis, 175 Tremont Street, an abutter.
The Notice of Intent was filed for a drainage system and two drainage discharge
locations to be located within the 100 ft. buffer of bordering vegetated wetlands. The
drainage will be for a cluster housing development.
Michele walked the wetland line on June 1, 2008 and found it to be accurate. The
proposed roadway is located outside the 100 ft. buffer zone. Any lots located within the
100 ft. buffer will have to have a separate filing.
A drainage system will be located on the north side of Williams Street and east of
Robinson Pond. There is a wetland on an abutting property to the east of this property
but will not effect the roadway. The roadway will also be at least 200 ft. away from the
pond. The drainage will be parallel to Williams Street. There will be an outlet, a gravel
swale, down by Robinson Pond. Michele asked Ralph to re-design the outlet because a
portion was over the BVW line. The swale has now been pulled out of the wetlands.
New plans have been submitted.
The swale and a retention basin will be constructed outside the 50 ft. The swale and
retention basin are necessary because the town will not allow the applicant to use the
drainage system on Williams Street for surface water. The surface water will flow off
the hill, be picked up by the swale and then drained into a small retention area. The
swale and retention area will be constructed to control the balance of flow to Robinson
Pond.
Ralph told the Commission they have been to the Planning Board twice and will meet
with them October 22, 2008.
Paul wondered about stormwater management. Ralph said the project would have a
deep sump and oil/water separators. Michele said the application complies with the
stormwater regulations. She also said John Sullivan has reviewed the plans.
Ralph told the Commission if the area for the cluster development is 35%, you no longer
have to comply with item #3, TSS removal, or item #4, ground water recharge, but you
still have to comply with no more water leaving the site than at the pre-development
stage. This project is over 35%; it is about 38%-40%.
Michele Busharis, a Tremont Street resident was concerned about the water flowing in
the back of the property. Ralph said there will be a 100 ft. buffer around the
development and the swale will take care of the water. No work is proposed in the
Tremont Street area.
Jack made the motion to accept the plans as shown, revised October 20, 2008.
Paul seconded.
Passed 4-0
Hearing ended at 8:10 pm.
4
Is. New Business
Maple Street Conservation Land: A letter was received from Lorilee Fish, the Parks
and Recreation Director, regarding the Maple Park Trails. She told the Commission this
is a beautiful, peaceful area that is under-utilized.
She suggested that the mapping and improvements to the trail/roads in Maple Park
would make a great Eagle Scout project or Gold Award Project for the Girl Scouts. She
has offered her time and assistance with this project.
She told the Commission she was concerned about fire pits in the area, a situation that
needs to be addressed. She walked the property with Don Tebeau, from the Fire
Department.
Paul thought the work could be done by students from the high school and middle
school and by cub scouts and the brownies.
(8:15 pm)
NRT Discussion: Stephen Holford, President of NRT, Colin Cauldwell, Lou Andrews,
Leonard Flynn, members of NRT and Marc Marcussen of 25 Keefe Lane, an abutter to
NRT land were present.
This was a reported potential wetland violation at 69 Charles Street. It was reported
that wetlands had been filled in, heavy equipment was being stored on the property and
the land had been cleared by the homeowner at 69 Charles Street.
In 2004, Lou Andrews told the Commission it was brought to the attention of NRT that
there was an encroachment on NRT land in the rear of 69 Charles Street. Mr. Andrews
and Mr. Flynn went out to the property and found that work had been done; filling and
basic construction had been done. A pile of fill had also been placed close to a wetland
on NRT land. Basically, it was determined Mr. D'Ambra was trespassing on NRT land;
Mr. Cauldwell and Mr. Andrews visited the property and did some measurements from
the marker on the property and determined Mr. D'Ambra had encroached on the
property. They notified Mr. D'Ambra and he promised to remedy the situation. The
property was visited again a week later and it looked as if Mr. D'ambra was taking care
of the problem.
Conservation received a complaint in 2008 from Marc Marcussen of 25 Keefe Lane, who
also abuts NRT land. Mr. Marcussen witnessed the work and the equipment used to
grade and fill the lot Again, Mr. Cauldwell and Mr. Flynn roughed out the dimensions of
the property and it looked as if Mr. D'Ambra had cleared 60 to 75 ft. of NRT land. In
addition, fill material had recently been placed on the site; the area has not grown back.
The pile of fill from 2004 had been removed; Colin said he was not sure if it had been
removed from the property or pushed into the wetlands. Trees have also been
removed. Mr. Cauldwell told the Commission "we are concerned that it is NRT land and
we don't want people violating the property by filling in wetlands and cutting trees. NRT
would like the historical wetland line determined and the wetlands restored." Mr.
Cauldwell would like a planting scheme to be submitted.
5
Michele said she, Cindy, Paul and Joe looked at the property and found no violations;
the wetlands had not been filled in and she did not think trees had been cut. Mapping
from 8 years ago by GIS was viewed; the yard has not changed in 8 years. Michele said
she also talked to John Sullivan and Rick Alves about the property. Mr. D'Ambra said he
had not filled wetlands.
Joe said Mr. D'Ambra was told to stop cutting and mowing the NRT land and Paul
recommended Mr. D'Ambra have his property surveyed (define the back property line
only) and then put up a fence. Joe said Mr. D'Ambra realized he was encroaching on
the property.
Carole said this is the first time she has heard anything about a fence. She said it is not
right for certain people on the board to make decisions. It should be discussed as a
board.
In regards to the changes on the property, Mr. Cauldwell said: "It certainly has changed
because the maps are different. There is material on 1 map that does not show on the
other map. Mr. Cauldwell reminded the Commission about 2 cases that occurred when
he was on the board that are similar to this property. 40 Grove Street: Mr. Fontanini
was issued an enforcement order in June 2006 for filling wetlands and working within
100 ft. of a vernal pool. He was required to hire a Professional Wetland Scientist to
determine the original/historic wetland line. He was required to remove the fill and
restore the wetlands and replant. 95 York Road: Michael Atwill had inadvertently
cleared 79 trees within the 100 ft. buffer zone of bordering vegetated wetlands and
Blake's Pond, altering 8,000 sq ft. of wetland. 18,000 sq. ft. was replanted with trees,
bushes, ferns. Both property owners were required to have the property surveyed,
restore/replant, install fencing and add signage to the property.
Mr. Cauldwell told the Commission trees have been removed and potentially some fill
material has been placed in the wetlands. "At the very least, it is work within the 100 ft.
buffer. It has been over time this has been done, but in a couple of cases I have cited,
it did not stop the Commission from requiring remediation by the person who did it.
The remediation will have to take place on our property. NRT will want to be involved,
have some input."
Mr. Cau/dwell: "In Mr. Fontanini's case, the Commission had pictures and we did not
take his word; he adamantly said he never filled wetlands. Mr. Fontanini had pictures
and aerial views and the Commission still asked for soil samples."
Mr. Cauldwell reminded the Commission that in the past when there has been a
compliant concerning a wetland violation, an enforcement order has been issued, the
violating party has been brought before the board and told what they need to do to
correct the violation. "At the very least, Mr. D'Ambra is working in the buffer zone.
Conservation has jurisdiction. He has cut trees in the buffer zone, whether it is in the
25 ft. or the 50 ft."
6
Mr. Cauldwell said the historical map shows that Mr. D'Ambra has worked in the buffer.
It shows he worked within the wetland and potentially filled the wetlands. He told the
Commission he saw fill material; it was cheap fill, not fill that would have been on the
property naturally.
Mr. Cauldwell would like Mr. D'Ambra to have a soil evaluation done to find the extend
of the encroachment; he would like this handled the same way Grove Street and York
Road were handled.
Carole asked if soil samples were taken when Michele, Cindy, Joe and Paul visited the
property. Michele said samples were taken but not when they were all there, that she
had gone back to take the samples. She said she would do them again.
Carole feels Mr. D'Ambra should have been brought in for a hearing. She thinks Michele
should go out with the auger and take samples and then have NRT and Mr. D'Ambra
come back before the board.
Mr. Flynn said he had talked to Michele and she said she had talked to John Sullivan,
Town Engineer. When Mr. Flynn asked Mr. Sullivan, he said he had not had a discussion
concerning 69 Charles Street with Michele. Michele said it was Rick Alves. Mr. Flynn
said Rick told him the only discussion he had with Michele was how to read the scale on
the map; no discussion about the possible violation.
Mr. Flynn told the Commission NRT owns approximately 300 acres of which 246 acres
have conservation restrictions. "We take our stewardship responsibility very serious.
We make all our land open to the public. We have a very basic rule-'take nothing off it,
leave nothing on it and enjoy it'. It is a small lot with a small disturbance. If we let this
go, it sets a terrible precedence. It has to be acted upon seriously." Mr. Flynn said he
hoped it would not go this far. Gary D'Ambra never acknowledged the letter of 2008.
(He told the Commission he acknowledged the letter of 2004; he even went to Lou
Andrews's house to apologize, but apparently never stopped using the land).
Mr. Flynn said they would rather have avoided all this but because Gary D'Ambra did not
respond, NRT is left no recourse but to move forward with the case. Mr. Flynn also said
in Michele's response to NRT's letter, the issue that was raised was never addressed.
Joe: "We will call Mr. D'Ambra before the Commission with NRT if they want to attend
and discuss what the next step will be. We will request soil samples be taken."
(8:55)
I 9. Old Business
Lester Epstein, Maple Street, Map 40, Block 92.
Mr. Epstein was issued an Enforcement Order in October 2007 for filling in a certified
vernal pool, #1968.
7
A letter, dated October 15, 2008, was received from Brandon Moss of Murphy, Hesse,
Toomey & Lehane with a proposed restoration plan for the vernal pool located at Maple
Street, Map 40, Block 92.
Carole: "In the letter, dated October 15, 2008 from Brandon Moss, law office of town
council, not once is it mentioned that this is a certified vernal pool. It describes it as a
depression. The whole point of all this is a certified vernal pool has been filled in. The
word vernal pool is not mentioned once in the restoration plan." She would like any
reference to a depression changed to certified vernal pool with the identification #1968.
Paul would like to have the document re-worded to reference the vernal pool. Michele
said it is called a depression because at this time it is a depression; it is no longer a
vernal pool.
Joe would like #5 of the restoration plan to read "minimum" instead of "approximately"
15 to 20 yards of material.
Carole is also concerned about the vernal pool in the rear of the property. She feels it
should be certified. Paul would like this area examined to make sure it is in fact a vernal
pool. Michele told Carole the certification of the potential vernal pool in the back of the
property can be a requirement when the restoration is complete and the enforcement
order is lifted.
The Commission asked when the restoration can be done, if there is still time before the
end of this year. She said there is still time; it is better if it is done now and not in the
spring.
Minutes
110. Adjournment
Adjourned 9:15 pm. Carole/Paul.
Next Meeting - November 17, 2008.
~2L~
Josep Mulkern, Chairman
II-i)-OJ-
Date
8